PROJECT INFORMATION AND STAFF COMMENTS
REQUEST Special Use Permit for work in the
Floodplain — Bank Stabilization
APPLICANT / OWNER Mark Gould
LOCATION 0200 Oak Lane — Westbank Ranch
Subdivision
SITE DATA 2.25 Acres
PARCEL ID NUMBER 2185-353-01-033
EXISTING ZONING RLSD — Residential Limited Suburban
Density
1. SITE LOCATION AND DESCRPTION:
Located in the Westbank Ranch Subdivision, South of Glenwood Springs access is
from CR 109, Lot 21 of the subject subdivision.
2. DEVELOPMENT PROPOSAL:
The applicant is proposing to construct adjudicated outlet features with bank
stabilization. The work will involve construction of two stream channels that will
route tailwater diverted from the Robertson Ditch. The diverted water from the
historic return flow channel that flows through the subject property near the upstream
property line will be put to use as water features on the site. The existing ditch water
that currently flows into the river will be split and routed through the property in
pipelines and lined open channel streams. The outfall locations of these streams at
the river embankment will be above the mean high water line and constructed with
select soil replacement matter and embedded rip rap. The site plan reflects only a
very small portion of the outfall locations will be in the floodplain. All other
proposed improvements will not be in the floodplain or the floodway.
3. APPLICABILITY:
Any use to be developed in the floodplain shall be required to obtain a Special Use
Permit, in accordance with the applicable regulations of Section 9 of this Zoning
Resolution concerning the submission and processing of such permits. In addition to
the determinations to be made by the Building Official under the provisions of said
1
Section 9, all applications for the Special Use Permit under this Regulation shall be
reviewed by the Floodplain Administrator.
4. REVIEW AGENCY AND OTHER COMMENTS:
This item has been referred to the US Army Corp of Engineers. Resource
Engineering, outside review agency for Staff, has also reviewed the application.
Below are the respective agency and outside review comments:
US Army Corp of Engineers: No comments received.
Resource Engineering: A 404 permit will not be required. Please see Exhibit H.
5. REVIEW CRITERIA
§6.08.01 Special Use Permit Required
(1) To assure that all necessary permits have been received from those governmental
agencies from which approval is required by Federal or State Law, including Section
404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C.
1344.
STAFF COMMENT: The applicant has stated that all proposed work will occur
above the mean high water (MHW) line without any encroachment or
disturbance below the MHW. There will be no placement of additional fill in the
floodplain. All work conducted above the MHW requires no Federal or State
Permits. Staff would conclude the applicant has submitted the proper material
showing that no further permits will be required by Federal or State Agencies.
(2) To determine whether proposed building sites will be reasonably safe from
flooding, and that the structure will be in compliance with the applicable provisions
for uses and standards for construction set forth in this Resolution.
STAFF COMMENT: There are no structures proposed in the floodplain. The
only work that will take place in the floodplain will be bank stabilization.
(3) To determine if the proposed development is located in the floodway. If located in
the floodway, assure that encroachment provisions of Section 6.09.01(1) (A) are met.
STAFF COMMENT: The applicant has submitted copies of the FEMA map
showing that no structure, building, bank stabilization or work is proposed in
the floodway.
(4) To assure that adjacent communities, the Colorado Water Conservation Board
and Federal Emergency Management Agency have been notified of the proposed
watercourse alteration or relocation.
2
STAFF COMMENT: A copy of the application to the District Court Water
Division 38 has been submitted, showing the applicant is applying for the tail
water adjudication and esthetic feature of the Robertson Ditch.
(5)To assure that the carrying capacity of the altered/relocated watercourse is
maintained. (A. 85-211) .09
STAFF COMMENT: The proposed bank stabilization will not increase the
carrying capacity of the Roaring Fork River, or affect the capacity of the
Robertson Tailwater Ditch.
6. SPECIAL USES AND STANDARDS FOR CONSTRUCTION
§6.09.02 Flood Fringe/Flood Prone Areas
(1) Prohibited Uses and Activities. The following uses and activities are prohibited in
the Flood Fringe/Flood Prone Areas:
(A) The development, use, fill, construction, substantial improvement or
alteration on or above any portion of the Flood Fringe or Flood Prone
Areas which alone, or cumulatively with other activities, would cause or
result in the danger of substantial solid debris being carried downstream
by floodwaters.
STAFF COMMENT: The purpose of this application is to improve the discharge
features of the river bank. By improving and stabilizing the bank, the amount of
solid debris carried downstream will decrease.
(B) The storage or processing of materials that in times of flooding is
buoyant, flammable, explosive or otherwise potentially injurious to
human, animal or plant life.
STAFF COMMENT: There will be no storing or processing of materials in the
floodplain.
(C) The disposal of garbage or other solid waste materials.
STAFF COMMENT: There will be no storage of garbage or solid waste.
(D) Any obstruction, which would adversely affect the efficiency of or
restrict the flow capacity of a designated floodplain so as to cause
foreseeable damage to others.
STAFF COMMENT: The intent and purpose of this application is to mitigate
any future problems in the floodplain outlet area.
3
(2) Permissible Uses. All Special Uses permitted in the Floodway, and all lawful uses
permitted by the underlying zoning, subject to Section 6.09.02(1) of this Regulation
and the regulations concerning the Special Use Permit, are permitted in the Flood
Fringe and Flood Prone Areas.
STAFF COMMENT: The applicant has submitted plans showing the FEMA
Floodway and the location of the proposed construction. No construction or
work will be in the Floodway.
(3) Performance Standards. The following performance standards must be met for
development in the Flood Fringe or Flood Prone Areas:
(A) The lowest floor, including basement, of any new or substantially
improved building designed for residential occupancy shall not be less
than one (1) foot above the maximum water elevation of the 100 Year
Flood.
STAFF COMMENT: There are no residential structures proposed.
(B) All new construction or substantial improvements shall be reasonably
safe from flooding.
STAFF COMMENT: The proposed bank stabilization is above the MHW mark
and should be reasonably safe from flooding.
(C) Any new construction or substantial improvement designed for
commercial or industrial uses shall either:
(i) Elevate the lowest floor level, including basement, to not less
than one (1) foot above the maximum water surface elevation of the
100 Year Flood; or
(ii) Provide flood proofing improvements so that below an
elevation of one (1) foot above the maximum water elevation of the
100 Year Flood, the structure, together with attendant utility and
sanitary facilities, is water tight with walls substantially
impermeable to the passage of water. Structural components shall
be capable of resisting hydrostatic and hydrodynamic loads and
effects of buoyancy. Evidence shall be submitted and certified by a
registered professional engineer or architect that the flood proofing
meets the standards as set forth herein.
4
STAFF COMMENT: No industrial or commercial uses are proposed.
(D) Any proposed development shall be reviewed by the Floodplain
Administrator to insure that the potential for flood damage by the 100
Year Flood is minimized, that all public utilities and facilities are located,
designed and constructed so as to minimize damage by the 100 Year Flood
and that adequate drainage is provided to reduce exposure to flood
hazards.
STAFF COMMENT: It is assumed this standard is for habitable areas. The
proposal is for rip rap bank stabilization that should mitigate some flood
hazards.
(E) All new construction or substantial improvements shall be designed
and adequately anchored to prevent flotation, collapse or lateral
movement, be constructed with materials and utility equipment resistant to
flood damage, and be constructed by methods that minimize flood damage.
STAFF COMMENT: The bank stabilization will increase the outlet feature's
ability to resist flood damage.
(F) New or replacement water supply systems and sanitary sewage
systems shall be designed so as to minimize or eliminate infiltration of
floodwaters. On-site individual sewage disposal systems shall be located
so as to avoid impairment of them or contamination from them during a
100 Year Flood.
STAFF COMMENT: No water supply or sewage systems are proposed.
(G) Within any area subject to sheet flow (Zone "AO" on the Flood
Insurance Rate Maps) all new construction and substantial improvements
of residential structures shall have the lowest floor, including basement,
elevated above the highest adjacent grade of the nearest street to or above
the depth number specified on the Flood Maps. Any new construction or
substantial improvements of nonresidential structures in areas identified
as subject to sheet flow shall have the lowest floor, including basement,
elevated above the highest adjacent grade to or above the depth number
specified on the Flood Maps, or, together with attendant utility and
sanitary facilities, be completely flood proofed to or above the elevation of
the water surface as specified on the Flood Maps.
STAFF COMMENT: No residential structures are proposed.
(H) Require that all manufactured homes or those to be substantially
improved to be placed within Zone A on a community's FEMA or FIRM
shall be installed using methods and practices which minimize flood
5
damage. For the purposes of this requirement, manufactured homes must
be elevated and anchored to resist flotation, collapse or lateral movement.
Methods of anchoring may include, but are not limited to, use of
over -the -top or frame ties to ground anchors. This requirement is in
addition to applicable State and local anchoring requirements for
resisting wind forces. A manufactured home should be elevated a
minimum of one (1) foot above the base flood level and anchored to the
elevated foundation. (A. 85-211; 89-057; 91-088)
STAFF COMMENT: No manufactured homes are proposed.
7. SUGGESTED FINDINGS
1. That proper public notice was provided as required for the hearing before the
Board of County Commissioners.
2. That the hearing before the Board of County Commissioners was extensive and
complete, that all pertinent facts, matters and issues were submitted and that all
interested parties were heard at that meeting.
3. That for the above stated and other reasons, the proposed Special Use Permit is in
the best interest of the health, safety, morals, convenience, order, prosperity and
welfare of the citizens of Garfield County.
4. That the Special Use Permit application is in conformance to the Garfield County
Zoning Resolution of 1978, as amended.
8. RECOMMENDATION
Staff recommends APPROVAL with the following conditions:
1. All representations of the applicant, either within the application or stated at the
hearing before the Board of County Commissioners, shall be considered
conditions of approval unless otherwise modified by the Board.
2. The Applicant shall meet all requirements of the Garfield County Zoning
Resolution of 1978, as amended.
9. RECOMMENDED MOTION
"I move to approve the Special Use Permit request for construction of two outlet features
for bank stabilization in the Floodplain at 200 Oak Lane, Lot 21 of the Westbank Ranch
Subdivision, Glenwood Springs, Colorado with the conditions proposed by Staff."
6
.....'RESOURCE
. l.•..
■ ■■.■ E N G I N E E R I N G I N C.
Richard Wheeler ,` CIF] V 1 August 30, 2005
Garfield County Building and Planning dept
108 8th Street, Suite 201 AUG 3 0 2005
. Glenwood Springs CO 81601
GARFIELD COUNTY
RE: Gould Floodplain Special Use Permit ReviewsUILDINC & PLANNING
Dear Richard:
At the request of Garfield County, Resource Engineering, Inc. (RESOURCE) has reviewed the
Gould Floodplain Special Use Permit Application. The application submittal was prepared by
Sopris Engineering, LLC and is dated May 2, 2005. Our comments are presented below.
PROJECT SUMMARY
The proposed project subject to the floodplain special use permit involves construction of water
feature channels within the 100 year floodplain and the floodway. The channels will be excavated
and partially backfilled with bedding material, a liner, and rock rip rap. The final grade will be
below the existing grade.
ANALYSIS SUMMARY
The proposed activity is consistent with the allowed uses and activities and meets the standards
for construction as outlined in Section 6.09 of the Garfield County floodplain regulations.
Specifically, it is consistent with the applicable floodway encroachment provisions of Section
6.09.01(1)(A) and the floodplain hazard provisions of Section 6.09..02 (1)(A).
In addition, we concur with the Sopris Engineering opinion that Section 404 permitting is not
applicable since the project is not located on tributary water of the U.S., is not within wetland
area, and is above the ordinary high water line of the Roaring Fork River (refer to Section
6.08.01(1
))•
Please call if you have any questions or need additional information.
Sincerely,
RESOURCE
ING, INC.
Michael J. Erb, , P.E.
Water Reso fe Engineer
MJ E/mmm
885-38.0
E:\Client1885\rwheeler gould flood plain 885.doc
CC: Yancy Nichol, P.E., Sopris Engineering
EXHIBIT
Consulting Engineers and Hydrologists
909 Colorado Avenue • Glenwood Springs, CO 81 601 • (970) 945-6777 • Fax (970) 945-11 37