HomeMy WebLinkAbout1.09 Construct5ion scheduleCONSTRUCTION SCHEDULE CONSTRUCTION SCHEDULE: Construction activities are scheduled to commence upon approval of land grants, land owners Right -of Way (ROW) agreements and associated permits with a completion date of approximately 8 weeks later. Construction will begin with pipeline ROW clearing and assuming a reasonable construction kick off date, expedient construction progress, limited weather-related delays, and winter stipulations, the reclamation and restoration of the ROW should be completed by the end of October 2006. Construction activities, except for hydrostatic testing, will only occur between the hours of 7 am and 5 pm, six days a week (usually Monday to Saturday)