HomeMy WebLinkAboutSoils Report.pdfI-II: I'WORTH-I'AWLAK (3E0 Ei iN
SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED RESIDENCE
895 COUNTY ROAD 223 (PETERSON LANE)
GARFIELD COUNTY, COLORADO
JOB NO. 114 203A
JUNE 18, 2014
PREPARED FOR:
MS. STEPHANIE GUBE
895 COUNTY ROAD 223
RIFLE, COLORADO 81650
s1cphra alcab.cun►
II ;IIH+ e
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY - 1 -
PROPOSED CONSTRUCTION 1 -
SITE CONDITIONS - 1 -
FIELD EXPLORATION
- 2 -
SUBSURFACE CONDITIONS - 2 -
FOUNDATION BEARING CONDITIONS - 3 -
DESIGN RECOMMENDATIONS - 3 -
FOUNDATIONS
3 -
FOUNDATION AND RETAINING WALLS - 4 -
FLOOR SLABS
- 6 -
SITE GRADING
- 6 -
SURFACE DRAINAGE
- 6 -
LIMITATIONS
- -
FIGURE 1 - LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2- LOGS OF EXPLORATORY BORINGS
FIGURE 3 - LEGEND AND NOTES
FIGURES 4 & 5- SWELL -CONSOLIDATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed residence to be located at
895 County Road 223 (Peterson Lane) east of Rifle, Garfield County, Colorado. The
project site is shown on Figure 1. The purpose of the study was to develop
recommendations for the foundation design. The study was conducted in accordance
with our agreement for geotechnical engineering services to Stephanie Cube dated May
27, 2014.
A field exploration program consisting of exploratory borings was conducted to obtain
information on the subsurface conditions. Samples of the subsoils obtained during the
field exploration were tested in the laboratory to determine their classification,
compressibility or swell and other engineering characteristics. The results of the field
exploration and laboratory testing were analyzed to develop recommendations for
foundation types, depths and allowable pressures for the proposed building foundation.
This report summarizes the data obtained during this study and presents our conclusions,
design recommendations and other geotechnical engineering considerations based on the
proposed construction and the subsurface conditions encountered.
PROPOSED CONSTRUCTION
The proposed residence will be a 1 1/2 story modular structure. Ground floor will be a
structural slab over crawlspace with a slab -on -grade garage floor. Grading for the
structure is assumed to be relatively minor with cut depths between about 2 to 4 feet. We
assume relatively light foundation loadings, typical of the proposed type of construction.
If building loadings, location or grading plans change significantly from those described
above, we should be notified to re-evaluate the recommendations contained in this report.
SITE CONDITIONS
The site is a relatively flat pad area approximately 900 feet west of County Road 223.
The site is accessed from County Road 223 with a gravel drive. The proposed building
Job No. 114 203A
Ge Gtech
-2 -
area was previously occupied by a single family residence with a walkout basement level.
The previous construction burned and has been removed. The building pad area has
reportedly been cut down to the previous walkout basement level, approximately 6 feet of
cut depth in areas. The pad area drops off to the north, east and south and is bordered to
the west by a relatively steep cut slope rising up to a small butte. Sandstone and
claystone bedrock crop out on the small butte to the west. Small stone retaining walls
terrace the slope down to the south. The cut surface of the proposed building area
consists of sandy clay with gravel and scattered cobbles. Debris from previous
construction and stripped soil from the building area were stockpiled on the east edge of
the site. An irrigation ditch runs below and south of the property.
FIELD EXPLORATION
The field exploration for the project was conducted on June 9, 2014. Two exploratory
borings were drilled in the proposed building area, as designated by the Client, and
approximately as shown on Figure 1 to evaluate the subsurface conditions. The borings
were advanced with 4 inch diameter continuous flight augers powered by a truck-
mounted CME -45B drill rig. The borings were logged by a representative of Hepworth-
Pawlak Geotechnical, Inc.
Samples of the subsoils were taken with a 2 inch I.D. spoon sampler. The sampler was
driven into the subsoils at various depths with blows from a 140 pound hammer falling 30
inches. This test is similar to the standard penetration test described by ASTM Method
D-1586. The penetration resistance values are an indication of the relative density or
consistency of the subsoils and hardness of the bedrock. Depths at which the samples
were taken and the penetration resistance values are shown on the Logs of Exploratory
Borings, Figure 2. The samples were returned to our laboratory for review by the project
engineer and testing.
SUBSURFACE CONDITIONS
Graphic logs of the subsurface conditions encountered at the site are shown on Figure 2.
Due to the cut surface in the proposed building pad area, topsoil was not encountered.
Job No. 114 203A
Ge Piech
-3 -
The subsoils in the building pad area consist of about 8 to 17 feet of medium stiff to stiff,
silty sandy clay overlying sandstone and claystone bedrock. The bedrock varied from
weathered to very hard in consistency. Depth to bedrock apparently varies considerably
across the building pad area.
Laboratory testing performed on samples obtained from the borings included natural
moisture content and density and finer than sand size gradation analysis. Results of
swell -consolidation testing performed on relatively undisturbed drive samples of the clay
soils, presented on Figures 4 & 5, indicate low to moderate compressibility under
conditions of loading and wetting and moderate compressibility under further loading
after wetting. The laboratory testing is summarized in Table 1.
No free water was encountered in the borings at the time of drilling and the subsoils were
slightly moist to moist and the bedrock was relatively dry.
FOUNDATION BEARING CONDITIONS
The silty sandy clay site soils are suitable for support of the proposed residence on
shallow spread footings with some risk of settlement. Any existing fill or loose and
disturbed soils should be removed and the foundation level extended down to the natural
site soils. Placing the foundation entirely on bedrock could achieve a low settlement risk.
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory borings and the
nature of the proposed construction, we recommend the building be founded with spread
footings bearing on the natural site soils.
The design and construction criteria presented below should be observed for a spread
footing foundation system.
1) Footings placed on the undisturbed natural silty sandy clay soils should be
designed for an allowable bearing pressure of 1,500 psf. Based on
Job No. 114 203A
GE~&ech
-4 -
experience, we expect initial settlement of footings designed and
constructed as discussed in this section will be about l inch or less. There
could be about 'A to 1 inch of additional differential settlement under
wetted conditions and precautions should be taken to keep the bearing
soils dry.
2) The footings should have a minimum width of 16 inches for continuous
walls and 2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided
with adequate soil cover above their bearing elevation for frost protection.
Placement of foundations at Least 36 inches below exterior grade is
typically used in this area.
4) Continuous foundation walls should be reinforced top and bottom to span
local anomalies such as by assuming an unsupported length of at least 12
feet. Foundation walls acting as retaining structures should also be
designed to resist lateral earth pressures as discussed in the "Foundation
and Retaining Walls" section of this report.
5) Any existing fill, debris, loose or disturbed soils should be removed and
the footing bearing level extended down to the stiff natural soils. The
exposed soils in footing area should then be moistened and compacted.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to evaluate bearing conditions.
FOUNDATION AND RETAINING WALLS
Foundation walls and retaining structures which are laterally supported and can be
expected to undergo only a slight amount of deflection should be designed for a lateral
earth pressure computed on the basis of an equivalent fluid unit weight of at least 55 pef
for backfill consisting of the on-site clay soils and at least 45 pcf for backfill consisting of
imported granular materials. Cantilevered retaining structures which are separate from
the structure and can be expected to deflect sufficiently to mobilize the full active earth
pressure condition should be designed for a lateral earth pressure computed on the basis
Job No. 114 203A
Geortech •
-5 -
of an equivalent fluid unit weight of at least 45 pcf for backfill consisting of the on-site
soils and at least 40 pcf for backfill consisting of imported granular materials.
All foundation and retaining structures should be designed for appropriate hydrostatic and
surcharge pressures such as adjacent footings, traffic, construction materials and
equipment. The pressures recommended above assume drained conditions behind the
walls and a horizontal backfill surface. The buildup of water behind a wall or an upward
sloping backfill surface will increase the lateral pressure imposed on a foundation wall or
retaining structure.
Backfill should be placed in uniform lifts and compacted to at least 95% of the maximum
standard Proctor density at a moisture content slightly above optimum. Backfill in
pavement and walkway areas should be compacted to at least 95% of the maximum
standard Proctor density. Care should be taken not to overcompact the backfill or use
large equipment near the wall, since this could cause excessive lateral pressure on the
wall. Some settlement of deep foundation wall backfill should be expected, even if the
material is placed correctly, and could result in distress to facilities constructed on the
backfill.
The lateral resistance of foundation or retaining wall footings will be a combination of the
sliding resistance of the footing on the foundation materials and passive earth pressure
against the side of the footing. Resistance to sliding at the bottoms of the footings can be
calculated based on a coefficient of friction of 0.40. Passive pressure of compacted
backfill against the sides of the footings can be calculated using an equivalent fluid unit
weight of 360 pcf. The coefficient of friction and passive pressure values recommended
above assume ultimate soil strength. Suitable factors of safety should be included in the
design to limit the strain which will occur at the ultimate strength, particularly in the case
of passive resistance. Fill placed against the sides of the footings to resist lateral loads
should be compacted to at least 95% of the maximum standard Proctor density at a
moisture content near optimum.
Job No. 114 203A
Gtech
-6 -
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded slab -
on -grade construction, such as in garage areas with some settlement potential if the
bearing soils are wetted. To reduce the effects of some differential movement, floor slabs
should be separated from all bearing walls and columns with expansion joints which
allow unrestrained vertical movement. Floor slab control joints should be used to reduce
damage due to shrinkage cracking. The requirements for joint spacing and slab
reinforcement should be established by the designer based on experience and the intended
slab use.
All fill materials for support of floor slabs should be compacted to at Least 95% of
maximum standard Proctor density at a moisture content near optimum. Required fill can
consist of the on-site soils devoid of vegetation, topsoil and oversized rock.
SITE GRADING
The risk of construction -induced slope instability at the site appears low provided the
building is located as planned and cut and fill depths are limited. Embankment fills (if
constructed) should be compacted to at least 95% of the maximum standard Proctor
density near optimum moisture content. Prior to fill placement, the subgrade should be
carefully prepared by removing all vegetation and topsoil and compacting to at least 95%
of the maximum standard Proctor density. The fill should be benched into the portions of
the hillside exceeding 20% grade. A drainage swale should be considered as part of the
civil design to route water away from the residence on the uphill side of the site.
Permanent unretained cut and fill slopes should be graded at 2 horizontal to 1 vertical or
flatter and protected against erosion by revegetation or other means.
SURFACE DRAINAGE
Positive surface drainage is an important aspect of the project to prevent wetting of the
bearing soils. A foundation drain should not be provided around shallow (less than 4 feet
deep) crawlspace areas. Foundation wall backfill should have adequate compaction and
Job No. 114 203A
Gtech
-7 -
positive surface slope away from foundation walls. The following drainage precautions
should be observed during construction and maintained at all times after the residence has
been completed:
1) Inundation of the foundation excavations and underslab areas should be
avoided during construction.
2) Exterior backfill should be adjusted to near optimum moisture and
compacted to at least 95% of the maximum standard Proctor density in
pavement and slab areas and to at least 90% of the maximum standard
Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be
sloped to drain away from the foundation in all directions. We
recommend a minimum slope of 12 inches in the first 10 feet in unpaved
areas and a minimum slope of 3 inches in the first 10 feet in paved areas.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill and foundation areas.
5) Landscaping which requires regular heavy irrigation should be located at
least 10 feet from foundation walls. Consideration should be given to use
of xeriscape to reduce the potential for wetting of soils below the building
caused by irrigation.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical
engineering principles and practices in this area at this time. We make no warranty either
express or implied. The conclusions and recommendations submitted in this report are
based upon the data obtained from the exploratory borings drilled at the locations
indicated on Figure 1, the proposed type of construction and our experience in the area.
Our services do not include determining the presence, prevention or possibility of mold or
other biological contaminants (MOBC) developing in the future. If the client is
concerned about MOBC, then a professional in this special field of practice should be
consulted. Our findings include interpolation and extrapolation of the subsurface
conditions identified at the exploratory borings and variations in the subsurface
Job No. 114 203A
Ge Ptech
-8 -
conditions may not become evident until excavation is performed. If conditions
encountered during construction appear different from those described in this report, we
should be notified so that re-evaluation of the recommendations may be made.
This report has been prepared for the exclusive use by our client for design purposes. We
are not responsible for technical interpretations by others of our information. As the
project evolves, we should provide continued consultation and field services during
construction to review and monitor the implementation of our recommendations, and to
verify that the recommendations have been appropriately interpreted. Significant design
changes may require additional analysis or modifications to the recommendations
presented herein. We recommend on-site observation of excavations and foundation
bearing strata and testing of structural fill by a representative of the geotechnical
engineer.
Respectfully Submitted,
HEPWORTH - PAWLAK GEOTECHNICAL, INC.
Ja es A. Parker, P.E., P.G.
Reviewed by:
Steven L. Pawlak, P.E.
JAP/ksw
Job No. 1 14 203A
Gtech
BORING 2
•
STEEP SLOPE UP
GARAGE
PROPOSED
MODULAR
HOME
BORING 1
NOT TO SCALE:
ACCESS DRIVE
114 203A
Gtech
HEPWORTH PAW' AK GEOTECHNIGU
LOCATIONS OF EXPLORATORY BORINGS
FIGURE 1
FIGURE 2
DEPTH - FEET
0
5
10
15
20
25
BORING 1
ELEV. =100'
r— 5/12
WC=13.9
.— 8/12 DD=110
/— -200=68
10/12
/ WC=11.4
14/12 DD=120
/
50/3
BORING 2
ELEV.=-101'
NOTE: Explanation of symbols is shown on Figure 3.
0
5
10
15
20
25
DEPTH - FEET
114 203A
IHEPWGerech
t EOTE,CFiNIc
AI.
LOGS OF EXPLORATORY BORINGS
FIGURE 3
LEGEND:
—7
4—
'04,4
CLAY
—
CLAY (CL); silty, sandy, medium stif to very stiff, slightly moist to moist, brown.
SANDSTONE/CLAYSTONE BEDROCK; weathered to very hard, slightly moist, tan, brown, gray and purple.
Relatively undisturbed drive sample; 2 -inch I.D. California liner sample.
5/12 Drive sample blow count; indicates that 5 blows of 140 pound hammer falling 30 inches were required to drive the
California sampler 12 inches.
NOTES:
1. Exploratory borings were drilled on June 9, 2014 with 4 -inch diameter continuous flight power auger.
2. Locations of exploratory borings and the proposed building area were designated in the field by the Client.
3. Elevations of exploratory borings were measured by hand level and are referenced to Boring 1 as elevation 100,
assumed'. The boring logs are drawn to depth.
4. The exploratory boring locations and elevations should be considered accurate only to the degree implied by the
method used.
5. The lines between materials shown on the exploratory boring logs represent the approximate boundaries between
material types and transitions may be gradual.
6. No free water was encountered in the borings at the time of drilling. Fluctuation in water level may occur with time.
7. Laboratory Testing Results:
WC = Water Content (% )
DD = Dry Density ( pcf )
-200 = Percent passing No. 200 sieve
114 203A
Ilef'wG ech
ICAI_
LEGEND AND NOTES
COMPRESSION (% )
COMPRESSION (% )
5
0
1
2
3
4
5
0
Moisture Content = 13.9 percent
Dry Density = 110 pcf
Sample of: Sandy Silty Clay
From Boring 1 at 5 Feet
Compression
upon
wetting
0.1
1.0 10
APPLIED PRESSURE ( ksf )
100
APPLIED PRESSURE ( ksf )
100
114 203A
Gtech
I1EPWOIZTH.PAWI.AK GEOTECHNICAL_
SWELL -CONSOLIDATION TEST RESULTS
FIGURE 4
Moisture Content = 11.4 percent
Dry Density = 120
pcf
Sample of: Slightly Gravelly S Ity Sandy Clay
From: Boring 1 at 10 Feet
NN0
.
Compression
upon
wetting
Ii
i
1 i n
APPLIED PRESSURE ( ksf )
100
114 203A
Gtech
I1EPWOIZTH.PAWI.AK GEOTECHNICAL_
SWELL -CONSOLIDATION TEST RESULTS
FIGURE 4
COMPRESSION (% )
1
2
3
4
5
0
I
1
I
I
Moisture Content = 13.8 percent
Dry Density = 118 pcf
Sample of: Silty Sandy Clay
From. Boring 2 at 5 Feet
,,—.1111111111111
Compression
jupon
wetting
•
•
1
1
i
i
I
1,
1
1 0
in
.,.,,
APPLIED PRESSURE (ksf )
114 203A
Gtech
I IEPWORTI I-PAWLAK GEOTECHNICAL
SWELL -CONSOLIDATION TEST RESULTS
FIGURE:. 5
ECHNICAL, INC.
Job No. 114 203A
1-
Co
CO
W
O
• re
ago
J
< co1
a �
= 0
• }
O <
O.
Lu
x 0
N
SOIL TYPE
Sandy Silty Clay
Slightly Gravelly Silty Sandy
Clay
Silty Sandy Clay
UNCONFINED
COMPRESSIVE
STRENGTH
(PSF)
ATTERBERG LIMITS
LIQUID PLASTIC
LIMIT INDEX
(%) (%)
- PERCENT
PASSING
NO. 200
SIEVE
00
1/400
Z
O
f
I
a a
N
O -
ga� ,
6 O W a
Z m
0
.r
0
.ti
00
ti
NATURAL
MOISTURE
CONTENT
(%)
i 13.9
,t
• -
.-i
00
Cr;
1--i
LOCATION
DEPTH
IR)
I5
.-i
V'1
W
J Ur
a Z
i a
co m
.y
N