HomeMy WebLinkAbout1.11 Fugutive dust planIILJVr Rust Constructors
Procedure Type
PROJECT SAFETY PLAN
CHEVRON Piceance Project
FUGITIVE DUST CONTROL PLAN
Revision No / Status
1 / AFU
Procedure No.
REC -06
Revision Date
16 December 07
Page
1 of 3
1.0 Purpose:
1.1
This Fugitive Dust Control Plan describes the general control measures to be taken by Rust
Constructors Inc. with all Subcontractors creating dust conditions to ensure that dust
suppression techniques are implemented to control fugitive dust sources during all
construction operations.
t2 Measures identified in this plan apply to work within the project area defined as the right -of-
way, access roads, temporary use areas, facilities and other areas used during
construction of the Project.
1.3 All Subcontractor personnel are to be thoroughly familiar with this plan and its contents prior
to initiating their construction activities on this Program.
2.0 Requirements for Dust Control
2.1 Each Subcontractor creating fugitive dust conditions is required to provide dust control
measures for all areas disturbed by construction. The measures addressed within this
section shall be required, as necessary, to control fugitive dust.
2.2 Dust control shall be implemented by each Subcontractor generating dust in areas of active
construction, within 500 feet of highways, residences, and power transmission rights -of -way
(unless waived by the owner /operator).
2.3 Dust control is required near roadways any time dust stays in the air for 5 minutes or
reaches 20 feet in height.
2.4 Dust control shall also be implemented on access roads, as determined by Rust
Constructors Inc., and as required by the Contractor for the health and safety of employees.
2.5 Dust control shall be achieved primarily through application of water or an approved dust
palliative. Application rates for the dust palliative will follow the manufacturer's
recommendations. All dust palliatives used shall be biodegradable. Use of salts with water
as a suppressant is limited to magnesium chloride (MC70).
3.0 Control of Unpaved Roads On -Site
3.1 During construction, operation, and maintenance of the project, each Subcontractor shall
control vehicle speed to minimize fugitive dust.
3.2 Each Subcontractor shall apply dust suppressants to the construction work area and access
roads at the request of Rust Constructors Inc., Client Representatives, the BLM, or county
or state representatives.
MAW Rust Constructors
Procedure Type
PROJECT SAFETY PLAN
CHEVRON Piceance Project
FUGITIVE DUST CONTROL PLAN
Revision No / Status
11AFU
Procedure No.
R EC -06
Revision Date
16 December 07
Page
2 of 3
3.3 Subcontractor shall employ control measures or operations procedures including but not
limited to, watering, chemical stabilization, road carpeting, paving, suggested speed
restrictions and other approved methods and techniques as required to maintain dust
control on unpaved roads.
4.0 Control of Paved Roads
4.1 Each Subcontractor shall implement the following requirements on paved roads:
a. Construction entrances shall be installed to prevent tracking mud and soil onto paved
roads. These entrances shall be constructed as required by county, state, or BLM
permits.
b. The Subcontractor shall clean any soil tracked onto a paved road that extends more
than 50 feet from the point of origin within one hour of discovery.
c. Any soil tracked onto a paved road that extends Tess than 50 feet shall be cleaned up by
the end of the working day.
d. Additional control measures or operational procedures may include but are not limited
to, covering the loaded haul truck, washing or otherwise treating the exterior of the
vehicle, limiting the size of the load and the vehicle speed, watering or treating the load
with chemical suppressants, and keeping the roadway access point free of materials that
may be carried onto the roadway and other approved methods and techniques as
required.
5.0 Control of Disturbed Areas On -Site
5.1 During construction, operation, and maintenance of the project, each Subcontractor will
suppress dust with application of water or other suppressant as needed, and will control
vehicle speed to 15 mph. All areas disturbed by construction will be revegetated in
accordance with the Client's Reclamation Plan.
5.2 Each Subcontractor shall apply dust suppressants to the construction work area and access
roads at the request of Rust Constructors Inc., Client Representatives, the BLM, and/or
county or state representatives.
5.3 Additional control measures or operational procedures for controlling dust during construction
activities may include but are not limited to, planting vegetation cover, providing synthetic
cover, furrows, and compacting, minimizing disturbed area in winter, wind breaks and other
approved methods and techniques as required.
RUSTRust Constructors
Procedure Type
PROJECT SAFETY PLAN
CHEVRON Piceance Project
FUGITIVE DUST CONTROL PLAN
Revision No / Status
1 / AFU
Procedure No.
R E C -0i6
Revision Date Page
16 December 07 3 of 3
6.0 Records
Records generated shall remain in site files until demobilization at which time they shall be retained
in Tong -term storage.
7.0 Referenced Forms
None
8.0 References
Colorado Department of Public Health and Environment (CDPHE) Air Pollution Control Division
(APCD)
Bureau of Land Management "Gold Book ", Fourth Edition, 2006
Garfield County Rules and Regulations