HomeMy WebLinkAbout1.3 Plan Development•
•
•
PORCUPINE LOOP
PIPELINE PROJECT
PLAN OF DEVELOPMENT
July 200 4
Applicant:
Canyon Gas Resources, LLC
7400 East Orchard Road, Suite 3025
Englewood, CO 80111
Prepared By:
Trigon EPC
592 South Main Street, Suite 23
Meeker, CO 81641
•
•
•
TABLE OF CONTENTS
1.0 In tro duction ......................................................................................................................... 1
1.1 Project Description .......................................................................................................... 1
1.2 Purpose and Need ........................................................................................................... 1
2.0 Pre-Construction Activi ti es ................................................................................................. 2
2.1 Design Factors ................................................................................................................ 2
2.2 Permits Required ............................................................................................................. 2
3.0 Construction Activities ....................................................................................................... 2
3.1 Access ............................................................................................................................. 2
3 .2 Engineering Surveys ....................................................................................................... 2
3.3 Hazardous Materials Management ................................................................................. 3
3.4 Solid Waste Management ............................................................................................... 3
3 .5 Fire Prevention and Suppression .................................................................................... 3
3.6 Pipeline Constructi on ...................................................................................................... 3
3.6 .1 C learing and Grading .................................................................................................. 3
3.6.2 Trenching .................................................................................................................... 4
3.6.3 P ipe Installation .......................................................................................................... 4
3.6.3.1 Stringing .............................................................................................................. 4
3.6.3.2 Bending ............................................................................................................... 4
3.6.3.3 Welding ............................................................................................................... 4
3.6.3.4 X-Ray Inspection ................................................................................................ 5
3.6 .3 .5 Coating ................................................................................................................ 5
3.6.3.6 Lowering-in and Padding .................................................................................... 5
3.6.3.7 Backfi llin g ........................................................................................................... 5
3.6.4 Cleanup ....................................................................................................................... 5
3.6.5 Revegetation ............................................................................................................... 6
3.6.6 Road and Pipeline Crossings ...................................................................................... 7
3.6.7 Drainage Crossings ..................................................................................................... 7
3.6.8 Pneumatic Testing ....................................................................................................... 7
4.0
4.1
4.2
5.0
5.1
5.2
5.3
5.4
5.5
Post-Construction Activities ................................................................................................ 8
Maintenance and Operation ............................................................................................ 8
Abandonn1ent .................................................................................................................. 8
Mitigation Measures ............................................................................................................ 8
Noxious Weeds ............................................................................................................... 8
Erosion ............................................................................................................................ 9
Threatened, Endangered, and Sensitive Species ............................................................. 9
Cultural Resources .......................................................................................................... 9
Air Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 0
Appendix A
App end ix B
Appendix C
Appendix D
App endix E
Appendix F
Appendix G
Proj ect Maps
Penni ts
S pill P lan
Fire Prevention and Suppression P lan
Stom1water Po ll ution Prevention P l an
Road Cross ing Typ ical
Dust Contro l P lan
• 1.0 INTRODUCTION
•
•
1.1 PROJECT DESCRIPTION
Canyon Gas Resources, LLC (CGR) has applied to the Bureau of Land Management (BLM) for
a right -of-way gran t under Section 28 of th e Mineral Leasing Act of 1920 , as amended, to
authorize the construction, operation, and maintenance of a 12 -inch diameter natural gas pipeline
and re l ated faci li ties in Garfie ld County, Co lorado. The project is approximately 4.3 miles in
length, of which 0.8 miles are located on fee -lands and 3.5 miles are located on BLM lands
administered by the Glenwood Springs Fie ld Office. The project is located south and west of
Rifle, Co lorado in Sections 1, 9, 10, 11 , and 12 of Township 7 South, Range 94 West in the
Rulison and North Mamm Peak USGS Quadrang les. Project area maps are included in Appendix
A.
The approximate area of temporary disturbance for construction within the right-of-way is 26
acres and total temporary disturbance is 29 acres . Table 1-1 below describes the width, length
and acreage of the right-of-way (ROW), and acreage for temporary u se areas (TUA), and
di sturbed areas (DA ) th at wi ll b e u se d duri ng constructi on .
Tab le 1-1 Estimated Area of Disturbance
Description Permanent Temporary Distance (ft) Acreage
W idth (ft ) Width (ft )
B LM R OW 50 0 18481 2 1.2 1
F ee ROW 25 25 4118 4 .73
Total 22599 25.94
BLMTUA 0 .83
BLMDA 0 .15
Fee TUA 1.95
FeeDA 0.2 3
Total 3.16
Total Acreage 29.10
Construction activities are expected to be completed in 4 to 6 weeks and are scheduled for
summer or fall 2004.
1.2 PURPOSE AND NEED
The proposed pipeline project would loop an existing CGR 6-inch diameter natural gas pipeline
and would connect CGR's Bentley and Porcupine Gathering Systems. The pipeline would
transport existing and future natural gas produced by Tom Brown, Inc. (TBI) in the Rifle,
Co lorado area for process ing at the Rifle C lough Compressor St ation . TBI plans to dril l more
than 40 new we ll s in 2004, all of w h ich are dedica ted to CGR's gath ering systems. Produ ction
from th ese we ll s is ex p ected t o in crease b y 35 mmscf/d, in creasin g t ot al thr o ugh p ut fr om 15
mmsc f/d to 5 0 mm scf/d. Sys t em throu ghput will in cr ease to 100 mmscf/d in th e n ex t four ye ars .
The proposed pip e lin e wi ll d e-bottleneck th e ex istin g gat h erin g system s and wi ll ensure
s uffici ent capacit y to c arry CGR 's current proj ectio n of fu t ure gas vo lum e s.
• 2.0 PRE-CONSTRUCTION ACTIVITIES
•
•
2.1 DESIGN FACTORS
CGR wi ll design and bu ild the pipeline according to the Nat ional Electrical Code (NEC),
Department of Transportation 40 CFR Part 192, and ASME B31.8 standards. Additionall y, the
facilities will be designed, constructed, and operated in compliance with the Occupational Safety
and Health Act (OSHA) regu lations pertaining to pipeline construction and operation. Proposed
pipe is as follows: 12.75 " OD, 0.219" wt, FBE Coated 12-14 mils, ERW, PSL2, Grade B -
pressure-tested with Nitrogen to 900 psig (12 5 % of 720 psig MAOP).
The proposed pipeline will be installed in a trench offset 10 feet from the existing CGR pipeline
and will require a construction right-of-way width of 50 feet. The majority of the construction
right-of-way will overlap the existing right-of-way and will utilize the previously disturbed
footprint. A launcher and receiver will be located at opposite ends of the pipeline, with risers,
blow-downs, and valve sets where appropriate along the right-of-way.
2.2 PERMITS REQUIRED
Th e G lenwoo d Sp ri n gs Field Office of th e Bureau of Land Managem ent w ill iss ue th e Right -of-
Way Grant wi th st ipul atio ns and th e No ti ce to Proceed. In addition , th e fo ll owing permit s w ill be
obt ain ed and ad h ered t o :
• BLM R ight -of-W ay Grant an d Noti ce to Proceed
• Garfield Co un ty road crossin g pennit and, i f applicabl e, Garfie ld County Special Use Permit
• Co lorado General Construction Stormwater Permit
• Colorado Industrial Wastewater Discharge Permit
• Colorado Air Emission Permit
• Army Corp of Engineers Nationwide Permit 12
A copy of the Right-of-Way Grant with stipulations and permits are included in Appendix B.
3.0 CONSTRUCTION ACTIVITIES
3.1 ACCESS
Access to the proposed pipeline route would be via County Road (CR) 317 (Beaver Creek Road),
CR 325 (Porcupine Creek Road), and CR 329 (Spruce Creek Road). New roads would not be
constructed and improvements to existing roads would occur within the previously disturbed
area. Roads used for the project would be maintained and/or repaired as necessary to co nditions
equal to or better than those which existed prior to project -related use .
3.2 ENGINEERING SURVEYS
Th e co n stru ction right -o f-w ay w ill be m ark ed prio r t o co n stru ction at approx im at e ly 2 00 -fo ot
int ervals w ith lath s an d fla gg in g . The r ight -o f-w ay st akin g will consist of markin g th e edges of
2
• the construction right -of-way boundaries , temporary use area boundmies, and disturbed area
boundaries . Survey station numbers will be marked on the lat h s . Laths wi ll be maintained
throughout construction and will not be removed until after revegetation activities have been
completed.
•
•
3.3 HAZARDOUS MATERIALS MANAGEMENT
To prevent the accidental release of hazardous materials and petroleum products, construction,
operation, and maintenance activities shall comply with CGR's Spill Prevention, Containment,
and Countermeasure (Spill) Plan. The Spi ll Plan is included in Appendix C.
3.4 SOLID WASTE MANAGEMENT
The construction right -of-way and temporary use areas will be maintained in a sanitary condition
at all times and waste materials on the project will b e disposed of promptly at an appropriate
waste disposal facility. Waste includes , but is not limited to, human w a ste, trash, garbage, ashes,
welding rods, etc. Portab le toilets will be available on-site . Liquid and solid waste generated
during construction of the project will be disposed of in an approved manner at an appropriate
facility so as not to impact air, water, soi l, vegetation, or wi ldlife .
3.5 FIRE PREVENTION AND SUPPRESSION
CGR's F ire Prevention and Suppression (Fire) P lan estab lishes standards and practices that will
minimize the risk of fire danger and, in case of fire, provide for immediate suppression. The Fire
Plan is attached in Appendix D.
3.6 PIPELINE CONSTRUCTION
The following sections include general descriptions of the various pipeline construction phases .
Also included in these sections are specific app licab le mitigation requirements that will be
implemented by the Contractor. The following operations are typical in a construction spread .
3.6.1 Clearing and Grading
Clearing, topsoiling and grading will be limited to the minimum area required for safe and
efficient construction. Clearing will be performed only to the extent necessary to allow for
construction activities . The ground surface will not be grubbed or c leared of vegetation less than
four inches in height when possible. Every effort wi ll be made to salvage root systems. Large
vegetation, such as trees and shrubs, will be cleared from the right-of-way and stockpiled or
windrowed at the edge of the approved workspace for lat er us e in reclamation .
Topsoil will be removed and stockpi led. Where topsoil is availab le, the top 4 to 6 inches of soil
wi ll be removed over the trenchline and in areas requiring grading . Topsoi l and cleared
vegetation wi ll be stockp il ed together on BLM l and s. Topsoi l wi ll be stockpi led separate from
c leared vegetation on fee-lands. The r ight-of-way wi ll be graded only to the extent necessary to
3
• create safe and efficient pipeline installation conditions. Topsoil will not b e salvaged over th e
existing CGR pipelin es.
•
•
3.6.2 Trenching
The ditch will be excavated and sloped in accordance with OSHA specifications. The cover from
top of pipe to ground level as graded to pre-construction contours will be in conformance with
DOT regulations. Cover will typically be 36-inches in depth. Greater depths of cover will be
required at road crossings, foreign pipeline crossings, and waterbodies. As a minimum, the ditch
will be excavated to a depth to allow a clearance of 18 inches between the CGR pipeline and
other pipelines or underground facilities. Machine excavation will not be performed closer than 5
feet from any existing pipeline encountered in the ROW unless authorized by the pipeline
owners/operators . Existing pipeline locations will be marked in the field and 48-hour prior
notification given to the operator of the underground utility .
Where rock is encountered, tractor-mounted mechanical rippers or rock trenching equipment
may be used to facilitate excavation.
The trench will be excavated an d subsoil mat erial stockpiled separately from topsoil stockpiles.
Based on field conditions, gaps will be made in topsoil and subsoil stockpiles to avoid ponding
or excessiv e diversion of n atural runoff during storm events .
3.6.3 Pipe Installation
Pipe installation will include stringin g, bending for horizontal or vertical angles in the alignment,
weldin g th e pipe segments together, x-ray inspection, coating the joint areas to prevent corrosion,
and then lo wering-in and padding as described in greater detail below.
3.6.3.1 Stringing
Pipe will be hauled by truck to the pipeline ROW. Each joint of pipe will be unloaded and placed
parallel to the ditch .
3.6.3.2 Bending
After the joints of pipe are strung along the ditch, individual joints of pipe will be bent to
accommodate hori z ontal and vertical changes in direction. Field bends will be made utilizing a
hydraulically operated bending machine. Where the deflection of a bend exceeds the allowable
limits for a field-bent pipe, factory (induction) bends will be installed.
3.6.3.3 Welding
After the pipe joints are bent, the pipe is lined up end-to-end and clamped into position. The pipe
is then welded in confo1mance with 49 CFR Part 19 2, Subpart E. "Welding of Steel Pipelines"
and API 1104, "Standard for Welding Pipe lin es and Re lated Facilities" .
4
•
•
•
3.6.3.4 X-Ray Inspection
Welds will b e visually inspected by a qualified in spector and by nondestructive rad io graphic
methods. At a minimum , radiographic inspection will be conducted in accordance with DOT
requirements. A specialized contractor, certified to perform radiographic insp ection, wi ll be
emp lo ye d to perform thi s work. Any defects wi ll be repaired or c ut out as required under the
specified regu lati ons and standards .
3.6.3.5 Coating
To prevent corrosion, the pipe w ill b e ex ternally coated w ith fusion bonded epoxy coatin g prior
to de li very. Aft er welding, field joints wi ll be coated with eit her tape and prim er or shrink
sleeves. Before th e pipe is low ered into th e ditch , the pipeline coating will be visuall y inspected
and tested with an electronic detector, and any faults or scratch es w ill be repaired.
3.6.3.6 Lowering-in and Padding
Once the pipe coating operation has been comp leted , a section of the pip e will b e low ered into
the ditch. Side-boom tractors wi ll be u sed to si multaneously lift the pipe , position it over the
ditch, and lower it in place. Inspection will be conducted to verify that minimum cover is
provided; the trench bottom is free of rocks, debris , etc .; external pipe coating is not damaged;
and the pipe is properly fitted and install ed into th e ditch . Specialized padding machines wi ll be
used to sift soil fines from th e exc avated subsoi l to provide rock -free pipeline padding and
bedding. In rocky areas, padding material or a rock shi e ld wi ll be u sed t o protect th e pipe .
Topsoil will not b e u sed to pad the pipe.
3.6.3.7 Backfilling
Backfi lling will begin aft er a section of th e pipe h as been successfull y p laced in th e ditch and
final inspection has been compl eted . B ackfilling will be conducted using a bulldo zer, rotary
auger backfill, padding machine or other suitable eq uipm ent. Backfilling the trench will
generally use the subsoil previous l y excavated from th e trench, except in rocky areas where
imported select fill material maybe needed . Backfi ll will be graded and compacted, where
necessary for ground stability, by being tamped or walked in with a wheeled or track vehicle .
Compaction will be performed to the extent that there are no voids in the trench. Any excavated
materials or materials unfit for backfill will be utilized or properly disposed of in conformance
with app licable laws or regulations.
3.6.4 Cleanup
Cleanup activities will be initiated as soon as practicable after backfilling activities have been
completed.
A ll co nstructio n -related debris will be removed and disposed of at an approved d isposal area .
The right -of-way and temporary use areas will be graded as near as possibl e to the pre-
construc ti on contours and natural runoff and drainage patterns will be restored. Stockpi led
topsoil w ill b e redistributed over th e trench and other portions of th e right -of-way from wh ich
th e topsoil was salvaged . T opsoil w ill be left in a roughened condition .
5
•
•
•
Permanent waterbars wi ll installed according to th e guid e line s in th e Storm water Pollution
Prevention Plan (attached in Appendix E).
Vegetat ive mulch and excess rock will be us ed to reduce erosion po t ent ial on ELM-admini stered
land s by providing additional surface relief structure. Vegetative debris salvaged during clearing
and grading operations will b e distributed across the right-of-way. Layering of rock may be used
on the surface of erodib le so ils in some critical areas to reduce erosion and res tore appearance of
native surface. Suitabl e sites include naturally rocky s lopes and areas that have a natural grave l,
cobble, or boulder veneer on the surface. Suitab le sites will be determined by the CGR
Representative in conjunction with the BLM on ELM-administered lands.
On fee -lands, vegetation removed during clearing operations will be removed and rocks will be
removed from the right-of-way to approximate pre-construction conditions. Vegetation and
excess rock will be disposed of at a location determined by the landowner.
All existing improvements, such as fences, gates, irrigation ditches, and cattle guards, will be
maintained and repaired by the Contractor to at least pre-construction condition and to the
satisfaction of the landowner or BLM field representative to minimize disturbance to the p ub lic.
OHV barriers may be required by the BLM. Suitabl e sites will b e determined by th e CGR
Rep r esentativ e in co njunction with the BLM on ELM-administered lands .
3.6.5 Revegetation
Every attempt will be made to see d disturbed areas within 24 hours of c ompl etin g topsoil
replacement and install ation of permanent soi l erosion and sed im ent control measures . If an area
is not seeded within 24 hours of topsoil replacement, the seed will need to be incorporated into
the soil.
All disturbed areas will be reseeded with the appropriate seed mix and rates by vegetation type as
determined by the BLM. Seed mixes will be purchased from commercial seed vendors and must
be state-certified weed-free mixtures . Seed bag tags will be collected and submitted to the BLM
to confirm that the seed was purchased from a commercial seed vendor and was tested and
certified . Seeding rate will be listed as pounds per acre of pure live seed (PLS). The BLM-
approved seed mixes for this project are listed in the stipulations attached to the Right-of-Way
Grant.
Seed will be placed in direct contact with the soil at an average depth of 0.5-inches, covered with
soil, and firmed to eliminate air pockets around the seeds. Seed will be applied using a rangeland
seed drill with a seed release and agitation mechanism suffic ient to allow seeds of various sizes
and densities to be p lanted at the proper seeding depth. Broadcast seeding will be employed only
in areas w ;1 ere drill seeding is unsafe or physically impossib le. Broadcast application rates will
be twice that of drill rates . Im m ed iate ly after broadcasting, the seed wi ll be uniformly raked,
ch a in ed, or dragge d to in corporate seed to a sufficient seedi n g depth . If th e area is see ded p1ior to
a so il crust formin g (within 24 hours of topsoil replac em ent), harro wing or raking may not b e
6
•
•
•
necessary. Fall seeding would b e completed after September I and prior to pro longed ground
frost. If necessary, spring seeding will be compl eted w h en th e ground thaw s and prior to May 15.
3.6.6 Road and Pipeline Crossings
Where the proposed line crosses existing access roads or parallels a county road within its
established ROW, it will be buried to a minimum depth of 48" below the surface, coated and
cathodic protection will be installed. Pipeline crossings of unsurfaced, lightly traveled, or rural
roads will be made with a mechanical ditching machine or a backhoe. Installation at these
locations , including cleanup and restoration of road surfaces, will usually be completed within
one day. In such cases, provisions will be made to detour or control passage of traffic during
construction. All applicable permits will be obtained for road and utility line crossings. (Please
see Appendix F for typical road crossing design.)
3.6.7 Drainage Crossings
The proposed project crosses Porcup in e Creek, one intermittent tributary to Porcupine Creek,
and two interm itt ent tributaries to Spru ce Creek. The project do es not cross any wetlands . T h e
project area is located within th e Lower Co lorado River basin. Waterbodies are anticipated to be
dry at the time of co n struction.
T emporary equipment brid ges wi ll be installed at a ll crossings of wat er bodi es which are flowin g .
If any waterbodies are flowing at the time of th e cons truction , waterbody flow will b e routed
across th e trench usin g a flume pipe and every attempt wi ll b e made to complete th e crossing
within 24 hours . T he flume pipe will be installed prior to trenching and will b e removed after
backfilling activities are completed. Spoi l from the waterbody crossings wi ll be p laced at least 10
feet away from the water's edge and sediment barriers will be used to prevent the flow of spoil
into the waterbody. If there is no flow at the time of construction, the waterbodies will be crossed
using typical upland construction techniques and the spoil will be stockpiled outside the creek
channel.
No fill will be placed below the level of the ordinary high water mark and no disposal sites are
required for excess excavated material.
3.6.8 Pneumatic Testing
The entire pipeline will be tested in compliance with DOT regulations ( 49 CFR Part 192.515 and
192.507). Prior to testing the pipeline, the pipeline will be cleaned by passing poly pigs through
the interior of the line. The pipeline will then be filled with air, pressurized, and held for the
duration of the test. The length of the segment tested may depend on topography .
7
• 4.0 POST-CONSTRUCTION ACTIVITIES
•
•
4.1 MAINTENANCE AND OPERATION
CGR w i ll maintain the area as required by the stipu l ations in th e Right-of-Way Grant.
Maintenance of the right-of-way includes, but is not limited to, soil stabilization and reseeding.
All existing improvements affected by construction and maintenance of this authorization will be
kept in as good as, or better than, original condition. CGR wi ll participate in the maintenance of
roads used to access the right-of-way and ancillary facilities in conjunction with other facilities.
The project will be operated according to natural gas industry standards. Supervisors and field
personnel will monitor and control the system by driving throughout the project area inspecting
facilities on a periodic basis. Travel down the reclaimed right-of-way will be kept to a minimum
and utilize the least impacting vehicle feasible (i.e . a four-wheeler). Disposal of any liquid and
solid waste generated during maintenance and operation of the pipeline will be done at an
approved facility in an environmentall y sound and approved manner.
CGR wi ll control nox iou s weeds as required in th e BLM stipulations attached to the Right-of-
Way G r an t and any Garfi eld Cou nty re qu irem ent s.
4.2 ABANDONMENT
Upon abandonment of th e pip elin e, a N oti ce of Intent to A bandon will b e fil ed w ith th e B LM for
final recommend ations regardin g s urface recl amation . A ft er abandonment of th e as soci ated
produc tion fa ci liti es, th e gas p ip elin es w ill b e abandon ed ac cordin g to BLM sp ec i fic ati ons. A t
th e tim e o f fin al ab a nd onm ent , th e intent of re cl am ation will b e to r eturn disturb ed ar ea s to near
natura l condit ions. All dis turbed surfaces wi ll be re-conto ured to the approximate natural
contours, with reclamation to be performed within six months, weather permitting, after fina l
abandonment.
The surface of disturbed areas will be re-contoured to blend all cuts, fills, road berms, and
borrow ditches to be natural in appearance as compared to the surrounding terrain . Disturbed
areas will be restored as near as practical to their original condition . Where applicable, these
conditions may include the reestablishment of natural drainage systems, the reestablishment of
appropriate soil conditions, and the reestablishment of vegetation as specified .
5.0 MITIGATION MEASURES
The following protective measures have been adopted by CGR to address specific resource
values and environmental concerns associated with the project. Additional mitigation measures
may be attached as stipulations to the BLM Right-of-Way Grant.
5.1 NOXIOUS WEEDS
No x iou s wee ds will b e controll ed as stipul ated in th e B LM stipul ations attach ed to th e Ri ght -of-
Wa y G rant. In addition , equipm ent will arriv e on the ri ght -of-way cl ea n and fr ee of mud from
8
•
•
•
other construction projects. After rec lam ation, mon itoring and treatment of any in fested areas
wi ll be conducted as specified in the BLM st ipulation s.
5.2 EROSION
Temporary and permanent erosion control measures will be implemented to contro l erosion and
transport of sediment. Erosion and sediment controls will be used and maintained during all
phases of construction. Selection of appropriate erosion controls will be selected based on soil
properties, steepness of the slope, and anticipated surface flow or runoff. Erosion control
measures are detailed in the Stonnwater Pollution Prevention Plan in Appendix B.
5.3 THREATENED, ENDANGERED, AND SENSITIVE SPECIES
There are no endangered or threatened species along the project route. Penstemon harringtonii, a
BLM-sensitive species and state rare species, is present in eleven locations along the route.
Mitigation measures are being developed with the Glenwood Springs BLM Field Office and will
include a combination of the following:
• avoidance, where feasib le;/ /
• identification of source populations adjacent to the right-of-way; and
• reseeding the right-of-way with seed co ll ected from source pop ul ations, if necessary. ¥.._
5.4 CULTURAL RESOURCES
A C lass I literature search and a Class ITI l evel cultural resource assessment were conducted for
access roads and the pipeline corridor determine whether cultural resources were present, and if
present, the effect the project would have on these resources. One prehistoric lithic scatter and an
isolated find were recorded as a result of the inventory. All were field evaluated as not eligible
for listing on the National Register of Historic Places .
Th e following mitigation measures will be followed during construction, operation, and
maintenance of the project:
• All persons in th e area who are associated with this project must be informed that if anyon e
is found disturbing historic , archaeological , or scientific resources, including collecting
artifacts , the person or persons will be subject to prosecution .
• The BLM authorized officer must be notified , by telephone, with written confirmation,
immediately upon the discovery of human remains, funerary items, sacred objects, or objects
of cultural patrimony. Activities must stop in the vicinity of the discovery and the discovery
must be protected for 30 days or until notified to proceed by the authorized officer.
• If in connection with operations under this contract the project proponent, his contractors,
subcontractors, or the employees of any of them, discovers, encounters or becomes aware of
any objects or sites of cultural or paleontolo g ic al value or scientific interest such as historic
or prehistoric ruins , graves or grave markers, fossils, or artifacts, the proponent shall
immediately s u spend a ll operations in th e vic init y of th e cultu ra l or paleontological resource
9
•
•
•
5.5
and shall notify th e BLM authorized officer of th e findings . Operations may resume at th e
discovery site upon receipt of written instructions and authorization by the authorized officer.
AIR QUALITY
Air quality impacts would be mitigated by following the Dust Control Plan included in Appendix
G. Any additional requirements li sted in the Emission Permit would also be impl emented .
10
• APPENDIX A PROJECT MAPS
I •
•
------------------,
•
Project Location
r
~
i
~
~
!L-~~~~~~~-::::::::--~~~~~~~~to;ES~CR;IPTI;ON;--~~~7Lo:c~at:io~nMM~op~~~~~~~--, ~' curnr ~~~ PORC UPINE PIPELINE PROJECT ./CJlt0~uCDl'oJ" ~L~~~~~~r==+~~~;oo;--~~~I
•
" G . s •<s o "• c < s DRAWN BY : CL DATE DRAWN : 6/2004 FILE NA~E : Exhibit 1-A ~ :::~EYED B~Ts TRICON-SHEEHA N. LLC REVISION: PREPARED BY TRIGON c~~: 1 :t :1: r;., ~ 1 ~ 34 Von Cor don, Su it e 200 ~ ___ _
,,-Lakewood, Colorado 80 228 E N G I N E E R S & C 0 N S T R U C T 0 R S ::i {303) 29 6-9645
.......... -.... ~ ..
' .. ).-.-..·,:
'· \. ,/
\j:.·
• . .c . :;
\,,,.· ' ·'·.:!!,. .. •,
-' ·.r
<·> ·• ~~
:~.<~
....
;p CLIEN T
'
... ... ,,•.
/•\, ... ./ ,,.,,,
Garfield County, Colorado
I
3000' 1500'
LEGEND
I
0
DES IGNATES BUREAU OF
LAND MANAGEMENT LA NDS
PROPOSED 12" LOOP LINE
PROPOSED ACCESS ROAD
3000' 6000'
SCALE: 1" = 3000 '
DESCRPTION Propo sed Ro ute
PO RCU PINE PIPE LI NE PROJECT
li'1-.-.-.-........................ -R-.•-•-o_.u_N_.o_•_•_._·_.'N ... o .......................................................................................... ....,_. ................................. -4
•~~s_CAL __ E_: ___ 1_"=_J_1 0_0_0_' ______ .._R_~_ISI0_~_· ______________ ,__0M_'v_m_ITT __ : _c_'L ..... ----------~-~-TE_o_~_~_'N: __ 6_/_2_0_0_4 _______ F_1~--N~_E_: __ E_xh_i_bi_t _1_-_s ____ ~
! SURVrrED Br ~:.:£;~~~~:~~ PRE PAR£D Bi TRIGON c~ ~ ; I ;; =I : w ~ I
::j (303) 296 -9645 E N G I ~J E E R S &: C 0 N S T R U C T 0 R S
.._ __________________________________________________ .... ________________________________________________ __.
·-
.r
~
i
B ...
·l ~
!-
JI
4
• p
.,,.
.I
1 : I
l
·:-y
curn r
r .. ·
... . •
l -
.;;:-t!All Nrll DU A D l!".11 , I N D
•
SOO.E: 1 "=800'
<I SURVffiD BY: TRIGON -91fTHAN , LLC
R 34 Vo n Gonion, Su il o 200
REVISION:
8 Lak ew ood , Ct>orodo 80228
~ (303) 296 -9645
LEGEND
• •
ORA•!IN BY: CL
,.
I, , • f
•
.. ---.. : .
'. _ ...
DESIGNATES BUREAU OF
LPND MA~JAGEM ENT LA~JOS
EXISTING C.A.NYON G.A.S Pl PELINE
PROPOSED 12'' LOOP LINE
PROPOSED A.CCESS ROAD
·-
DESIGNATES TEMPORAR Y USE ARE/..S ('ruA)
DESIGNATES DI STU RBED AREAS (DA)
Df SCRPrlOH Propo se d Rout e
PORCUPIM E PIP ELIN E PRO JECT
DATE 01\ll.WH: 6/2004 r ~E NA~E: Ex hibit 1-C
TRIGON C%,; I ;t #I: W~I
ENG I NEERS &: CONSTRUCTORS
,. .....
l .
••
~ CUEN f
Garfield County, Colorado
LEGEND
r:::::::1 DESIGNATES BUREAU OF
LAND MANAGEMENT LANDS
__,,,___,,___,,_,,___,,.__,,_ EX IST ING CP..NYOt~ GP.S Pl PELINE
PROPO SED 12 " LOOP LINE
---PROPOSED ACCESS ROAD
• DESIGNATES TEMPORARY USE AREAS (TUA)
OESCRPTION Proposed Route
PORCUPINE PIPE LI NE PROJEC T
~t------------------R~••_a_u_"_•_r_s __ ._•_N_a ______ ..,... ______ __. ________ .,... ________________ ..,.... ________________ -t
•
SCALE : 1 "=80 0' RC:VISIOlol: ORAWll Ill: CL DATE DiW\111: 6/2004 FILE NAME : Ex hibit 1-0
;t. SURVEYED BY: n;1 G?11-9 H l lAN , ~LC
f.1 3, \·on Goni on, Sv ol e 200
ti Loke•11ood, Colorad o 802211
::i (303) 296 -9(>45
PP.E PARED BY TRIGONC~~ I I #J ~: ~1 ~I
ENG I NEERS & CONSTRUCTORS
/
i ,
;
" i
I
I
I
i 1
/ / i / .r· '
'
Garfield County, Colorado
LEGEND
DESIGNATES BUREAU OF
L/l.ND MANAGEMENT LANDS
_,,___,. ____ ,,, _ _,,_,,_,,_ EX IST IN G G.A.NYON GAS PIPELINE
PROPOSED 12" LOOP LINE
---PROPOSED ACCESS ROAD
• DES IGN!.JES TEMPORARY USE .A.RE.A.S (T\JA)
• DESIGNATES DISTURBED AREAS (DA) ...... ~~~~~~~~~~~~~~~~~~~~--~~~~~~~~~~~~~~~~~~~~~ ...
~ CLIEN T
'
DESCRPTION Proposed Ro ut e
~ PORCUPINE PIPE LIN E PROJECT
~ ..... ~~~~~-8-A-ft~A~·-•-DU_N_O_r_•~·-'-N -O ~~.....,.....,~~~..._~~~ ..... ~~~~~~~~ ...... ~~~~~~~--t I ORAi/ti BY: CL
•
SD\LE : 1 "=800 ' REVISIO N:
6 SURVflED BY: TRIGON-Sli::EHAll, LLC
i'l 34 Van Gartlon, Suae 2Q(J
8 Lo>.ewood , Colorado 80228
DATE DRAWN: 6 / 200 4 m NA~E: Exhi bit 1---E
Pfl£P ARED m' TRIGONC~i I HI #I: W ~I
::i (303) 296 -9645 ENG I NEERS & CONSTRUCTORS
~ CLIEN T
' ~
LEGEND
1::::::1 DESIGNATES BUREAU OF
LAND MANAGEMEN T LANDS
_,,_,,__,1-11-1,_,,_ EX IST ING C.ANYON GAS Pl PEUNE
PROPOSED 12'' LOOP LI NE
---PROPOSED ACCESS ROAD
• DES IGN/I.TES TEM POR/l.R Y USE AREAS (TUA)
• DES IGNATES DI ST URBED .!'.\REAS (DA)
DESC RPTIOH Propo sed Rout e
PO RCUP INE PIPELIN E PRO JE CT
~~----------~s~·~·...;;.~~~~·~D ~U N~n~r~•:.....;.·~·~N ~D ----....... ---------'-------..... ----------------....-----------------t
•
Sc.\LE : 1 "=800' REVISKJ fl: ORAWll BY: CL DATE DRAWN : 6/2004 rlLE NAME: Exhib it 1-F
-SURVEYE D Br : TRIGON-9-HHAll, LLC
g 34 Von Gordon , Su ite 200
to" Lakewood , Cacrod o 80228
PflEPARED fii TRIGONC~~; I #i #I: W ~I
]j (.103) 296-9645 E N G INEER S & CONSTRUCTORS
•
•
•
OWNER
~
TRACT NO.
R.O.W. WIDTH
ROOS/FT.
UJtlMlM DEPTH
Of C<MR
(f) z
0
f-
~
(f)
f-z w
2 z
C)
_J
<(
w
_J
LL
0
0:::
Q_
7150
-#:-I-EXISTING PIPELINE
-!><I-~~~TlOtl BLOCK _I_ PIPE CHANGE ('.7 ::TE =e= ~~~ LINE
<Yl CATHODIC TEST _.x_ STATION
0 FEOOlAL HIGHWAY =~ ==LINE 0 STATE HIGIM'AY -x-FENCE
~ ::iWi~a SIGN ---88'/!filETEl'ff'E CJ CO IJNTY ROADS -T~~=~ CM!U:
-s--SEWER LI NE C> TRACT NUMBER --w---WATER LINE t EQUATION
..........,_ CONCAETE
WEIGHIB
--· -• -· -· ACC£SS ROAD --o--CA8U
-11/W--RIGHT OF WAY
llUI
0:::)
5'1'-ROW
JOU6 -
/IJISIHf: !Ml(
/
,,_ a. ._,_ a. ..... "' ""
a. _ ..
...,_ .. _ ..
.... -r""°'
·-
C) g
+ .....
M
c
0
~
12 Porcupin e Alignment
•
•
•
OWNER
&
lRACT NO.
R.O.W. WIDTH
ROOS/FT.
Ml,_.. OEPlll
OF C<MR
U1 z
0
~
I-
U1
w
_J
LL
0
Ct:
CL --
~
Ii!
!:!
i
<I ..
~
i
"' !
I
~ EXISTING PIPELINE
~ . ISOLATION BLOCK _j_ PIPE ctwlGE f""I 1'1TERSTATE -·---C/L ROAD
--.....,-V'l..1/£. V HIQNIAY -t-PR()PERTY LINE
ffi CATHODIC TEST
___I.__ STATION
-=-CASING 0 f"EOCR>L HIGHWAY =~= =: WIE
Q STATE HIGHWAY -x (tJND:UNO) ~ ~ SIGN ._..,.. =ET~PE CJ COUNTY R<W>S -T-TELEJ>HONE CABLE
-s--SEWER LI NE ..__.. ~m 0 TflACT NUMBER --w--WATER LI NE
-0--CASI.£
-R/'fl--RIGHT Of WAY
EQUATION
-·-·---AC<::ESS ROAD
rt.II
CV
SO'-l!Oli (Coe ___ ,)
~ ~ I
-_,..
C>
¥!-ROW --
~ !
" Ii!
! ~ ~ ii i
<I <I
~ I ::i ~
o!
/--/
•fa< _,.,_
l/a4
1llLE DA1E
i ~
" b i ~
<I
!
o!
Cl __,,.,, _ ... -..
Cl
a. ......
II' --, . ....,.
!
,,,.,,.
12" Porcupin e Alignm ent
----1944-01 01 94401-500 Sheet 2
...
A
•
•
•
OWNER
&
TRACT NO.
R.o.w. wumt
ROOS/FT.
..-... llEPTH
OF C<MJ!
U1 z
0
~
U1
f-z w
2 z
C)
_J
<t::
_J
<t::
0:::: w
~
2
0
0
0 + .....
U)
c:
0 :;:
l'O ....
Cl)
Cl>
.5 ::c: '
(.) -l'O ::e
~
-s-,.
CJ:)
"1 ... ROll Coi-nn-
I I I i !l . Ii i i
" Ii! " " " Ii! ,, " ; ~ ~ ~ ~ ~ ; lt i I i " • Ii .. .. .. .. .. .. <I .. .. .. t i! i j i ~ ! ~ ~ i a ;! I ~ ~ ~ ~ ~ ~ ~ ~
0 c:>
0 + ...-en
c:
i~
.5
Cl)
Cl> c:
::c:
(.) -l'O
::::&
i ..
i v mslN& -j /
lll +oO 90+~
i i
.. .._11'COo~ .. l ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~i
i I
~ EXJSTING PtPEUNE
~ ISOLAJlON BLOCK _j_ PIP!: CHANGE f""l INTERSTATE ---·--C/L ROAi>
---.-.---Vl<J..VE V HIGHWAY -t-PROf'ERIY LI NE
•/1ll04 -""
(T) CAJliOOIC TEST _:r:._ STAllON
~~=SI GN
t EQUATION
0 F£DERAl HIGHWAY =~= =~ UHE
0 STATE HIGHWAY -x-f£NCE
---~PE CJ COU NTY ROADS -T (~~ CA8U
-s--SEWER UN£
.........,_ ~'if£E C) TRACT NUMBER -w--WATER LINE
-c--C>.81.E
-R/111-RIGHT OF WAY -·---·-ACa:SS ROAD
........... 12 Porcupin e Alignment
•/1ll04 a. --.. Goo -°""I -.,..... a.
.... NO. mu: .. ,. -0194401 -500 Shee t 3 A
•
•
•
OWNER
&
lRACT NO.
R.o.w. WIDTH
ROOS/n .
""' ....... D£PIH OF ClMR
(f) z
0
I-~
(f)
1-z w
2 z
(.'.)
_J
<(
w
_J
LL
0 n::::
()__
i ..
I
j
.. s...
C0
JO'W.R!IW
(Orii'nid --2}
i\ ~ ~
!:I !:I !:I
! ~ "' .. .. ..
i i I
o! o! o!
-
llUI
C2::)
SO' lldt ROii
1116.7, liq
------; ! ~ M !
"'· "' "' !:I "' § I \t ! e I ! I .. ~ ei I!! .. .. .. .. .. ..
il -j Si ; ~ ! I
i ii ! i I! o! ~ o! o! o! ~ :I
/~ CRMI(
115«<! n MO
! i i 1 -~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Pripoood~~1 2"_~~P\l0h~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~---j1
i I
__,_,,,.._ EXISTING PIPEUNE
~ ~~ BLOCK _L PIPE QWIGE (j ::TE :=._, -~ IJN£
a. .,,... ..........
(i) CAniOOIC TEST -=-CASING Q FEDERAi. HIGHWAY ~ :o'i:': LINE
__:r_ STATION O x FENCE
Is} PIPEUN£ _........,.. COtlCllOE STATE HIGHWAY -(UNOERGROIJHO)
___:r__ WARNING SIGN COATED PIPE c::::J COUNTY ROADS -T--TElEPHONE CIBLE
-s-SE:"tllER LINE
-eeee-~<;:WE 0 TRACT NUMBER ----WATER LI NE
---c-CABLE
-!VW-RIGHT Of WAY
........
.......... ,,_ a.
•/2004 a. ... ,, .., °"' -,. ......
12" Porcupin e Alignm ent
EOUATION
_ ... _ --1944-01 0'194401-500 Sheet 4 --· ---· --ACCESS ROAD .... NO.
....
A
•
•
•
OWN ER
&
TRACT t<O.
R.o.w. W1UTH
ROOS/FT.
t.lfNUM DEPTH
Of COVER
(/)
z
0
~
(/)
I-z w
2 z
C5
_J
<(
w
_J
LL
0
0:::
Q_
I
I
I
1100
OlQ
121+00
II.II
c:z:>
~-ROt'
(C.0_...,_4)
,,
~ I;;
<!
i E
;!
i
j
i
123+«1 125+00 127+oo
ti fi ft
"' ~ g
~ <I i I t ;;!
. c:>
c:> c:> +
'N ll')
~
Cl> ·= :c
(,) .....
"' ::E
5
5
;--II.Ill: ~~ a ----I
141ttl0 -
I ! JI ,._,!"Qi,"""" a1 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~--1f
I I
~ EXISTING PIPEUNE
-M-~~OON BlO\,"K _j_ PIPE CHANGE (j =~TE =-e:= ~ LI NE
(f) CATHODIC TEST _:r__ STATION
-=-CASING Q FEDERAL HIGHWAY =~ :c::IE UN£
Q STATE HIGHWAY -x-f'ENC£
(s) .._ go ~-li!bETE (UNDERGROU ND)
_:r__ ~ SIGN QA PIPE CJ COU NTY ROOlS -T-TELEPH ONE CAB LE -s--SEWER LI NE
.............. ~E 0 TRACT HUMB ER --w--WATER LINE
--<:-CABLE
--• -• -• -ACCESS ROAD -ft/W-RIGHT OF WAY
EQUATI ON
-ND.
a. _ ...
_..._ ...
-... .. 12 " Porcupin e Alignm ent .......... _
a.
a.
_,..._ --.. NO. .... " 0194401 -500 Sheet 5 A
/
•
OWNER
&
TRACT NO.
R.0.'11. W1DTH
ROOS/FT.
MINIMUM: C£PTH
Of C011ER
a
ff)
" !:> z ~ i 5 0 !!
f-I .. ..
~ .. i ff) I i
;;!
f-z w
2 z 0
0 C) c::>
_J + N
<( II') .....
c
0 :o:; .e rn
Q) c:
:c: u .... ca
:iE
7250 w
_J ! LL
0 i -er:: i Q_
M50
~ EXISTING P!Pa!NE
-!><}---ISOUITION BLOCK _j_ PIPE CHANGE
VAi.YE (j ~~:TE ::;-·-~~ LINE
cD CATttO!llC TEST
_)'._STATION
Is) PIPELINE
_)'._ WMNING SIGN
t EOU4.TION
__. CONCRETE
0 F'EDERAL HIGHWAY =~ ~E LINE
0 STATE HIGHWAY -x-F'ENC£
(UNDERGROUND)
-T--TEl.EPHONE CIBlE COATED PIPE 0 COUNTY ROADS
-s--SEWER LINE
---WATER LINE --<:--CAlll.E
-------ACCESS ROA() -R/W --RIGHT Of WAY
-e91Ht-~~ QTRACT HUMBER
n ~ ~
151+m 161+(11)
llll
CD
!511' .... ROii
(Ca!tinoo'1m9*1•)
u i ii i ii il
Ii! !:> "' Ii! !:> !:> !:> Ii!
! ~ e )! ;: ! I i II ~ ii ll .. <I <I .. .. .. I
i a ~ i il i ~ ! ~ ! !! ~ I ;;! ;:! ;:! ;:! ;;! ;:!
.....
/il1S1116 -/
177+11> 111+00
REVISIONS atA•ft
a. ,,.,...
....... "" .........
_,.,,..., 12" Porcupine Alignme nt ,_. Q.
l/>OIM Q. """"
..... NO. Tl1l..E .. ,, "' QI(. -r"""
•
•
•
OW NER a.
1RACT NO.
R.o .w. WIDTH
ROOS/FT.
M ....... DEPTH
OF CXMR
(/) z
0
~
(/)
1---z w
2 z
C)
_J
<(
_J
<(
0::: w
~
2
~
'· -212+oo
i ii
I
I
i
-M-ISOLATION BLOCK _j_ PIPE CtWKl£
VALVE
i CATHOOIC TEST -=-CASlllG
STATION
~ PIPEUHE WARNI NG SIG N ---~~
----CONCRETE EOVATION ~CKTS
i ~ ~
,, ,,
~ ll i
<I <I
I il
!
;;!
~ -
~ EXISTING P1PEUNE
" INTERSTATE ---C/L ROAD
HIGtrNAY -e--PROPERTY LINE
0 _,.__ POWER LINE
FEDERAL HIGHWAY -r-TEl.!PHONE LI NE
0 STATE HIGHWAY -x-FENCE
(U NOERGROU NO)
Cl COUNTY ROAOS -r-TELEPHONI: CABLE
0 TTW:T NU MB ER
-->--SEWER LI NE
--w--WAltR UN[ • --o--CASl£ -----·-ACC(SS RO AO -1\/W--RIGHT Of WAY
IUI
G:>
SO'-liOW
(Conhodhm91eot4)
Ull!i B
Raia ,, R
~ .. j .. ~ • ~·~ 5
<I
UH ii ~ ~
o!ltdlt ;;! ;;!
/IJISlllC -/
ttQIES;.
,,_,,,
......... _..,
_,,,, 12" Porcupin e Alignm ent
.,_ a. ........ a. --.. -... .., DIC. Ifft . 0194401 -500 Sh eet 8 A
•
•
•
OWNER
&
TRACT NO.
R.O.W. WID!li
ROOS/FT.
.. .......... DE1'IH
OF covm
(/) z
0
I-
<(
I-
(/)
1-z w
2 z
C)
_J
<(
w
_J
LL
0
0::::
0....
i
I
I
-
~ E 6 ~ !! ~
Ii! ,, ,, Ii!
i t
<I <I <I
I i I jl
i
;I ;I
/1l1S11111
--
llM
C0
SO' W1dl IQ (-"""-•)
~ I I 1J I
.. .. .. .. ,,
~ l ~ l g
I ~
<I <I <I <I <I
I i ~ i i i
I ;I ;I ;I
----
llRAllE i ..
K
i --210+00
_J
<( I i
t 1--------------------------------------------------P1,,...i--1r_Ga1_,,..... ___________________________________________________ -; i 0:::: w
~
2 I I
~ El<ISTTHG PIPWNE
ISOLATION BLOCK _j_ f""I INTERSTATE ---C/L ROAD -l><t-VALVE PIPE CHANGE V HIGHWAY -t-PROPERTY IJN£
(i') CATHODIC TEST _:r_ STATION
{s) PIPELINE _:r_ WAAt~IHG SIGN
EQUATION
Q FEDERAi. H IGHWAY=~ =~EUHE
Q STATE HIGHWAY -x-FD4C£
---~~~PE CJ COUNTY ROADS -r (~~CABLE
-s-SOl(R UN£
-eeee-~~ETE 0 TRACT NUMBER _,.__ WATER UNE
~ CABU: ---• ----ACCESS ROAD -ft/oW--RIGHT Of WAY
REVISIONS 41<!\Tn.. _ ..
G"'S ~E f>OUl>C f;6 , I NC:: __ .. _ ... 12" Porcupin e Alignment
---IMO.HO. ..,. 01 94401-500 Sheet 7 A
• APPENDIX B PERMITS
•
•
•
•
•
BLM Right-of-Way Grant with Stipulations and Notice to Proceed
To be inserted upon receipt .
•
•
•
Garfield County Special Use Permit and Conditions
To be inserted upon receipt .
•
•
•
Co lorado General Construction Stormwater Permit and Conditions
To be inserted upon receipt .
'1.; •I ·<t"1~ It '-~ 'l(• :-' ' • . • ' ti~ •• ~-' f: ' ' t.~~\ ; • • .<J ,' ji-<. ' ' • ' ' -: : '' ' ' . "! ' .. ·:-. . ·"" . » · . , ; ·. : .... "" ;: .:' · , ,.,1{") • 1 .••• Your Pipeline ,To The Future ..
• ;. • , ~ ' ' •• ~ ~ .. •• \ '1 ' • .. '• f •• • • ... ... • -~ •
ENGINEERS & CONSTRUCTORS
•
July 8 , 2004
Colorado Department of Public Health and Environment
Water Q ua lity Contro l Divis ion
WQCD-Permits
4300 Cherry Creek Drive South
Denver, CO 80246 -1530
To Whom It May Concern:
Oil & G as P1pe i.,,es
Telecommun1cat1ons
Facd 1t1es
Survey ing
Pe rm1:-t1ng
Land Services
Engineering
Desig n
Procurement
Const;uct1cn
Field Ser·11ces
Canyon Gas Resources , LLC has reta in ed the services of Trigon-Sheehan, LLC to comp lete the permit
process for the Porcup in e Loop Pip e lin e Proj ect. Enclosed is the Genera l Permit Application for the
proj ect. A Storm w at e r Manageme nt Plan has been developed and is ava il ab le at your request.
Please ca ll me if you have any quest ions or requ ire addit iona l information.
Brenda Lin ster Herndon
W estern Slop e E nvironm enta l, Permitting, a nd RO W Coord in ator
Enclosure
• D E N V E R ~.\ E E f\ c R D U R A N G
532 Main Street . Suite 23 (p hy s ica l)• P 0 . Box 436 (mil din g ,1 • i,\eeker CO 8 1641 •Phone 970 i 878-9838 • rax 970/878-5288
GENE RA L P ERMIT AP PLIC ATION • ST ORMW AT ER DI SC HA RGES
ASSOCIATED WITH:
CONSTRUCTION ACTIVITY
For Age nc y Use Only
COR -03 ___ _
Year
Date Receive d
Month Day
(Permit No. COR-030000) C od e: 9A 9B 9C(l) 9D(2) 9E (3) 9F (4)
Please print or type. A ll it em s m ust be co m p lete d accurate ly an d in their entirety or th e ap pli cati on wi ll be dee med inco mplete and
pro cess in g o f the permit wi ll no t begin unti l a ll informatio n is received. Please refer to the instructions for informati on ab out the
re qui re d it ems. An origi na l signatu re of th e app li cant is required.
I. Name and address of the permit applicant:
Company N ame Ca n yon Gas Reso u rces, L L C
Mailing Address 7400 E . Orc h ar d Roa d, S uit e 3 0 25
City, Sta te and Z ip Cod e E n glewood, CO 8 0111
Phon e Nu mb er (3 0 3 ) 2 2 2 -6 2 1 8 Who is app lying? Owner @ Deve lop er 0 Contrac t or D
• Federal Tax pa yer (o r Emplo ye r) ID #: i.._ .!{ -_!_ £.. L L _J_ .Q_ _£__
Enti ty T ype: Pri va te [}: Federa l 0 S tat e D C oun ty D City D Oth er:-----------
Loca l Co ntact (fam ili ar with fac ili ty ) Art S mith
Tit le P ro j ec t E n gi n eer P hon e N umb er (3 0 3 ) 22 2-6 2 18
2. Location of t h e construction site:
StreetAdd ress linear pipe l ine project between Garf i e l d County roads 350 & 31 7
City, State and Z ip Co de
Co unty Garfield
La titud e an d Long itu de
so u t h west of R i fle, CO 8165 0
Nameofp lanordevelopment Porcupine Loop Pipelin e P roject
107 .86 a n d 39 .46
3. Briefly describe the nature of the construction activity:
P l ease see attac hm en t
•
2/0 2/c o n s t -1-
Anticipated construction schedule (SEE INSTRUCTIONS!):
Commencement date: 08/01/0 4 Comp letion date: 04/01/0 5
5. Area of the construction site:
Total area of project site (acres) 29.1
Area of project site to undergo disturbance (acres) 29.1
If project site is part of a Larger Common P lan of Development or Sale, total area of common plan to undergo disturbance
(see Instructions) N _N_o_t __ A-=p-'p=--l_i_c_a_b_l_e ______________________ _
6. The name of the receiving stream(s). (If discharge is to a ditch or storm sewer, also include the name of th e ultimate
7.
•
receiving water): Porcupine Loop, tributary to Porcupine Creek,
tributary to Spruce Creek (2), ultimate receiving water is
Colorado River
Stormwater Management Plan Certification:
"I certify und er penalty of law th at a comp lete Stonnwater Management Plan . as descri bed in Appendix A of th is
app llcation . has been prepared for my facility. Based on my inquiry of the person or persons who manage th e system, or
those persons directly responsible for gathering the information , the Storrnwater Management Plan is, to the best of my
knowledge and b e li ef, true , accurate, and comp lete. I am a ware that there are signific a nt penalti es for falsely certifying
the comp letion said SWMP, including th e possibility of fin e and impri sonment for knowing vio lations."
Signature of App li cant Date S igned
Art S mith Project Engineer
Name (printed) Title
8 . Signature of Applicant (legally responsible person)
•
"I certify under penalty of law that I have personally examined and am familiar with the information submitted in this
application and all attachments and that, based on my inquiry of those individuals immediate ly respons ibl e for obtain in g the
informallon, I be · ye that the mforrnat10n i s true, accurate and comp lete . I am aware that there are s ignificant penalties
foe rnbm>tun ;;:i(o m~7 md ding tho po"ibdity of fino oc tmpn'Onmont"
~ ·1 :~/ j 2<Jvl-/
Signature of App lic ant Date Signed
Art Smith Pr o j ect Engineer
Name (printed) Title
2/02 /co nst -2-
• PROJECT DESCRIPTION
•
•
Canyon Gas Resources, LLC (CGR) has applied to the Bureau of Land Management
(BLM) for a right-of-way grant under Sect ion 28 of the Mineral Leasing Act of 1920, as
amended, to constru ct, operate, and maintain a 12-inch diameter natural gas pipeline and
related facilities in Garfield County, Colorado. The proposed pipeline project would loop
an existing CGR 6-inch diameter natural gas pipeline and would connect CGR's Bentley
and Porcupine Gathering Systems. The pipeline would transport existing and future
natural gas produced by Tom Brown, Inc. (TBI) in the Rifle, Colorado area for
processing at the Rifle Clough Compressor Station. TBI plans to drill more than 40 new
we ll s in 2 004, all of which are dedicated to CGR's gathering systems. Production from
these wells is expected to increase by 35 mmscf/d, increasing total throughput from 15
mmscf/d to 50 mmscf/d. System throughput will increase to 100 mmscf/d in the next four
years. The proposed pipeline will de -bottleneck the existing gathering systems and will
ensure sufficient capacity to carry CGR' s current projection of future gas volumes.
T he project is approximately 4.3 miles in length, of which 0.8 miles are located on fee-
lands and 3.5 miles are lo cated on BLM lands administered by the G lenwood Springs
Fie ld Office . The project is lo cated so uth and west of Rifle, Colorado in Sections 1, 9, 10,
11, and 12 of Township 7 So uth , Range 94 West in th e R ulison and North Marnm Peak
· USGS Quadrangles .
CGR will design and build the pipeline in accordance with the National E lectrical Code,
Department of Transportation, Title 40 CFR Part 192 , and ASME B3 l .8 standards.
Facilities will be designed, constructed, and operated in comp lianc e with the
Occ upation al Health and Safe ty Act (OSHA) regulations pertaining to pipe lin e
c onstruction and operation.
The right-of-way construction width will be 50 feet. A launcher and receiver will be located
at opposite ends of the pipeline, with risers, blow-downs, and valve sets where appropriate
a lon g the right-of-way.
CONSTRUCTION SEQUENCE
Construction activities are expected to be completed in 4 to 6 weeks and are scheduled
for summer or fall 2004.
The standard open cut construction method will be used to install the pipeline . This
method includes clearing, grading, trenching, pipe stringing, pipe bending, welding, joint
coating, padding where required, lowering-in, backfilling, pneumatic testing, cleanup,
an d revege t ation.
C learing, topsoiling and grading wi ll be limited to the minimum area required for safe
and efficient cons tru ction. C learing will b e performed only to the ex te nt necessary to
allow for construction activities . The ground surface will not be grubbed or cleared of
vegetation less than four inch es in he ight when possible. Every effort will b e made to
CGR Porcupine Loop Pipeline Proj ect -3-Attachment to General Pennit Application
•
•
•
salvage root system s. Large vegetation, such as trees and shrubs, will be cleared from the
right-of-way and stockpiled or windrowed at the edge of the approved workspace for
later us e in reclamation.
Topso il will b e removed and s to ckpi led. Where topsoil is availabl e, the top 4 to 6 inches
of soil will be removed over the trenchline and in areas requiring grading. Topsoi l and
cleared vegetatio n will be stockpi l ed together on BLM lands. Topsoil will be stockpi led
separat e from c leared vegetation on fee-lands. The right-of-way wi ll be graded only to
the extent necessary to create safe and e fficient pipe line installation conditions. Topsoil
wi ll not be sa lvaged over the existing CGR pipelines.
The ditch wi ll be excavated and s loped in accordance with OSHA specifications. The
cover from top of pipe to ground level as graded to pre-cons truction contours will be in
conformance with DOT regulations. Cover will typically be 36-inches in depth. Greater
depths of cover will be required at road crossings, foreign pipeline crossings, and
waterbodies. As a minimum, the ditch wi ll be excavated to a depth to a ll ow a clearance of
18 inc h es between th e CGR pipe lin e and other pipelines or underground fac iliti es.
Machine excavation will not be performed closer than 5 feet from any ex isting pipeline
encount ered in the ROW unless a uthori ze d by the pipeline owners/operators. Existing
pipeline lo cations will be marked in the field and 48-hour prior notification given to the
·op erator of the und erground utility .
Where rock is encountered, tractor-mounted mechanical nppers or rock trenchin g
equ ipm ent may b e used to facilitate excavati on.
The trenc h will be excavated an d sub so il material stockp il ed s eparatel y from topsoil
stockpil es. Based on field co nditions , ga p s wi ll b e made in topsoil a nd s ubsoil stockpiles
to avo id ponding or excessive divers ion of natura l runoff during storm events.
Pipe install ation wi ll include stringin g, bending for horizontal or vertica l ang les in the
alignment, we lding the pipe segments together, x-ray inspection , coating the joint areas to
prevent corrosion, and then low ering-in and padding as described in greater detail below.
Pipe wi ll be hauled by truck to the pipeline ROW. Each joint of pipe will be unloaded
and placed parallel to the ditch .
After the joints of pipe are strung along the ditch, individual joints of pipe wi ll be bent to
accommodate horizontal and vertical changes in direction. Fie ld bends will be made
utili z ing a hydraulically operated b end ing machine . Where the deflection of a bend
excee ds th e all owab le limits for a field -be nt p ip e, fac t ory (induction) bends wi ll be
installed.
A ft er t h e pip e joints are bent, the pip e is lin ed up end -to -end and clamped in-,o position.
The pip e i s th en w e ld ed in conformance with 49 CFR Part 192, Subp art E. "Welding of
Stee l Pipelines" and API 1104, "Standard for We ldin g Pipelines and Related Faci lities ".
CGR Porcup ine Loop Pipe line Projec t -4 -A n;i c hme nt to Genera l P ermi t Application
•
•
•
Welds will be visually inspected by a qualified inspector and by nondestructive
radiographic methods . At a minimum, radiographic inspection will be conducted in
accordance with DOT requirements . A specialized contractor, certified to perform
radiographic inspection, will be employed to perform this work. Any defects will be
repaired or cut out as required under the specified regulations and standards.
To prevent corrosion, the pipe will be externally coated with fusion bonded epoxy
coating prior to delivery. After welding, field joints will be coated with either tape and
primer or shrink sleeves. Before the pipe is lowered into the ditch, the pipeline coating
will be visually inspected and tested with an electronic detector, and any faults or
scratches will be repaired.
Once the pipe coating operation has been completed, a section of the pipe will be lowered
into the ditch. Side-boom tractors will be used to simultaneously lift the pipe, position it
over the ditch, and lower it in place. Inspection will be conducted to verify that mi.nimum
cover is provided; the trench bottom is free of rocks, debris, etc.; external pipe coating is
not damaged; and the pipe is properly fitted and installed into the ditch. Specialized
padding machines will be used to sift soil fines from the excavated subsoil to provide
rock -free pipeline padding and bedding. In rocky areas, padding material or a rock shield
wi ll be used to protect the pipe . Topsoi l will not be used to pad the pipe.
Backfilling will begin after a section of the pipe has been successfully placed in the ditch
and final inspection has been completed. Backfilling will be conducted using a bulldozer,
rotary auger backfill, padding machine or other suitable equipment. Backfi llin g the trench
w ill generally use the subsoil previously excavated from the trench, except in rocky areas
where imported se lect fill material maybe needed . Backfill will be graded and compacted,
where necessary for ground stability, by being tamped or walked in with a wheeled or
track vehicle. Compaction will be performed to the extent that there are no voids in the
trench . Any excavated materials or materials unfit for backfill will be utilized or properly
disposed of in conformance with app li cable laws or regulations.
Cleanup and restoration will begin as soon as possible after backfill activities are
comp leted. The right-of-way will be graded to the original contours and natural runoff
and drainage patterns will be restored. Topsoil will be redistributed over the trench and
other portions of the right-of-way from which the topsoil was salvaged and permanent
erosion contro l measures will be in stalled. Disturbed areas will be seeded with seed
mixes approved by the BLM and fee -landowner.
CGR Porcupine Loop Pipeline Project -5-Attachment to General Permit Application
•
•
!
~
~
§.
[ZJ//
///
///
·/~//////
/ ,/ ,/ ,/ ,/ ,/ ,/ / ,/ ~. ,/ ~,/ ,/ ,/ ,/ ,/
Project Location
1
j ~L._~~~~~-::::-~~~~~~--i~D E~SCR~l~l~ON~~~~Lo c~ot~ion~M~o~p~~~~~~ ~ CLJEl{f ~ PORC UPINE PIPELINE PROJECT il_~~__:~GAfS~R~ES~OU~RC~E~S=·~·NtC~t-:D=~~N ~BY:~C~L L_~---r=DATE~D~~~N~6/h200004z---i-;mr~~;EfE~xhiliibit\ 1~-AA~ •"lsscCAt£~:~N~TS~---=~~R~rn~s10N~:~~~__L:::_~~m:RIT;-r;-:;:;;~~~~~r§T~iil~jjl
L7uRVEYED BY: TRIGON-SHEEHAN, UC PREPARED BY TRIGON CS§~= I #I :fl: w ~I 34 Von Gordon , Suite 200 ·-__
;_'. Lakewood, Colorodo 80228 E N G I N E E R s & C O N S T R U C T 0 R S i (303) 296 -9645
••
\ .. · ~\
•
. } . .......
~ CUENT
\'. / \ !!.= . .i:. ·. :::
-...; .
.... J
'.1 •
. '
/
'• '
.( ,'
/
Proposed 12"
Loop Line
Garfield County, Colo_rado
I
3000' 1500'
LEGEND
I
0
DES IGNATES BUR EA U OF
LA ND MA NAGEMEN T LANDS
PROPOSED 12" LOOP LI NE
PROPOSE D ACCESS ROAD
3000' 6000'
SCALE: 1" = 3000'
DESCR PT ION Propo se d Ro ut e
PORCUPINE PIPELIN E PROJ ECT
;V".' •. _'1
'·
./ ..
, ... /' ,,
•!~s~~:L;[;:;;-;;;1~"-=~3ITTO;,OO~·~r;:;~~R~--'~-o~-·-------------'-D-R_Ml_N_~_, __ c_L r;;;;::;~-;--=:O:Af:E ~D~~=WN::-:::6 :/:20~0:4-::;~;;:;F;l~;:;::N~:8;·;E;x;h~ib;it;::;1 ;-;B;:;-"i
5
1 suRlmo sr 2~YE~<l~:~~~t~~~~~ PREPARED BY JRIGQN (Sfu, : I @) tA : W ~ I
~ ..... ______ ...;.o_oJ~)-29_6--9-64_s ______________________________ .a... ________ E_N_G __ 1_N_E __ E_R __ s ___ & ___ c_o __ N_s __ T_R_u __ c __ T_o_R __ s __ __.
•
' .
I '
.,
•'
l !._
t,
I
I
~ CUEN!
v
·. ·+..
'·
,~
-· I ----··>/ . ,/
/,'
,-.
. '.
. r .. ..-----
/
Garfield County, Colorado
LE GEND
DESIGNATES BUREAU OF
LAND MANAGEMENT LAN DS
-11-11-11--11-11-1;-EXISTING CANYON GAS PI PELINE
PROPOSED 12" LOOP LINE
---PROPOSED ACCESS ROAD
.. (
·--
• DESIGNATES TEMPORARY USE AREAS (TIJA)
• DES IGNATES DISTURBED AREAS (DA)
DESCRIPT ION Proposed Route
PORCU PINE PIPELINE PROJECT
' -
·~ .·r"
!.. SCl\l£ : 1 "=800 ' REVISION: ORAw11 fJY: CL DATE DRAWN: 6/2004 rLE 11AME: Exhibit 1-C ~~s-u-~-,8-10--8 r-.--E-:-~-~-J-~-~H-£-~-~~~-J-~----------------__. ________ ....,._ffi-,E-PA-RE-D-~---._..._ll __ l __ Cl __ () ___ l\l ___ c __ ~---_-~~--;-1--;t--~--=--i-~-,--~--,--t
~ ..... ______ ...;..(Jill...;..)_29_6--9-64_s ______________________________ ._ _______ E __ N_G_1_N __ E_E __ R_s ___ & ___ c __ o_N __ s_T_R __ u __ c _T_o __ R_s ____ _.
.. --
. .,; •. \.f....' ' _, . } ·. c ' '! ~~--::~·s:~~~:;;!~:f~~;~$?~~-
,...
~-. ..~ ~
'.. --... : .• '! :.. --. ,·
-·--....... ::'.
Garfield County, Colorado
~ CUENT
~AR Alrl!IOURDl!S , I ND
} S~LE : 1 "==800 ' REV ISION:
SURVf!EO BY: TRIG[J\/-SffiHAN, LLC
LEGEND
DESIGNATES BUREAU OF
LAND MANAGEMENT LANDS
-1,_,_,, __ ,, _ _,,_,,_ EXIST IN G CANYON GAS PIPELINE
PROPOSED 12° LOOP UNE
---PROPOSED ACCES S ROAD
• DES IGNATES TEMPORARY USE AREAS (TUA}
DESCRIPTION Proposed Ro ul e
PORCUP INE PIPELINE PROJECT
DRAWN IJY: CL DATE OOAWM 6/2004
PREPAR ED ffY
..
'>
\
"" ·,
\ \
• l
\ \
34 Von Gordon , Su ile 200
Lakewood , Colorado 80228
(303) 296-96 45 CONSTR U CTORS
~ CUENT
LEGEND
DES IGNATES BUREAU OF
LAND MANAGEMENT LANDS
_,, __ _,,, __ ,,, __ ,,_,,_,,_ EX IST ING CA NYON GAS PIPE LIN E
PR OPOSED 1 t' LOOP LIN E
-----PROPOSED .A.CCESS ROAD
• DES IGNATES TEMPORARY USE AREAS (ll.JA)
9 DESIGNATES DI STURBED AREA S (DA)
OESCRiP1 10N Proposed Ro ute
PORCUPINE PIPELINE PROJEC T
•~.~_. i-S C-~L_[_, __ 1'_' =_s_o_o_· ----'--REV-ISi-ON_: ______ __._o_RA_w_N_BY_:_c_L_PR_E_PA_R_ED_DY __ T.._oR_AT_E _DAAl_G_wN_: _0_6 _/_2No_o_4_'-~~~~~:~~~~~~~~~~~~~~~--t
SURVffID SY : IRIGON --StHHAN, LLC 0 1
34 Von Gordon, Su ile 200
3· Lakew ood, Colorado 80228
~.__ ___ ....;(-30~3J_2_96_--_96_4_s __________________ ...... _______ E_N_G_I _N_E_E_R __ s_& __ c_o_N_S_T_R_u_c _r_o_R __ s _ __,
! SCALE : 1 "=8 00 ' REVISION:
•
SURVEYED B\': TRIGON-SHEEHAN , LLC
34 Von Gordon, Su ile 200
[;° Lakewoo d, Colorado 80228
~ (3 03) 296-9645
LEGEND
DESIGNATES BUREAU OF
LAND MANAGEMENT LANDS
_,,_,,_,;-.:.,1--1,_.,,_ EXISTING CANYON GAS PIPE LIN E
PROPOSED 1z• LOOP LINE
---PROPOSED ACCESS ROAD
• DES IGNATES TEMPORARY USE AREAS (TUA)
9 DES IGNATES DISTURBED AREAS (DA)
OESCRPTION Proposed Route
PORCUP INE PIPELINE PROJECT
DRAWN BY: CL DATE ~: 6/2004 fli NAME: Ex hib it 1-F
ffiE PARED BY TRIGON (S]k~; I ;1 :t: w ~I
E NGIN E E RS & C ON S TRU CT O RS
•
•
•
Colorado Dewatering Industrial Wastewater Discharge Permit and Conditions
To be inserted upon receipt .
TRIGON e:--'1: I ;1 =I: '111 ~I >~ -· < ·:, · > ~"..: (" :·,_,--,· , • , ::-; ·i ,, , " · -: ,: '! :·vour Pipeline To The Future
'f-~ f • 't , " • : I > • •
ENG I NE E RS & CONSTRUCTO RS
•• 20 04
~o l orado De partment of Pub lic Hea lth a nd En vironm e nt
WQCD-P-82
4300 Che rry Creek Drive South
Denver, CO 80246-1530
To Whom It May Concern:
Oil & Gas P1pel1nes
Tel ecommun1ca t1ons
Facrh!!es
Surveying
Perm1 tt1ng
Land Services
Engineering
Design
Procurement
Construction
Field Ser',1ces
Canyon Gas Resources , LLC has retained the services of Trigon -Sheehan, LLC to comp lete the permit
process for the Porcupine Loop Pipeline Project. Enclosed are two copies of the Construction Dewatering -
lndustria l Wastewater Discharge Appl ication.
Please ca ll me if you have any questions or require additional information.
da Linster Herndon
,.;s t e rn S lope E nv ironmenta l, Permitting, a nd ROW Coordinato r
Encl os ure
• D:ONVER M E E K E R D U R A N G C
532 Main S tr eet. Su it e 23 (p hy sical)• P 0 Box 436 (mai ling)• Meeke r, CO 8 1641 •Pho n e 970i878·9838 •Fax 9701878-5288
FOR AGENCY USE ONLY
CONSTRUCTION DEWA TERING-
INDUSTRIAL WASTEWATER DISCHARGE APPLICATION
PERMIT NUMBER
c 0 0 7
DA TE RECEIVED
YEAR MONTH
Do not attempt to complete this form before reading the accompanying instructions. PLEASE PRINT OR TYPE
§NEW OR D RENEWAL -EXISTING PERMIT NO.----------
I. Is application for a short-term certification (certification wi ll only be effective for no more than I year after issuance)?
OR
Is application for a regular term certification (certification will be effective for 5 years from issuance)? D
2. Specify whether owner or operator is making application for the permit: GJ OWNER D OPERA TOR
DAY
3. Name, address, and telep hon e number of the person or persons that are responsible for the permit, and to whom this permit should be
sent. Note: The person or persons th at are responsibl e for th e permit w ill be req uired to sign Item 2 1 of thi s application.
•
Co mp any Name Canyon Gas Resources, LLC
lndividual'sName Art S mith
Project Name Porcupine L oop Pipeline Project
FEDERAL TAXPAYER J.D. NUMBER[l] [2) [ZJ [I] [l] [I] [1j [£] W
Facility Name Not Appl i cable
MailingAddress 7400 E~ Orchard Road, Suite 3025
Street Address 7400 E . Orchard Road, Suite 3025
City Englewood
County Arapahoe
State CO E-mail as mi th@can terana t ura lg as . com
Zip Code 80111
Telephone Nu~ber (3 0 ~ 2 2 2 -6 218 Fax. No}03) 222 -6206
4. Name, address , and te lephone number of the owner of the facility producing the discharge.
•
PropertyOwner(s) Canyon Gas Resources, LLC
Fac ilityName N/A --Project name is Porcupine Loop Pipeline Project
Maili ngAddrcss 7400 E. Orchard Road, Suite 3025
StreetAddress 7400 E. Orchard Road, Suite 3025
Ci,y Englewood
Co unt y Arapahoe
State CO E-mail as mith@cant era riaturalgas .co m
Z ipCode 80 111
Te lep hon e N umbe r (3 0 3 2 2 2-6 2 ] 8 Fax. No. (3 0 3 2 2 2 -6 2 0 6
(JJ
5 . Locationoffacility lin ea r p ipe l i n e pro j ect
r oads 350 a n d 31 7
locate d be tw ee n Garf i eld County
Longitude 1 0 7 • 8 6 La titud e 3 9 • 4 6
~----------• Legal d escription (T ow nship , Range, 1/4 Sec tion) __ T_7_s_, __ R_9_4_W_, _s_e_c_t_i _o_n_s _l_, __ 9_, __ l _O_, _l_l _, __ 1_2_
S tree t N/ A County Garf i e ld ---------
C ity SW o f R i fl e S tate_C~O~----Zip Code 8 1 6 5 a
Local C ontact (famili ar w ith fa cility) Art S mi t h
----------------~
Telep hon e N um ber ( 3 0 ~ 2 2 2 -6 218 T itle Project Engineer
Pl ease provide direc ti ons to the operation from a nearby town or landmark.
Fro m I -70,Rifle exit, west on CR 320, south on CR 329,
so u t h west on CR 350 to pipeline rig h t -of -way
6. T yp e o f ac tivity: e .g., bui ldin g construction , gen eral construction, highway bridge and tunnel construction, etc. and a descripti on of acti v ities
b e in g performed , i ncl udin g cons tru c tion schedul e a nd months of operati on . Specify source(s ) of wastewater to be di scharged (i .e. groundwater,
s torm water runoff).
P l ea s e see a t t a c hm ent
•
7 . Do you anti c i pate the need fo r changing or adding the disc harg e poin t(s) as construction progresses? If s o, bri efly exp lain .
Yes . di sc h arge p oi nt s will b e d e t er mine d base d o n s t or mwa t er
an d/or gro un dwa t er acc umul ation i n pipeli n e trenc h .
8 . A location map des ignatin g the fac ility property and di scharge po in ts shall be submitted. The map s hall be from a 7 0 or 15 minute USGS quad
sheet or a map of com parabl e scale. A nonh arrow shall b e shown. Any public water supply intakes within a 5 m il e radi us of the fac ility shall
also be iden tified, if known (see item 20). This map must be on paper 8 Y,x 11 inches.
9. A legible sketch of the site shall be submitted and inc lude appurtenant facilities (bui ldings, ponds, diversion ditches, etc.), stream location,
numbered d ischarge po ints, sampli ng and fl ow monitoring points. Sketch shall be on paper 8 D x 11 inches. Label the outfal ls on the sketch to
correspond with the numbers listed in 10. This map must be on paper 8 Yi xii inches
I 0. W ill the discharge go to a ditch, storm sewer, or any other type of conveyance? D YES fXJ NO
If YES , submit doc umen tat ion that the owner of the ditch , storm sewer, or any other type of conveyance, allows this disc harge. No
certification will be processed unless documentation of approval is received.
11 . Meth o d o f fl ow meas ur ement fo r each disc harge (i.e. 90° v-no tch weir, p ump capacity, parshall fl ume, etc.). Designate wheth er currently
in s tall ed or p roposed .
p ump capac it y, proposed
• 2. Do yo u have bulk s to rage o f di ese l fu el, gaso lin e, solv ent s, or oth er hazardo us m aterials on s ite? @ YES D N O
(4)
13 . For each outfa ll provid e in th e ta bl e below, includ e t he foll owin g : (1) The average a nd maximum flo w ex pected from each outfall ; (2 ) A
• di scuss io n of the m e thod used to m eet penni t effl ue nt limits, (3) The n a m e of the receiving stream . In di cate fl ow rates as gpm or MGD.
OUTFALL TREAT MEN T AND FLOW
RECEIVING STREAM
NUMBER
TREATMENT AVG.FLOW MAX.FLOW
001 * Gro und wa t er wil l be var i ab l e varia bl e Depe n di n g u po n di s c h arge
movi n g di s h araed to a s t a bl e , l ocat i o n, mav be
b ased or well-veqetated u p l a n d Porcupine Creek,
acc um -site t r i butary to P orc u ine
ul a t io n Cree k, or t r ibu tar' t o
i n oi oe l in e tLe n c h Spruce Cree k (2 ).
14. Artaly ttc a l a ata tor th e toll o wing parameters s h all b e submitted fro m at least one sam p li ng of each di scharge point. See ins truc tions . If no water
•
is currently a v a il a ble for a nalys is, so indi ca te. U 1 t i ma t e rec e i v i n g water
___ Alkali n ity (mg/I) ___ O il & Grease (mg/I) i s th e CO 1 o r ado R i Ve r .
__ p H (s .u .) ___ COD (mg/I )
___ To ta l S uspended Solids (mg/I ) ___ Total Di sso lved Solids (m g/I )
___ N o wate r to a n a lyz e a t this tim e .
The D iv is ion m ay re quest ana lysis of o ther parameters once the app li cati o n h as been revi ewed .
Wit h t he exceptio n o f the
Co l or a do River , al l
wat e rbo d ies are expected
to be dry at t h e ti me of
c o n struct i o n .
No te t o t h e a ppli cant: If th e D iv ision reques ts a repre sentative a na lys is of th e w a ter which will b e di scharged , the a ppli c a t io n process t im e
m ay be le ngthened.
15. ls or w ill la nd a pplication o f a n y was iewater be prac ti ced for purposes o th er than reclamation or dust contro l? G:J YES DNo
W ill there be a d isc ha rge fro m thi s area? Q YES 0 NO See above
16 . ls thi s operation located withi n one mile of a landfi ll , or a ny mi n e or m ill tai li ngs? OYEs QNo
Wi ll dewatering take p lace on the site of an abandoned landfi ll ? DYES Gal NO
Has the dewatering area been checked for possible groundwater contamination, such as p lumes from leaking
undergro und storage tanks, etc?
DYEs ~NO
If YES, pl ease sh ow locati o n o f the landfi ll , ta ilin gs, o r possibl e groun d water contam inati on on th e locat ion map (7) o r general sketc h m a p (8 ).
P lease ex p la in the locati o n , extent o f contami nat io n, a nd possibl e effec t o n th e gro undwater p um p ing from thi s fac ili ty, p lease s ubmi t ana lys is of
th e p aram e te r s . Note: Please contact Water Quality Control Division for the proper parameters to report.
No t App l i cab l e
•
Note t o the applicant: If th e Di vis io n mus t re ques t a re presenta.ti ve a n a ly s is of th e water to be d ischarg e d , th e a p p li cati o n proc ess time m ay b e
le ngthe ned.
(5 )
17. W ill tlo ccul ants (se nlin g age nt s or chemi ca l addi tiv es) be use d to tr ea t wa ter prior to disch arge? DYES
If YES, spec ify ch emica l used and s ubmit Materials Safety Data Sheet (MS DS).
• Not App li cab l e
18. Estimate how long the dewatering will las t ___ Years ___ Mon th s. xx H ours
19. Wh en will co nstru ction anddewa terin g beg in? s umm er or fal l 2 00 4
20 . Are th ere dow nstr ea m wa ter suppl y inta kes w ith in 5 mil es of th is fac ili ty? D YES G1 NO
If YES, spec ify name(s) of ow ners o f wa ter s uppl y int ake (i f kno w n)
N ot App li cab l e
21. Do yo u have any oth er environm ental pennits und er any of th e fo ll owin g programs?
Pe nnit Name Yes No Appli ed Fo r , Dat e
Colorado Di vision of M in erals and Geo logy (formerly
MLRD ) xx
Undergroun d Inj ec tion Contro l xx
Dr edge or fill permit und er Section 404 of th e Clea n Wa ter
Ac t (CWA ) (Arm y C orps o f Engin eers ) xx
Res ou rce Con serva tion and Reco very Act (RCRA ) xx
COPS S tonn wa ter xx 0 7/0 9 /0 4
Colorado State Air Po ll ution Emission xx 0 7 /0 9 /0 4
Oth er xx
NO
Pe nnit No.
22 . I ce rti fy und er pena lty of law th at I h ave perso nall y exam in ed and am fam ili ar wi th th e info nnati on s ubmined in thi s app li ca tio n an d all attac hm ents
and that, based on my in qui ry of those indivi du als imm ed iately responsib le for obta ini ng the infonnation, I beli eve that the information is true,
acc ura te and comp lete. I am aware that there are significant penalties for submining fa lse information, incl uding the possibi li ty of fine or
1mpnsonment. /
''''"'=ofOwnoc(<) /IZ::;_ ~ D"oSignOO E7 2, 20IJ'/
Name (pri nt ed) __ A_r_t_~_S_m_1..,,.· q.t_h_(_C'_~-_-/_--~--------Title Project Engineer
S igna tur eo f 0perator __ 6(5 _____ ~--.... ~ )'--"~ _______ Date Signed J7i ly Z 2~1 'I
Name (pri nted) Art S m i th ____ Titl e __ P _r_o-=.j _e_c_t_E_n-'g"--i_n_e_e_r _______ _
•
(6)
• PROJECT DESCRIPTION
•
•
Canyo n Gas Resources, LLC (CGR) h as ap plie d to the Bureau of Land Management
(BLM) for a right -of-way grant under Section 2 8 of the Mineral Leasing Act of 192 0 , as
amended, to construct, operate, and maintain a 12 -inch diameter natural gas pipe line and
related faci lit ies in Garfield County, Colorado. The proposed pipeline project would loop
an existing CGR 6-inch diameter natural gas pipeline and would co nn ect CGR's Bentley
and Porcupine Gathering Systems. The pipeline would transport existing and future
natural gas produced by Tom Brown, Inc. (TBI) in the Rifle, Colorado area for
processing at the Rifle Clou gh Compressor Station. TBI plans to drill more than 40 new
wells in 20 04 , all of which are dedicated to CGR's gathering systems. Production from
these w e ll s is expected to increase by 35 mmscf/d, increasing total throughput from 15
mmscf/d to 50 mmsc£'d. System throughput will increase to 100 mmsc£'d in the next four
years. The proposed pipeline will de-bott leneck the existing gathering systems and will
ensure sufficient capacity to carry CGR's current projection of future gas volumes.
The project is approximately 4.3 mi les in length, of which 0 .8 miles are lo cated on fee-
lands and 3 .5 miles are located on BLM lands administered by the G lenwood Springs
Fie ld Office. The proj ect is located south and west of Rifle, Colorado in Sections 1, 9, 10,
11, and 12 of Township 7 South , Range 94 West in the Ru li son and North Mamm Peak
USGS Quadrangles.
CGR wi ll d esign and bui ld the pipe li ne in accordance with the National E lec trica l Code,
Department of Transportation, T itl e 4 0 CFR Part 192, and ASME B31.8 standards .
Fac ili t ies will be designed, constructed, and operated in comp li ance wi th the
Occupational Health and Safety Act (OSHA) regulations pertaining to pipeline
co nstruction and operation.
The right-of-way construction width will be 50 feet. A launcher and receiver will be located
at opposite ends of the pipeline, with risers, blow-downs, and valve sets where appropriate
along the right-of-way.
CONSTRUCTION SEQUENCE
Construction activities are expected to be completed in 4 to 6 weeks and are scheduled
for summer or fall 2004.
The standard open cut construction method will be used to install the pipeline. This
method includes clearing, grading, trenching, pipe stringing, pipe bending, welding, joint
coating, padding where required, lowering-i n, backfilling, pneumatic testing, cleanup,
and revegetation .
Clearing, topsoi ling and gntding will be limited to the minimum area required for sa:e
and efficient co nstruction. C learing wi ll be performed on ly to the extent necessary to
a ll o w fo r con stru cti o n ac tiv it ies. Th e gr ound surfa ce w ill no t be grubb ed or clear ed o f
v ege ta tion less th an fo ur in c hes in h e ight wh en po ss ibl e. E very effo rt w ill b e m ad e to
CGR Porcu p ine Loop Pipeline Proje c t (7) A ttachme nt to C onstru c tion D e watering-
Indu stria l Waste water D ischarg e Appli cation
•
•
salvage root systems. Large veget ation , such as trees and shrubs, wi ll be cleared from the
right -o f-way an d stockpi led or w indrowed at the edge of the approved workspace for
lat er use in rec lamation.
Top soil will be remo v ed and stockpil ed. Wh ere to p soil is avail abl e, th e top 4 to 6 inc hes
of soil will be removed over the trenchline and in areas requiring grading. Topsoil and
cl eared vege tation wi ll be stockpi led togeth er on BLM lands. Topsoi l will be stockpi led
separate from c leared vege tat io n on fee-lands. Th e right-of-way wi ll be graded on ly to
the ex t ent nece ssary to create safe and efficient pipe line installation conditions. Topsoi l
wi ll no t be salvaged over the existing CGR pipelines.
The di tch wi ll be excavated and sloped in accordance with OSHA specifications. The
cover from top of pipe to ground leve l as graded to pre-construction contours will be in
conformance wi th DOT regulations. Cover will typically be 36-inches in dep th. Greater
depths of cover will be required at road crossings, foreign pipeline crossings, and
waterb odies. As a minimum, the ditch will be excavated to a depth to allow a clearance of
18 inch es b etw ee n th e CGR pip elin e and other pip elines or und erground fac ilit ies.
Machine ex cav ation will not b e performed closer than 5 fe et from an y existin g pip elin e
encountered in the ROW unless authorized by the pipeline owners/operators. Existing
pipe li ne locations will be marked in the field and 48 -hour prior notification given to the
operator of the underground utility.
Where rock is encountered, tracto r-mounted mechanical nppers or rock trenching
equipment may be used to faci li tate excavation.
Th e trench will be ex cav ated and subsoil material stockpil ed separately from topsoil
sto ckpil es. Based on fi eld con ditions, gap s w ill b e made in top soil an d subso il stockp iles
to avoi d p ondi ng or exces sive divers ion of natural runoff during storm event s.
Pipe installation will include stringing, bending for horizontal or vertical angles in the
a lignment, we lding the pipe segments together, x-ray inspection, coating the joint areas to
prevent corrosion, and then lowering-in and padding as described in greater detail below.
Pipe will be hauled by truck to the pipeline ROW. Each joint of pipe will be unloaded
and placed parallel to the ditch.
After the joints of pipe are strung along the ditch, individual joints of pipe will be bent to
accommodate horizontal and vertical changes in direction. Field bends will be made
utilizing a hydrau lically operated bending machine. Where the deflection of a bend
exceeds the allowable limits for a field-bent pipe, factory (induction) bends will be
ins tall ed.
After th e pip e joi n ts arr bent, th e p ipe is lined up end-to-end and clam p ed into p o '>it ion.
Th e pipe is then we lded in conformance w ith 49 CFR Part 192 , Subpart E . "Welding of
• Stee l P ipe lin es" and API 110 4, "Standard for We lding Pipe lin es and Re lated Facil ities".
CGR Porcupine Loop Pip e line Project (8) Attachment to Construction Dewatering-
Industrial Waste water Di scharge Application
•
•
•
We lds will be vis u ally inspected by a qualified inspector and by nondestru cti ve
radiographic methods. At a minimum, radiographic inspection will be conducted in
accordance with DOT requirements. A specialized contractor, certified to perform
ra diographi c inspe ction, will be employed to perform this work. Any defects will b e
repaired or cut out as required under the specified regulations and standards.
To prevent corrosion, the pipe will be externally coated with fusion bonded epoxy
coating prior to delivery. After welding, fie ld joints will be coated with either tape and
primer or shrink sleeves . Before the pipe is lowered into the ditch, the pipeline coating
will be visually inspected and tested with an electronic detector, and any faults or
scratches will be repaired .
Once the pipe coating operation has been completed, a section of the pipe will be lowered
into the ditch . Side-boom tractors will be used to simultaneously lift the pipe, position it
over the ditch, and lower it in place. Inspection will be conducted to verify that minimum
cover is provided; the trench bottom is free of rocks, debris, etc.; external pipe coating is
not damaged; and the pipe is properly fitted and installed into the d itch. Specialized
padding machines will be used to sift soil fines from the excavated subsoil to provide
rock-free pipeline padding and bedding . In rocky areas, padding material or a rock shield
will be used to protect the pipe. Topsoil will not be used to pad the pipe .
Backfilling will begin after a section of the pipe has been successfu ll y placed in the ditch
and final inspection has been completed. Backfilling will be conducted using a bulldozer,
rotary auger backfill, padding machine or other suitable equipment. Backfilling the trench
will generally use the subsoil previously excavated from the trench, except in rocky areas
where imported select fill material maybe needed. Backfill will be graded and compacted,
where necessary for ground stability, by being tamped or walked in with a wheeled or
track vehicle. Compaction will be performed to the extent that there are no voids in the
trench. Any excavated materials or materials unfit for backfill will be utilized or properly
disposed of in conformance with applicable laws or regulations .
Cleanup and restoration will begin as soon as possible after backfill activities are
completed. The right -of-way will be graded to the original contours and natural runoff
and drainage patterns will be restored. Topsoil will be redistributed over the trench and
other portions of the right -of-way from which the topsoil was salvaged and pern1anent
erosion control measures will be installed. Disturbed areas will be seeded with seed
mixes approved by the BLM and fee-landowner .
WASTEWATER SOURCES
Wastewater sources for the project are groundwater and stormwater that may accumulate
in the trench.
Wastewater must be removed from the trench prior to pip e lowering -in and tie -in
activities . The wastewater m ust be removed prior to lowering-in activities to inspect for
the proper configuration (fit) and for rocks and other debris that cou ld damage pipe
CG R Porcupine Loop Pip e line Proj ec t (9) Att ac hme nt to Constru c tion D e w a te ring-
Industrial Waste wat er Di sc harg e A ppli ca tion
•
•
•
coatin g if not removed from th e tre n ch . Was tewater must be re moved pri or to tie -in
activ it ies to allow for w elding and coating of the pipe.
Wh ere tren ch dew aterin g is re quired p ri or to lo w ering-in or ti e-in activit ies , dew ateri n g
sh all be acc omp lish ed b y pump ing wat er from th e tre nch at a co ntro lled rate that p re v ent s
erosion and sedimentation. Wastewater will be dewatered into a stable, upland area .
Was tewater wi ll not be pumped direc tl y into a flowing waterbody .
CGR Porcupine Loop Pipeline Project (10) Attachment to Construction Dewatering -
Industrial Wastewater Di scharge Application
•
•
Project Location
• SURVEYED BY: TRIGON -SHEEHAN. LLC PREPARED BY TRIGON cSlki; 1~:1:m~1 34 Von Gordon, Suite 200 __ _
"'. Lak ewoo d. Colorado 80228 E N G I N E E R S & C 0 N S T R U C T 0 R S i (303) 296-9645
' ·~ !
.... ,
..::.:..· ..
·~· .t ..
\ t:
,':.:.
•
,-.
;Ji CLI ENT
.~rJ ___ ·;":', ::-. :·
.. ~ .. :._ .. J;\ ...
~ ,_-'\.·· ·\·
Garfield County, Colorado
I
300 0' 150 0'
LEGEND
]
0
DESIG NATES BURE AU OF
LAND MANAGEMENT LA NDS
PRO POSED 12" LOOP LI NE
PRO POSED ACC ESS ROA D
3000 ' 6000'
SCAL E: 1" = 3000'
DES CRJ7T ION Pro pos ed Rout e
PORCUPINE PIPELINE PROJECT
. ........ ;
:.
·'
1>1-~~~~~~~~....;·~·;,;,.;m;...~A;..;;.•~·~a;;.:;u~A;;,.;;C~·:;.;;•~~·~·~N;;.,;;D~~~~ .... ~~~~~~..L~~~~~~ .... ~~~~~~~~~~~~~.-~~~~~~~~~~~~~
~ SCALc 1"=3 000' REVISION: DR AWN Err: CL DATE DRAWN: 6/2004 FILE t1 AME: Exhibil 1-B
.... S-URV_EYE_t_D -BY -: -~-41G_-?a_~--~;-d[o-~~-NS-u;(l .... eC 2-00 _______ ..._ ___ ..,...PRE_P_AR_ED_BY_T......_R_l_G_O __ N_(_C"t:( __ Q~ ... -=_1 _;1_=_=_~-~-~-~-, -t
'8 lokewood, Colorado 80228 ~ -- -------·
~L-------~(J_oJ~J -29_o ·-·9-64_s ______________________________ "'-______ ....;.E_N_c __ 1_N_E __ E_R __ s~-&---c-o __ N_s __ r_R_u __ c __ r _o_R __ s __ __.
•
,,. ...-
• '"' ( - -2'i
1 •
. I
'\
·,· ,. .. ,
" I '·I
-.... ,.
,, I !
.,
• 800 '
~ CLIE NT
.-_ ......... . ·. Proposed 12'"
Loop Line
, .
,.
f
_,. ..
-_,
........ -
. . ~ ' .
'·
I -
,.
• ,.
. ·r
f '
-.. ,.
.. _,
L ... _ -~ "".,,'
.>·~·c :;if ~ ~ -
_.,... ........ .....,, ...
.. -.. ...,.,· _ ..... .
·~
Garfield County, Colorado
LE GEND
• •
DE SI GNATE S BUREAU OF
LAND MANAGE~~ ENT LAN DS
EXI STING CANYON GAS PIPELINE
PROPOSED 12" LOOP LINE
PROPOS ED ACCESS RO AD
DESIG NATE S TE MPORARY USE AREA S ('TUA)
DES IGNATES DI STU RBED AREAS (DA)
OESCRPT ION Proposed Rou te
PORCUPI NE PI PELl l\JE PROJEC T
~ SC~L E : 1 ":::8Q Q' REVISIO N: DRAW N BY: CL DATE OP-AWN: •71-su_R_V~-r-o--aY_· __ ffil __ ca_; ___ sHE __ n_1A-N-. L-L~C --------------------..1...---------.-PR-E-P-AR_[_D_m __ T .... _R ___ l_G ___ O ____ N ________ ..._ __________________ --i
§ 34 Von Gordon, Su i(e 20 0
<3 Lakewood, Colorado 802 28
~.__~~~_.;.(J_03~)-29-6--9-64_5~~~~~~~~~~~~~~~"-~~~-E~N -G~l -N _E~E -R~S ~&~-r-v_O~N -S~T -R_U~C -T~O -R~S~__,
'.
·-
J\ CU ENT
Garfield County, Colorado
LEGEND
DESIGNATES BUREAU OF
LAND MANAGEMENT LANDS
--;1-11-1,_,,_,,_,,..._ EXIST IN G CANYON GAS PIP ELINE
PROPOSED 12" LOOP LINE
---PROPOSED ACCESS ROAD
• DESIGNATE S TEMPORARY USE AREAS (T\JA)
OESCRPllON Proposed Roule
PORC UPINE PIPELINE PRO JEC T
~ •..
~'--~~~~~.....:·~A~8;._;R~·~9~C~U~R~O~·~B:;_;,~I N~O:;._~~-.-~~~~.J...~~~~..-~~~~~~~~-.-~~~~~~~~--t
t.. SC.\LE : 1 "=800 ' REVISION: DRAWN BY: CL DATE DRA.WN 6/2004 m NAME: Exhib it 1-0 ~~s~u~~m~o~B~Y--;;;;~l~~~:-~~;~:~~N~Sul~i~~20_0 ____________ .._ ____ -r~ffi~EPA~RE~D ~~~T::::fl:::l~()=-=o==l\l=-=-c~~;::::::;;;~~~~;~1 ==1:;::=~::::r.~~,;:;~~,--'1
0 · Lakewood , Colorado 80228 ____ _
(303 ) 296-96 45 E N G I N E E R S & C 0 N S T R U C T 0 R S ~L-~~.....:.:.;.;.;...;,..;..~~~~~~~~~~~~~-'-~~~..;_~~~~~~~~~~~~~~--'
•
\
!
''·
•
~ CLJ[N f
I
J
I ,.
.. \ i \
I
.l'
' /
i
J I
I
(", ' ,
Garfield County, Colorado
LEGEND
DESIGNATES BUREAU OF
LAND MANAGEMENT LANDS
_,,_,,__,/-ff-ff-(,_ EX IST ING CA NYON GAS PIPELl/\IE
PROPOSED 12" LOOP LINE
---PROPOSED .4CCESS ROAD
• DES IGNAT ES TEMPORARY USE .'\REAS (TIJA)
1ll DESIGNATES DISTURBED AREAS (DA)
0[5CRIP1tOI• Proposed Route
POR CUPINE PIPE LINE PRO JECT
) /,
J '/
r ' I
I ,
I ' I '
\
1
f.. S~'<LE : 1 "=800' REv 1s10 1·.1 : DRAWN !l'T': CL DATE DPPWM: 6/2004 r L·E 11At.1E: Exhibit 1-E
.1-S-UR-V[l_[_D -OY:-1K-4 1 ~-~--~-~~-<l~H-:N-Su...J\~c-20_0 ______ __._ ____ P_RE-PA-R[-D _8Y_T..._R_l_G __ O_N_C_SID __ ~ .... -=_1_:t_~-=-i-il-,-~-,--i
8-Lakewood, Colorado B022B _ _ _ _ _ _ _
(303 ) 296-9645 E N G I N E E R S & C 0 N S T R U C T 0 R S ~L-~~~~;._,;_~~~~~~~~~~~~~~~~~~~'-~~~~~~~~~~~~~~~~~~~~~~~~ .....
;j; CUENT
r
i
LEGEND
DES IGNATES BUREAU OF
LAND MANAGEMEl~T LANDS
_,, _ _,,__,,1---fl--fr-t,_ EX ISTIN G CANYON GAS PIPE LIN E
PROPO SED 12" LOOP LIN E
---PROPOSED ACCE SS ROAD
• DES IGNATES TEMPORARY USE AREAS (TUA)
9 DES IGNAT ES DISTURBED AREAS (DA)
OESCRP110N Proposed Route
PORCUPINE PIPELINE PROJECT
~1--------------·-A _•_R_•_•_n_u~R-"-~-·---•-N_D ______ .,.... ______ _,, ________ ..... ________________ ...,... ________________ ~
•;~s_c~_L[_: ___ 1_"=_s_o_o_· ______ .__R_~_,s1o_N_: ____________ ..._o _RA_~_~_._. _c_L .... ______ __._o_Af_E_oAA_w_N_·_6_/_2_00_4 ____ ..... _r_lE_N-AM-E: __ E_x_hi_b._1t _1_-_F __ ~
~ SURVffiD Bi' ~:~~~~:J;:~~:~~~l~:;~~ PREPARED HY TRIGON (~G) ; I :; = : w ~ I
' (303) 296-9645 E N G I N E E R 5 & C 0 N 5 T R U C T 0 R S
..__ __________________________________________ _,, ____________________________________________ ~
•
•
•
Colorado Air Emission Permit
To be inserted upon receipt .
TRIGON e: ... j: I ~ = : Y!1 ~I
ENG I NEERS & CONSTR U CTORS
•
July 8, 2 004
Co lorado Department of Pub li c Hea lth and Environment
Air Pollution Con trol Divi sion
APCD-SS-81
4300 Cherry Creek Drive South
Den ver, CO 80246 -1530
To Whom It May Concern:
Oi l & Gas P ip e lines
Te lecommun1c at1ons
F ac1iit1es
Surveying
Perm 1~1ng
Land Ser ·11 ces
Eng ineerin g
Design
Procur ement
Construction
Field Ser•,1ces
Ca nyon Gas Resou rces, LLC has retained the services of Trigon-Sheehan, LLC to comp lete the penn it
process for the Porcupine Loop Pipel ine Proj ect. Enc lo sed is the Air Po llut ant Em iss ion Notice and
App li ca tion for Construction Perm it for the project. A Dust Co ntrol Plan has been developed and is
attached for your review.
P lease ca ll me if you have any que st ions or requ ire addit iona l information .
Brenda Lin st e r Herndon
Western Slope E nvironm enta l, Permitting, and ROW Coord in ator
E nclosure
• D E c: I/ E R. ~.1 E E K E R D U R A ~J c; C
5:02 f,1 21;; S1r.:et. S uite: 23 (phys ic a l)• ?.O . Bex 436 (ma ti 1n9) • L l ee ~.er. CO 8164 1 •Phone SI0 1 S7~-9333 •Fax 970i 878-5283
-------··---~----------------------------------------.
AtAhth •... ..,. ___ w_...._._ F I RST
NATIO N AL
8ANK OF TH[ ROCIQIES •
Meeker , CO
.AY EXACTLY **119 AND 96 /100 DOLLARS
TO THE CDPHE APCD
Personal Money Order
108132
Date : 7 /07 /04
Branch: 0101
ORD ER OF~~~~~~~~~~~~~~~~~-.,,...:=;.__~~ $119 . 96
11 •0 0 00 Ii.DB.:\ 211 • 1: li.O 2 li.O Iii 5 "18•: goo Ii.D O g :\Ii.II '
--------·------------------------------------·---------------·-------·-------------· ------------------------------
~:4lL~h& •.. ..d--llllM~11Ua.JlLF 1 RST
NATI ONAL
BANl<.()F~~-
~k~ker , CO
• DATE: 7/07/04
RE MITTER:
TO:
•
Personal Money Orderl08132
Not Negotiable
Thie ci:..stomc:r procun.'1g the P:non..il \.icrcy Order fonn, corr::sponOn2 ::-.
nu.'i10a il!ld amc\!.~.c lo ti'.J.t shown hereon., a.g:":~ to m.se r1 lh:::r~cr. :n Ir"'.
Lh..: Cate. pa~oe~. hl.Yhc r Slgnaru.re and add.r:..s.s ar.d usumcs rcsporu 1btliry (0:
all :veru.s made ;><»Si ble by hi•·hcr r~Jcr: <o do so
BRA:'\CI!: 0 101
ORl G l:'\ATOR: B SI~O
TL\!£: 13: 5 9 : 3 5
Ch':A\!T: $119. 96
FEE A\IT: $2 . 0 0
TOT AL: $119.96
Colorado D epartment o f Public Health and Environment
Air Pollut ion Contro l Division
-LAND DEVELOPMENT -
Page 1 of 3
• Air Po llut ant Em ission Notice (APEN) -and -Application for Construction Permit
•
•
C8J Ne w Facility O Transfer of Owner ship * O Change in Production O No Change (APEN Update On ly)
A ll sections of this APEN and app li cation must be completed prior to submittal to the Division for both new and
existing facilities. An application with missing infonnation may be determined incomplete and may result in
longer engineer processing times.
* Note: If yo u are transferring the ownership of a permit, you must also submit an Administrative Amendment
form and Transfer of Emission Permit Agreement form.
Permit Number AIRS Number
Company Name : Canyon Gas Resources, LLC
Billi ng Address: 7400 East Orchard Road, Suite 3025
E n glew ood, CO
Person to Contact: Art Smi th
Ema il A ddress : asmith@canteranatura lgas.com
P lease provide description o f the actiYity: (A lso, please provide a site map)
Pl ease see attachment.
Project ?-:a m e & Location: Porcupine Loop
Section: 1, 9-12 Township: 7S
Zip Code: 80111 -------
Phone N umb er: 3 03 -222 -62 18
Fax N umbe r: 3 0 3-222-6206
Range. 'Ll '.\" Co unty: Garfield
Total ar e a of land in project:
-----
29 Acres
Date earthmoving wi ll -Commence: Summer 2004 Stop : Fall 2004
Total area subject to earthmoving : 29 Acres --------
Total disturbed area at any one time: 29 Acres
Area to be pa v ed (roa ds , parking lots ): NIA Acres
Date paving will be completed: NI A --------
Estimated time to complete entire project (includes buildings) 4 to 6 weeks
List any known or suspected contaminates in the soil :
No kno\\.TI or suspected conta minates in the soil.
Brief description of how the proj ect deve lopment wi ll occur (attach an additional page ifnecessa;·::)·
P lease see attachme nt.
Rev ise d J uh 20 0 1 h ttp :i/www. c ct p he.s tate.c o. u s/ a p/s ta ti o n a rv. a_ill
•
•
•
Co lo ra do Department of Publi c H ea lth and E n v irorunent
A ir Po llution Control Div is ion
-LAND D EVELOPMENT -
P age 2 of3
FUGITIVE DUST CONTROL PLAN FOR LA ND DEVELOPMENT
(Th is mu st be s ubm itted wit h th e Air Pollu ta nt Em iss ion No ti ce -and -App li cat ion for Emi ss ion Perm it)
Regulation No . I r e quire s that a fugi tive d u st control p lan be submitted by app li cants w ho s e s ource I activity re su lts in fugit ive
d ust emiss ions . The control plan mu st e n able the sourc e to minimize e mi ssions of fug itive dus t to a leve l th at is tec hno lo gic all y
fe as ib le and econo mically reasona ble . If the c ontrol p lan is not a de qu a te in minimizing e miss ions a r evi se d c ontro l p la n may b e
requ ired. The contro l p lan (if acceptable to the Divis ion) will be used for enforcement p urposes on th e sources.
Please ch eck t h e dust control measures wh ich you propose for yo ur activity. The D iv is io n wi ll enforce the control measures
c h ec k e d . Use separate sh ee ts if mo re space is nee d ed. A lso no te items wi th an as terisk (*). This indicates those measures whic h
will probab ly be required.
I. Control of Unpaved Roa d s on Si te
1:8] Watering
D Frequent (Watering Frequ ency of 2 or More Times Per Day)
1:8] As Nee d ed
D A pplicati on of C h emica l S tab il izer
1:8] Vehi c le S peed C ontro l
S p eed s limited to 15 mph maximum. S p eed limit signs m us t b e p o sted.
(Gene ra ll y 30 mph is max imum approvable speed on site .)
D Grave ll ing
II . Contro l of Di s turb ed S urfac e Areas on S it e
Wate ring
D Frequent (Wat e rin g Fre q uency of 2 or More Times Per Da y )
1:8] As Nee d e d
D App li ca tion of C h emi ca l S ta bil izer
Ve hicl e Speed C o n tro l
Speeds Limited To 15 MPH Maximum. Speed Limit Signs Must Be Posted.
1:8] Revegetation Re\·egetatio n Must Occur Wi thin One Year Of So il Disturbance
1:8] Seeding with mulch
D Seeding witho u t mulch
D Furrows at rig h t angle to prevai li ng wind
Depth of furrows Inches (must be greater th an 6")
D Compaction Of Disturbed Soi l On A Dail y Basis To Within 90 % Ofi'v!aximum Compaction
(As detennined by a Proctor Test).
D Foundation areas only; or
D All distur b ed so il.
D W in d Breaks
T ype : (Exa m p le: Sno w F e n ce, S il t Fen ce, e tc.)
1:8] Syn the ti c Or Na tu ra l C o ve r F or S tee p S lopes .
Typ e :
Re \ ise d Ju ly :Z OO l
v ege tativ e d e bris and
rock m u lc h (N ett in g , Mulching, e tc.)
h tm ://www .cdp h e .s tate. c o. u s/::rn sta tion a rv .aso
•
•
•
Colorado Department of Public Health and Environment
Air Pollution Control Division
-LAND DEVELOPMENT -
III. Prevention Of Mud And Dirt Carried Out Onto Paved Surfaces.
0 Prevention
D Gravel Entry Ways
D Washing Vehicle Wheels
l2J Other: N /A --No pave d roads adjacent to project.
D C leanup of Paved Areas Frequency:
D Street Sweeper
D Hose With Water
12] Other: N/ A --No p aved roads adjacent to project.
Additional Sources of Emissions
L ist any other sources of emissions or control methods
Times Per Day
Exhaust from construction e quipment and vehicles will be emitted during construction. Control methods will include
maintaining and tuning equipment to manufacturers' specifications.
l0~ I·
Project Engineer
Name (please print) Title
Check the appropriate box if you want :
D Copy of the Preliminary Ana lys is conduct ed by t h e Divisio n
D To review a draft of the permit prior to issuance
(C hecking any of th ese boxes may result in a n increased fee and/or processing time)
Send this form a long with $11 9.96 to :
Telephone: (3 0 3 ) 692 -3 150
Colorado Department of Public Health and Environment
Air Pollution Control Division
Small Business Assistance Program
(303 ) 692 -3 148
Small Bus in ess Ombudsman
(303) 692 -2 135
Revised Jul y 200 I
APCD -SS-Bl
4300 Cherry Creek Drive South
Denver, CO 80246-1530
http :I /www. cdphe .s tate .c o. u s/ a p/ s ta ti ona rv . asp
•. PROJECT DESCRIPTION
•
•
Canyon Gas Resources , LLC (CGR) has applied to th e B ureau of Land Management
(BLM) for a right -o f-way grant under Sectio n 2 8 of the Mineral Leasi n g Act of 192 0 , as
amende d, to construct, operate, and maintain a 12 -in ch diameter natural gas pipeline and
related facilities in Garfie ld County, Colorado. The proposed pipeline project would loop
an ex istin g CGR 6 -inch diameter natural gas pipeline and wou ld connect CGR's Bentley
and Porc upin e Gath ering Systems. The p ip e line would transport ex istin g and future
natural gas produced by Tom Brown, Inc . (TBI) in the Rifle, Co lo rado area for
processing at the Rifle Clough Compressor Station. TBI plans to drill more than 40 new
wells in 2 004, all of which are dedicated to CGR's gathering systems. Production from
th ese we ll s is expected to increase by 35 mmscfi'd, increasing total throughput from 15
mmscfi'd to 50 mmscfi'd . System throughput will increase to 100 mmscfi'd in the next four
years. T h e proposed pipeline will de-bott leneck the existing gathering systems and will
ensure sufficient capacity to carry CGR's current projection of future gas vo lum es.
The project is approximately 4.3 mile s in length , of which 0 .8 miles are lo cat ed on fe e-
lands an d 3.5 miles are located on BLM l and s a dministered by the G lenwood Springs
Fie ld Office . The project is lo cated so uth and west of Rifle, Co lo ra do in Sectio ns 1, 9, 10 ,
11, and 12 of Township 7 S outh , Range 94 West in the R ulison and N orth Mamm Peak
' U SGS Quadrangles .
CGR will design and build th e pip e lin e in acc ord ance with th e Natio n a l Electrica l Code,
D epartment of Transportation, Tit le 4 0 CFR Part 19 2, and ASME B3 l .8 standards.
Facilities will b e d es i gne d , constructed , and op erate d in comp li ance w ith th e
Occ upation a l H ea lth and Safet y Act (O SHA) re g ulation s p ert ainin g to pip e li n e
construction an d operation .
Th e right -of-way cons tru ction width wi ll be 5 0 feet. A launcher and receiver will be lo cated
at opposite ends of the pipe li ne , wit h risers, blow -downs, and valve sets w here appropriate
a long the righ t-of-way.
CONSTRUCTION SEQUENCE
Constrnction act ivit ies are expected to be comp leted in 4 to 6 weeks and are schedu led
for summer or fall 2 004 .
The standard open cut constmction method will be used to insta ll th e pipeline. This
method in c lud es clearing, gradi ng , trenching , p ipe stringing, pipe bending, we lding, joint
coat in g, paddin g w h ere req ui red, l owering-in , backfilling, pneumatic testing, cleanup,
and revege tat ion .
C lea ring , top s oiling and gradin g will b e limit ed to th e minimum area required for safe
and efficient co nstmction. C learing wi ll be p erfom1e d only to th e extent necessary to
allow for constmction ac tiviti es. Th e gro und surface wi ll not b e gmbbed o r cleared of
vege tation les s than four in ch es in hei ght \v h en po ss ible. Every e ffort will be made to
CGR Porcupin e Loop Pi pe lin e P ro j ect A tt ::!ch m e nt to Appl ica ti on for
Co n s tru cti on P em1i t
•
•
•
salvage root systems. Large vegetation, such as trees and shrubs, will be cleared from the
right-of-way and stockpiled or windrowed at the edge of the approved workspace for
later use in reclamation.
Topsoil will be removed and stockpiled. Where topsoil is avai lable, the top 4 to 6 inches
of soil will be removed over the trenchline and in areas requiring grading. Topsoil and
cleared vegetation will be stockpiled together on BLM lands . Topsoil will be stockpiled
separate from cleared vegetation on fee -lands. The right-of-way will be graded only to
the extent necessary to create safe and efficient pipeline installation conditions. Topsoil
will not be salvaged over the existing CGR pipelines.
The ditch will be excavated and sloped in accordance with OSHA specifications. The
cover from top of pipe to ground level as graded to pre-construction contours will be in
conformance with DOT regulations. Cover will typically be 36-inches in depth. Greater
depths of cover will be required at road crossings, foreign pipeline crossings, and
waterbodies. As a minimum, the ditch will be excavated to a depth to allow a clearance of
18 inches between the CGR pipeline and other pipelines or underground facilities.
Machine excavation will not be performed closer than 5 feet from any existing pipeline
encountered in the ROW unless authorized by the pipeline owners/operators. Existing
pipeline locations will be marked in the field and 48-hour prior notification given to the
' operator of the underground uti li ty .
Where rock is encountered, tractor-m ounted mechanical nppers or rock trenching
equipment may be used to facilitate excavation.
The trench will be excavated and subsoil material stockpiled separate ly from topsoil
stockpiles . Based on field conditions, gaps will be made in topsoil and subsoil stockpiles
to avo id ponding or e_xcessi ve diversion of natural runoff during storm events.
Pipe installation will include stringing, bending for horizontal or vertical angles in the
alignment, welding the pipe segments together, x-ray inspection, coating the joint areas to
prevent corrosion, and then lowering -in and padding as described in greater detail below.
Pipe will be hauled by truck to the pipeline ROW. Each joint of pipe will be unloaded
and placed parallel to the ditch.
After the joints of pipe are strung along the ditch, individual joints of pipe will be bent to
accommodate horizontal and vertical changes in direction. Field bends will be made
utilizing a hydraulically operated bending machine. Where the deflection of a bend
exceeds the allowable limits for a field -bent pipe, factory (induction) bends \viil oe
installed.
After the pipe joints are bent, the pipe is lined up end-to-end and clamped into position.
The pipe is then welded in conformance with 49 CFR Part 192, Subpart E. "Welding of
Stee l Pipelines" and API 1104 , "Standard for Welding Pipelines and Related Facilities".
CGR Porcupin e Loop Pipeline Project Ai-tachment to Application for
Constructio n Permit
•
•
•
Welds will be visually insp ec ted by a qualified in spector and by nondestructive
radiographic methods . At a minimum , rad io graphic inspection wi ll be conduct ed in
accordance with DOT r equirements . A speciali zed contractor, certified to perform
rad io grap hi c insp ection , wi ll b e employe d to perform thi s work. Any de fects wi ll be
re pai red or cut out as re quired under th e spec ifi ed regu lations and st an dards.
To prevent corrosion, th e pipe wi ll be ex ternall y coated with fusion bonded epoxy
coating prior to deliv ery. A ft er we lding, fie ld joints w ill be coated with ei th er tape and
primer or shrink s leeves . Before the pipe is lowered into the ditch, the pipeline coati ng
wi ll be visually inspected and tes t ed with an electronic detector, and any faults or
scratches will be repaired .
Once the pipe coating operation has been comp leted, a section of the pipe will be lowered
into the ditch. Side-boom tractors wi ll be used to simu ltaneously lift the pipe, position it
over th e ditch, an d lower it in p lac e. Inspection will be conducted to verify that minimum
cover is p rovided; the trenc h bottom is free of rocks, debris, e tc.; ex t ernal pipe coating is
not damaged; and th e pipe is properly fit t ed and installed into the ditch. Spec iali ze d
padding machines will be u sed to s ift so il fines from the excavat ed subsoi l t o provide
rock -free pipelin e padding and b edding. In rocky areas, padding mat eria l or a rock shie ld
wi ll b e u se d to protect the pipe . Topsoi l wi ll not b e u sed to pad the pipe .
Backfilling will be gin after a sect ion of th e pipe has been su ccessfu lly placed in th e ditch
and final in spection has been comp l eted. Backfi llin g will be c onducted u s in g a bulldozer,
rotary aug er backfill , paddin g machine or oth er s uit ab le eq uipm ent. Backfilling the trench
wi ll generall y us e th e subso il prev iou sly excavated from the trench , except in rocky areas
where import ed se lec t fill material maybe n ee d ed. Backfi ll wi ll b e gra d ed and compac ted,
where necessary for ground s tabilit y, by be ing tamped or walked in w ith a whee led or
tra ck vehi c le. C ompaction wi ll b e performed to th e ex tent th at th ere are no voids in th e
trench . Any excavated materials or materials unfit for backfi ll will b e utilized or properly
disposed of in conformance w ith app li cab le Jaws or regulations .
C leanup and restoration will begin as soon as possib le after backfill activities are
comp leted. The right -of-way will be graded to the original contours an d natural runoff
and dra in age patterns wi ll be restored . Topsoil wi ll be redistributed over the trench and
oth er portions of the right -of-way from which the topsoi l was salvaged and permanent
erosion control measures wi l l be installed . Disturbed areas wi ll be seeded with seed
mixes approved by the BLM and fee -landowner.
CGR Porcup ine Loop Pi pe lin e Proj ec t A tt :ic hment to App li ca tion for
C on s tru c tion P enrnt
•
•
•
PORCUPINE LOOP
PIPELINE PROJECT
DUST CONTROL PLAN
July 2 004
Applicant:
Canyon Gas Resources, LLC
7 400 East Orchard Road, Suite 3025
Englewood, CO 80111
Prepared by:
Trigon-Sheehan,LLC
532 Main Street, S uite 23
Meeker, Colorado 81641
•
•
•
1.0 INTRODUCTION
The following Fugitive Dust C ontrol (Dust) Plan describes the general control m eas ures which
shall be followed before, duri n g, and after any dust generating operation assoc iated with
const ruction activities for the Canyon Gas Resources, LLC (CGR) Porcupine Loop pipeline
project in western Colorado.
This Dust Plan identifies measures to be [aken by CGR and its contractors (Contractor) to ensure
that dust suppression techniques are i mplemented to control fugitive dust sources during
c onstruction operations. Measures identified in this plan apply to work within the project area
defined as the right -of-way, access roads, temporary use and disturbed areas, and other areas
used during construction of the project. Additional mitig ation measures may be required and will
be listed as conditions in the Air Emission Permit.
CGR and contractor personnel are to be thoroughly familiar with this plan and its contents prior
to initiating construction on the Porcupine Loop project.
2.0 REQUIREMENTS FOR DUST CONTROL
2.1, GENERAL REQUIREMENTS
The Contractor is required to provide dust control measures for all areas disturbed by
constmction. The m eas ures listed below will b e required, as necessary, to control fugitiv e dust.
Additional measures , ifrequired , will b e list ed in th e Air Emission Permit.
2.2 CONTROL OF UNPAVED R OADS ON -SITE
• Suppress dust with application of water or other suppressant as needed.
• Contro l vehicle speed to 15 mph . Signs must be posted by the Contractor.
Dust suppress ants will be applied to the construction work area and access roads at th e request of
th e BLM , Garfield County, and/or fee landowne rs .
2.3 CO NTROL OF DISTURBED AREAS O N-S ITE
• Suppress dust with applic ation of water or other s uppres sant as need ed .
• C ontrol vehicl e speed to 15 mph. Signs must be posted by the Contractor.
• R evegetate disturbed are as in accordance with the BLM Right -of-W a y Grant and attached
stipu l ations to stabi lize soils after construction activities are complete.
• App ly vegetative mulch and excess rock across s lopes on BLM-administered lands to
minimize wind erosion after construction activities are comp lete .
Controlling vehicl e speeds and revegetating the right -of-way are mandatory miti gation m eas ur es.
Dust suppressants will be applied to the construction work ar ea and access roads at the request of
the BLM, Garfield County, and/or fee landown e rs.
•
•
f
~ c; --;;-
·t
Project Location
i ~L-----------~--~--~~~-r;D~~c;R1~~0N:---~~~Lo=ca~l i o~n ~Ma~p~~~~~---"1 ~Lcu_E~~--_j~~~~~~R<~s~~~~~fp~~~.~~Nc'.'."._~r=~~~--J:;:;:P~OR~CU~Pl~NE~P-I PE_LINlE~PR~OJ;EC~T~th~
:s-DRAWN BY: CL DATE DRAWN: 6/2004 FlLE NAME: Exh ibit 1-A ~lsscc~A~~:~N~TS'.___--::-~~Rru~"s~i oN ______ __J_:::...:._~;;;:n;-;;;;;:;;;;~;-:::r~raT~iil~TII •~RYEYEO BY: IB IGON -S HEEHAN. UC PREPARED BY TRIGON c~~,--,---,~ ....... : ........ 1---;t ........ :tll'"l:r'llr.ri~--~..,, 34 Von Gordon , Suite 200 ___ _
:. Lakewood, Colorado 80228 E N G I N E E R s & C O N S T R U C T 0 R S ; (303 ) 296-9645
•
•
-:/:;
/
/. j /.
-. -~~ ... ·
··~-· .. . ... : ··\-'
;i; CU ENT
;:!;
r .
Garfield County, Colorado
I
3000' 1500'
LEGEND
I
0
DES IGNATES BURE.6.U OF
L.A.N D MANAGEMENT LAN OS
PROPOSED 12" LOOP LINE
PROPOSED ACCESS ROJl.D
3000' 6000 '
SCALE: 1" = 3000 '
,· ~
./··,·:~i :
~ SC~L [ 1 "=3 000' REVISIOI": DRAWN ll'Y: CL DATE DRAWN : 6/2004 ~~s~u~~,m~D~B~Y -3~~G~~~~-~~~~~=:.~~~u;~~-20_0 ____________ .__ ____ "l".p~RE~PA~R[~D ~~~T::::R=-:l~G=-=o=-=N=-=-c~~:::::=~::::;=1 =;;::=~~:===ra~·,:::~~,-i
!'! Lakewood , Col o1o do 80228 ·------ -----
Fil£ NAME: Ex hib il 1-B
~L-~~~__,,:(~30~J J~2~9~6 -~9-64~5 ~~~~~~~~~~~~~~~....1~~~~-E;;,_N_G~l -N...;.E ~E-R~S~-&~-C~O-N~S~T -R_U~C~T -O~R -S~~...1
•
~· "'"'.f: .......... ,-
i. <. l _ _..
.:1
' . '·. ~
--.
,;
•
; I
"*~ .. ~/ ~ •• -.. ,~'l.
.ll;~~ r:·r:...·7'· ___ ,.,..,., ........ -_ .. i "\ ..
'· -I
L•
' --... 4 -~-. I'
·--
·-
Garfield County, Colorado
LEGEND
• •
DESIGNATES BUREA U OF
LAND MANAGEMENT LA NDS
EX IST IN G CANYO N GAS PIPE LI NE
PROPOSED 12'' LOOP LIN E
PROPOSED ACCESS ROAD
DESIGNATES TEMPORARY USE AREAS ('ruA)
DESIGNATES DISTURBED AREAS (DA)
. --
· .. ,.
' . •' . .,, ~
'
·-~-~
l sc,LE : 1''=80 0' REV1s10N: DRAWN ffl': CL DATE OAAWN: 6/2004 m NAME : Exhib it 1-C
• ~S-UR-VfJ_I_D -BY-: -I~-1c:-~~--~-~~-[o~-~l-~u-~l~!..c 2-00--------'-----P-RE-PA-RE_D_B'i_T.._R_l_G_O __ N __ c_~-~-3.__;_1_=-=-=-,_-.-,-~-, --t
0· Loke••ood, Colorado 80228 -
(303) 296 -9645 E N G I N. E E R S & C 0 N S T R U C T 0 R S ~L-~~....:.:::.:..:.:;~;:_~~~~~~~~~~.L-~~~...;__;;...;._...;._...;._~~~~~~~--'
•
•
' '
Garfield County, Colorado
LEGEND
DESiG NA1ES BUREAU or
LAND lvlANAGEM El~T lJll·~OS
___,,___,,,___,,/-(f--i;-{1-EXISTING CANYON GAS PIPELINE
PROPOSED 12" LOOP LINE
---PROPO SED ACCE SS ROAD
• DE SlmATES TEMPORARY USE ,l\R EAS (ruA)
;i; CUENT OESCRIP'TION Proposed Roule
PORCUPINE PIPELINE PROJECT ~
=1-~~~~~~__::.:,.:._~·~·~·~o;:.:;:_u ~A~n~~~s:.._~·~'~N~a:._~~--.~~~~~..L.~~~~-..~~~~~~~~~~..,..~~~~~~~~~~~
l SCALE : 1 "=80 0' REVIS ION DRAWN BY: CL DATE DRAWN: 6/2004 f l E 11,\ME: Exh ibil 1-D
.1-S-UR-V[i_I_O -BY-: -~-IG-~'1-0--~~-rd[o-~~-NS-u~tLJ..ec 2-00 _______ ...._ ___ -r-PR-EP-AR_[D_f:l)_' _T...._R_l_G __ O_N_~---~..i.-;_1 _:t_#l_: _f_~-,-~-, --t
5-co kewood , Colorodo 80228 _
(303) 296--9645 E N G I N E E R S & C 0 N S T R U C T 0 R S ~L_ ____ __:;:.::;_::,;.;_.:.:.;.:. ________________________ _._ ______ .:.... __ ......;~------------------------i
•
•
~ CUENT
LEGEND
DESIGNATES BUREA U OF
LA NO MANAGE MENT LANDS
_,,_,,~;-;,_,,,_,,__ EX ISTIN G CANYON GAS PIPE LIN E
PROPO SED 12" LOOP LINE
---PR OPO SED .A.CCESS RO AD
• DE SIGNATE S TEMPOR ARY USE AR EAS (TIJA)
8 DE SIGNATE S DI STURB ED AR EAS (DA)
DE SC RIP1 10N Propo sed f~oute
PORCUPINE PIPELINE PROJEO
~ .... ~~~~~~....;;,.•_A~~~~~·~8~0~l~J ~Q~0 ~~~8....;.,_'~N~O;._~~--i~~~~~£....~~~~...-~~~~~~~~~..,..~~~~~~~~~--t
ii. SCl\LE : 1 "=800' REV1s10N: DRAWN B'i: CL DATE DRl\W~I 6/2004 rLE NAME: Exhibit 1-E
..... S-URV_Eit_D_BY-: -~-4 1 ~-~~--6~-.d~-~N-Su .... ~l~c-20-0 ------------P-RE-PA-R[D_[l'(_T._R_l_G_O_N_C_(\:(_~m .... __ l_i_~-=-,-~-,-~-,---t
s· Lakewood, Colorado 80228 -~-________ .
~ ..... ~~~~{J_oJ_J _2s_o-_9_04_s ~~~~~~~~~~~~~~~ ...... ~~~~E -N~G -l _N_E~E -R~S ~-&~-C -O~N -S~l -R_U~C~T -O_R~s~__.
•
•
LEGEND
DESIGN.i\TES BUREAU OF
LP.ND l1·1ANAGEMENT LANDS
-o---n--tf-{;-;;--;;--EXIST ING CA NY ON G/i.S PIPELIN E
PROPOSED 12" LOOP LI NE
-----PROPOSED ACCESS ROAD
• DES IGNATES TEMPORARY USE AREAS (TUA)
1ll DESIGN.ATES DISTURBCD AREAS (DA)
~ CUENT DESC RIPTIO N Prop osed Route
PORCUPINE D!P ELI NE PR OJ ECT
•:~S-C-~L_[_, ___ 1'_'=_s_o_o_· ______ ....i.._R~ __ 1s1_0N_: ____________ __._o_RA-Vfl_~_~_, __ c_L"T-________ ._o_Ar_r _o~ __ wN_: __ 6_/_20_0_4 ______ ._rl_E_N_AM_E_: _E_x_h_ib_it __ 1_-_F __ --I
.. SUR\mD BY ~I G~~-~~d[o~NSu~l~c 200 PR[PARLD Bl' TRIGON c~ ~ ; I ~ :t : ,lt, ~I
<;. Lakewood , Colorodo 80228 ~-J - - - - -----.
~'----~--...;.(3-0 3~)-29_6--9-64_s ______________________________ ,,_ _______ E __ N_G __ l _N_E __ E_R __ s __ & ____ c _o __ N_s __ T_R_u __ c_T __ o_R __ s __ __.
•
•
•
US Army Corps of Engineers NWP 12 Verification
To be inserted upon receipt .
• APPENDIX C SPILL PLAN
•
•
•
•
•
PORCUPINE LOOP
PIPELINE PROJECT
SPILL PREVENTION,
CONTAIN MENT, and
COUNTER M EASURE PLAN
July 2004
Applicant:
Canyon Gas Resources, LLC
7 400 East Orchard Road, Suite 3025
Englewood, CO 80111
Prepared By:
Trigon EPC
592 South Main Street, Suite 23
Meeker, CO 81641
•
•
•
TABLE OF CONTENTS
1.0 Introduction ............................................................................................................................ 1
1.1 Regulatory Overvie\v .......................................................................................................... 1
2.0 Training .................................................................................................................................. 2
3. 0 Hazardous Materials Managem ent ........................................................................................ 2
3 .1 Transportation of Hazardous Materials .............................................................................. 2
3 .2 Hazardous Materials Inventory ........................................................................................... 3
3.3 Storage of Hazardou s Materials .......................................................................................... 3
3.3.1 Storage Requirement s ................................................................................................... 3
3.3.2 Labeling Requirem e nts ................................................................................................. 4
3.4 Disposal of Hazardous Wastes ............................................................................................ 4
3.5 Inspection and Recordkeeping ............................................................................................ 5
4.0 Spill Prevention Practices ...................................................................................................... 5
4.1 Storage ................................................................................................................................ 5
4.2 Emergen cy and Personal Protec ti ve Eq u ipment.. ............................................................... 6
4 .3 Fue lin g an d Maint en an ce .................................................................................................... 6
4 .4 Near Waterbod ies ................................................................................................................ 6
5 ;0 E m erge n cy Resp on se Procedures .......................................................................................... 7
5 .1 Resp on sibiliti es ................................................................................................................... 7
5 .2 Resp on se Meas ures ............................................................................................................. 7
5.3 N oti ficati on and D ocum ent ati on ......................................................................................... 8
5.3.1 Rep ort in g Criteria ......................................................................................................... 8
5 .3 .2 No ti fication ................................................................................................................... 9
5.3 .2.1 Agen cy No tification ............................................................................................. 9
5.3.2.2 Landowner Notificat ion ....................................................................................... 9
5.4 Documentation .................................................................................................................. 10
Appendi x A
Appendix B
Appendix C
Hazardous Substances Inventory Fonn
Hazardous Materials Inspection Form
Emergency Co ntact List
• 1.0 INTRODUCTION
•
•
The following Spill Prevention, Containment and Countermeasure (Spill) Plan was developed for
implementation during construction, maintenanc e and operation of the Ca nyon Gas Resources
LLC (CGR) Porcupine Loop project in western Co lorado.
The p urpo se of thi s plan is to provid e a description of hazardous materials management, spill
prevention and spi ll response/cleanup measures associated with the construction, operation, and
maintenance of the project.
This plan includes the following components:
• transportation, inventory, storage, and disposal of hazardous materials guidelines;
• spill prevention practices;
• emergency response procedures; and
• notification and documentation measures.
CGR and contractor personnel are to be thoroughly familiar with this plan and its contents prior
to initiating construction on the Porcupine Loop project.
1.1 REGULATORY OVERVIEW
Major legislation pertaining to hazardous materials includes the Comprehensive Environmental
Response, Compliance, and Liability Act (CERCLA), the Resource Conservation and Recovery
Act (RCRA), the Clean Air Act and the Clean Water Act.
Numerous other federal, state, and loc al reg ulations also govern th e use, storage, transport,
production, and disposal of hazardous materials. Some of the key requ irements of these laws are
outlined in the following:
• Title 29, CFR, Part 1910.1200 (hazard communication standards)
• Title 27, CFR, Part 55 (storage and use of explosives)
• Title 40, CFR, Parts 112, 260 to 263 and 279 (hazardous wastes definitions, standards for
hazardous waste generators, and requirements for Spill Prevention, Containment and
Countermeasure Plans)
• Title 49, CFR, Parts 171to180 (hazardous mate1ials transportation)
• Bureau of Land Management (BLM) Instruction Memorandum 94-253. Title 40, CFR, Part
1910.101 to .111 and .120 (OSHA regulations)
• Superfund Amendments and Reauthorization Act (SARA) Title III, Section 301 to 303
(emergency planning), Section 304 (emergency release notification), and Secti on 311 and
312 (community right-to-know reporting req ui rements)
This plan is intended to comply with and compliment existing regulations pe11aining to the safe
use of hazardous materials. Persons responsible for handling hazardo us materials for this project
will be trained in the proper use/management of the materials and will be familiar with all
• applicable laws , polici es, procedures, and best managem ent practices (BMPs) r elated to th em.
•
•
2.0 TRAINING
Th e Contractor will provide basi c hazardous materials management, spill prevention and
response training to cons truction and in spection personnel. Addit ional training will be provided
to all personne l who will be involved with the transportation and storage of fuels or hazardous
substances, equipment maintenance, and spill response . Persons accountable for carrying out the
procedures specified herein will be designated prior to construction and informed of their
specific duties and responsibilities with respect to environmental compliance and hazardous
materials . The Contractor is required to maintain a record of those workers who have received
training . At a minimum, this training will include the following :
• a discussion of individual responsibilities;
• an overview of all regulatory requirements;
• methods for the safe handling and storage of hazardous materials and petroleum products;
• sp ill prevention procedures;
• operation and location of spi ll contro l materials ;
• inspect ion procedures for spi ll containment equipment and materials;
• emergen cy respons e procedures;
• u se of personal protective eq uipm ent and spill cleanup eq uipm ent ;
• procedures for coordinating with emergency response teams; and
• agency notifi cat ion req ui rements.
3.0 HAZARDOUS MATERIALS MANAGEMENT
Construc ti on, operation, and maintenance of the project will require the use of certain potentially
hazardous materials such as gasoline , diesel fuel, lubricating oils , hydraulic fluids, paints, and
solvents . By definition, hazardous materials (substances and wastes) have the potential to pose a
significant threat to human health and the environment based upon their quantity, concentration,
or chemical composition. Hazardous materials will be stored in the construction storage yard and
not on the right -of-way. When transported, stored and disposed of properly as descri bed below,
the ri sks associated with thes e materials c an be r educed substantially.
3.1 TRANSPORTATIO N OF HAZ ARDOUS MATE RI ALS
Pro c edures for loading and transporting fuels and other haz ardous materials will meet the
minimum requirements established by the Department of Transportation (DOT) and other
pertinent requirements. Hazardous materials will be transported in DOT approved containers at
all times. Prior to transporting hazardous materials, appropriate shipping papers wi ll be
completed . Vehicles carrying hazardous materials will be eq uip ped with cleanup materials to
co ntain a small spill shou ld one occur during transport In add iti on, vehicles transporting such
materials w ill b e properly signed (p lacarded ) and/or marked. Prior to transportin g haz ardous
materials, vehicles will b e inspected for leakage and other pot ential safety problems . The
Contractor will ensure that vehicle drivers are prop er ly trained to respond to and report spills,
2
• leakage, and/or accidents involving h azardous materia ls (see Sec tion 2.0).
•
•
All hazardous mat erials used for the proj ect wi ll b e properly con tai nerized and lab eled at all
times, includ in g during transportation. Small er DOT approved con tainers wi ll be used on-site to
transport needed amounts of hazardous materials to a specific location . Transfer of materials
from large to small containers will not be done by hand pouring, but will be accomplished using
appropriate equipment including pumps, hoses, and safety equipment. These smaller service
containers will also be clearly labeled.
3.2 HAZARDOUS MATERIALS INVENTORY
The Contractor will provide a complete inventory to CGR of all substances that will be used
during construction of the pipeline. The inventory will include a list of all fuels, oils and
hazardous substances that are typically expected to be on-site during construction, quantities
stored on-site, and the federal and state reportable quantities for each substance. The Contractor
will also provide the MSDSs for fuels, oils, and hazardous substances to be utili zed during
construction activities which, if released, may pose a threat to human health or the environment.
Hazardous materials that wi ll be us ed during co nstruction , operation, and maint enan ce of the
project will be identifi ed on th e Hazardous Subst anc es Inventory Form included in Appendix A .
3.3 STORAGE OF HAZARDOUS MATERIALS
Hazardous materials , petroleum products, lubricants, paints and coatin gs will not b e stored
w ithi n 100 feet of any waterbody. If topographic or sit e-spec ifi c co ndition s do not allow for
stationary equ ipm ent, such as pumps or generators, to be p laced in upland areas, the stationary
equipment shall be stored in secondary containment structures in accordance with the Spill Plan.
Cleanup materials, including absorbent spill pads and plastic bags, will also be stored in these
areas .
3.3.1 Storage Requirements
Security: Hazardous materials will be stored in secure areas to prevent damage, vandalism
and/or theft. During construction hours, hazardous materials may be .stored temporarily on the
right-of-way but overnight storage on the right-of-way will be prohibited. All storage containers
will remain sealed when not in use and storage areas will be secured (gated, locked, and/or
guarded) at night and during non-construction periods .
Containers: Containers will be compatible with the hazardous materials or wastes stored . If the
container leaks or becomes damaged, the substance must be transferred to a container in good
condition. The Contractor will inspect containers at least weekly to discover any leaks in the
containers or the containment systems. Containers used for transportation must comp ly with the
DOT requirements, including those in Title 49, CFR, Part 173. Containers holding hazardous
su bstanc es will be kept closed during transfer and storage, except when it is n ecessary to add or
remove the sub stance. C ontainers 55-ga llon s or greater will be stored on pall ets and surround ed
by secon dary con tainm en t.
3
•
•
•
Seco nd ary Co ntainment: Seco nd ary co nt a inm ent w ill includ e, bu t wi ll no t b e lim it ed to , a
portabl e cont ainme nt sys tem co nstrn ct ed of stee l, PVC or oth er s uit ab le material or berm ed or
diked are as th at are li ned wi th a m inim um of 10 mil thi ck po lyeth ylene. Second ary contairun e nt
st ru cture s mu st b e capabl e of ho ldin g 110 percent o f th e vo lum e o f th e stor ed m ateria l plus any
po ten tial prec ip it ati on acc umul ati on . Secondary containment is requ ired for a ll containers 55-
ga ll on s and great er.
Incompati b le W as tes: Wastes that are in compatib le wit h other wastes wi ll n ot b e p laced in th e
same conta in er, nor in an unwas hed container, that previous l y h eld an incompatible material.
Ignitab le or Reactive Substances: Substances that may igni te or are reactive must be located at
least 50 fee t from the constrnction yard boundary. "NO SMOKING" signs will be conspicuously
p laced w h erever there is a hazard from ignitab le or reactive waste. Examp les of ign itable wastes
are: paint wastes, certain degreasers, thinners and so lvents (petroleum distillates), epoxy resins,
and adhesives.
Storm water : It m a y be nece ss ar y to dr ain acc umul ated stormw ater fro m w ithin th e sec ond a r y
contairunent ar ea s th at contain th e fuel storage tanks. If th e stonnwater has b een cont aminate d ,
absorbent pads or booms w ill b e used to remov e floating petro l eum products . A lter the
contaminati on has been removed, the stormwater w ill be left to evaporate , if possible, otherwis e
it w ill be d isposed of in an appropriate manner. Prior to di sposal, the C GR Representative wi ll
ch ec k for sh een or oth er ev ide n ce of cont am inat ion .
3 .3 .2 La be lin g Re q u ireme nt s
The Contractor wi ll comp ly with the fo ll owing lab e lin g r equirem ents for any on -site contain er
(in cluding tank s) us ed to st ore acc umul at ed h azardou s was tes. The container s w ill be lab eled as
req u ired in T itl e 4 0 CFR, Part 262 and wi ll contain at least th e fo ll owing in formation:
• chemical name (oil, diesel, etc.);
• the accumu lation start date and/or the date the 90-day storage period began; and
• the words "Hazardous Waste" and warning words indicating the particular hazards of the
waste, such as "flammable", "corrosive", or "reactive."
3.4 DISPOSAL OF HAZARDOUS WASTES
The Contractor will be responsib le for ensuring that all hazardous wastes generated during their
operations are collected regularly and disposed of in accordance with all applicable laws. The
Contractor wi ll determine details on the proper handl ing and disposal of hazardous waste, and
will assign respons ibi l ity to specific ind ivid u als prior to construction of the proj ect.
A ll co n tam in ated art icl es an d so il s recovered dmi n g a re lease event sh all be properly hand led
and stored in DOT appro ve d contain er s. A ll w as tes ge nerat ed as a res ult o f spill r es p on se
act ivities sh a ll be ana lyzed to determi n e i f haz ar dou s , un less know ledge of co ntaminant s is
ap p li ed to class ify th ese was tes as non -h azardou s . Was tes determin ed to b e h azardo u s sh all be
properl y lab e led , profi led , and m ani fes ted to an autho r iz ed hazardous was te, treatme nt , and
4
•
•
•
disposal fac ility. Hazardous wastes wi ll b e stored in a secured location as discussed in Sec tion
3.3 .1.
Any Contractor (gen erator ) p rod ucing m ore th at 100 kilo gram s p er m onth o f h azard o us wast e
must app ly for an EPA Ident ificat ion N umber. The Contractor (generator) producing less t han
100 kg per month are cons idered co nd iti onall y exempt sm all q u antity generators. A gen erator
can store hazardous wastes on-sit e for a period of up to 90 days w itho ut having to obtain a permit
as a storage faci lity, or as a small quantity generator up to a total of 10 00 ki lograms .
3.5 INSPECTION AND RECORDKEEPING
The Contractor will inspect all storage facilities on a regular basis, but not less than weekly. The
Hazardous Materials Inspection Form in Appendix B w ill be used to record the condition of the
faci lity. In addition to the weekly inspection, the Contractor will maintain records for hazardous
material s and h azardous wastes as required by all app licab le federal, stat e, and local regulations
and permit conditions. Record keeping re q uirements incl u d e:
• hazardous materi al insp ec ti o n lo g ;
• trans portation do cuments ;
• bills of lading;
• manifests ;
• shipping papers ;
• training records;
• release report forms ; and
• spill history .
Th e CGR Representat ive wi ll monitor, in spect, doc ument, and report on th e Contractor's
comp liance w ith all hazardo u s materials and hazardous waste management practices.
4.0 SPILL PREVENTION PRACTICES
The Contractor shall take the following precautions to ensure that a release of oil and hazardous
materials is prevented or contained.
4.1 STORAGE
Containers and tanks used for fuel and material storage will be stored and labeled as discussed in
Section 3 .1 .
5
•
•
•
4.2 EM ERGENCY AND PERSONAL PROTECTIVE EQUIPMENT
The following eq uipm ent will be maintained on -site with each crew using h e avy equ ipm ent for
use in cleanup situations :
• shovels,
• absorbent pads/materials,
• personal protective gear,
• fire fighting equipment,
• medical first -aid supplies,
• phone list with emergency contact numbers,
• storage containers/materials, and
• communications equipment.
4.3 FUELING AND MAINTENANCE
Construction vehicles and equipment will be fueled and maintained in upland areas at least 100
feet from waterbodi es. Fueling will not occur within 2 00 feet of private wells or 400 feet of
municipal wells. \Vhen selecting fueling areas, consideration will be given to slopes and other
topographic co nditions. Fueling locations wi ll generally be flat to minim ize the chance of spi ll ed
substance reaching a waterbody. Every e ffort wi ll be mad e to minimize the threat of a fu e l spi ll
during fueling and servicing .
Construction eq uipment requiring maintenance which might resu lt in the draining or leaking of
fluids wi ll b e serviced only after a 12 mil polyethylene lin er has b een installed betwee n the
eq uipment and th e soil. This liner must be placed in such a manner that a ll fluid is co ntained.
A ll service vehicles used to transport lubri cants and fuel must be equipped with an emergency
response kit. At a minimum, this kit must include polyethylene sheeting, absorbent mats, a
bucket or p lastic pan to catch fuel, personal protective equipment, and a minimum of 20 pounds
of suitable absorbent material to handle potential spills. Each service vehicle shall have a
sufficient number of shovels, brooms, polyethylene sheeting, and fire protection equipment to
control a moderate-sized spill.
4.4 NEAR WATERBODIES
If stationary equipment (i .e., pumps, generators, etc.) cannot be located at least 100 feet from
waterbodies because of topographic conditions or space limitations, special precautions (e.g.
placing pumps and small refue lin g cans in secondary containment structures) will be taken to
prevent the spill or release of h azardous materials into the waterway.
In areas where cons tru ction acti vity wi ll cross a flowing waterbody, absorbent booms will be
placed on the water surface downstream of the construction zone, prior to construction. An
emergency response kit will be re quired on-site during clearing, grading, ti e-in, and cl eanup
activities w ithin 100 feet of a waterbody. The emergency response kit will include oil socks,
boons, and pillows , polyethylene sheeting, absorbent mats , a bucket or plastic pan to catch fuel ,
6
• and a minimum of 2 0 pounds of suitabl e ab sorbent mate1ial to handle potential spills.
A ll equipment , vehicle s, pumps, hoses, and gen erators will b e che cked for leaks on a daily basi s.
Le ak s or dri p s wi ll b e re pai re d imm ed iate l y.
5.0 EMERGENCY RESPONSE PROCEDURES
This section provides a generic description of emergency response procedures to be performed to
address petro leum and hazardous substance re leases during construction, operation, and
maintenance of the Porcupine Loop. Each response will vary depending on the nature and extent
of the incident; however, general protocols outlined below will be fo ll owed.
5.1 RESPONSIBILITIES
The Contractor is responsible for:
• Designat ing an em ergen cy coordin ator and two alt ern ate em ergenc y coordin ators;
• Training personn el on conte nt s and r equirements o f Spill P lan ;
• R outinely inspecting and maintaining equipm ent to prevent ac c id ental leak s and spill s;
• C l eanin g-up and addre ssing all spill s whi ch occ ur as a result of th eir op eration s;
• Immediat ely notifying the CGR Representativ e of any spills ; and
• • Documenting spills in a daily log .
•
CGR i s re sponsibl e for :
• Notifying ap prop1iate age nc ies o fre leases in excess o f RQs , in c ludi ng follo w-up noti ficat ion;
and
• Providing supporting personnel and equipment to address RQ re leases.
5.2 RESPONSE MEASURES
Response actions are intended to ensure that all spills are promptly and thoroughly cleaned up.
However, the first priority in responding to any spill is personnel and public safety. Construction
personnel will be notified of evacuation procedures, including evacuation routes, to be used in
event of a spill emergency. In general, the first person on the scene will:
• attempt to identify the source, composition, and hazard of the spill;
• isolate and stop the spill and begin clean up of the spill, if safe to do so;
• notify appropriate personnel and initiate reporting actions; and
• initiate evacuation of the area if necessary.
Persons sh ou ld onl y att em p t to c lean up or con trol a spi ll if they h ave received proper
tra ining. Untrain ed indi v idual s will imm ediat ely n oti fy th e Contrac to r's pr im ary or alt ern ate
emergency coordinators .
Ifthere is a spill of an unknown substance and its identity cannot be determined by observing
7
•
•
•
obvious clues (i .e. lab els on containers , or observing an obvious sources (e.g. h ydrau li c lin es,
fuel tanks, etc .), it would not be considered safe for th e average person to contain the spi ll . Any
sp ill of an unknown s ubstance should be treated as a hazard and should be approached, contain ed
and samp led by trained emergen cy response personnel. General constru ction personn e l should be
instructed to contain and cleanup spill s of only tho se sub stances they can safe ly ide nt i fy and that
can b e safe ly approached (from upwind and upgradient) and handl ed, after identifyi n g the
materials from a safe distance and location.
In general, expert advice wi ll be sought to properly cleanup major spills (defined as any spill
over the reportable quantity for that substance). For spills on land, berms will be constructed to
contain the sp ill ed material and prevent migration of hazardous materials or petroleum products
toward waterways. Dry materials will not be cleaned up with water or burned. Contaminated
soi ls will be collected using appropriate machinery, stored in suitable containers, and properly
disposed of in designated areas off-site.
After co ntaminated soil is recovered, all machinery utiliz ed will be decontaminated, and
recovered soi l wi ll be treated as used oil if co ntaminated with petrol eum products or hazardous
waste if contaminated with hazardous waste. Contaminated c lean up materials (absorbe nt pads,
etc.) and vegetation will be disposed of in a similar manner.
If spilled materials reach water, booms and skimmers will b e used to contain and remove
contaminants. Other actions will be taken as necessary to clean up contaminated waters .
Contaminated soil and materials will b e stored and dispo sed of in accordance with Sec tion s 3 .3
and 3.4.
5.3 NOTIFICATION AND DOCUMENTATION
Notification and documentation procedures for all spi ll s that occur during project construction,
operation, or maintenance will conform to applicab le federal, state, and local laws . Adherence to
such procedures will be the top priority after initial safety and spill response actions have been
taken. The following sections describe the notification and documentation procedures, and
should be implemented in conjunction with the response procedures listed in other sections of
this plan.
5.3.1 Reporting Criteria
The Con tractor will report to the CGR Representative all hazardous substance re leases regardless
of size and petroleum product spills which threaten or enter any waterbody or that are over 1
gallon in size. Verbal reports are required immediately following a major sp ill when doing so
would not de lay clean up or administration of urgent m edical care. Any re lease of h azardous
material over th e app li cabl e reportab le quantities (provid ed by the Contractor on the Hazardous
Material Inventory Form) must be reported imm ediat ely to th e Nati onal Response Center (NRC),
the BLM, th e Colorado Department of Public Health and Envirorunent (CDPHE) and local
authorities . Any spill of petroleum product 55 gallon s or greater or any spill that en ters or may
enter a Co lorado waterbody must be repo1ied to the CDPHE imm ed iat e ly and followed-up with
written communication within 5 days . Any spi ll greater than 1 gallon or any sp ill that enters or
8
• may enter a waterbody on BLM-lands will be r eported to the BLM.
•
•
5.3.2 Notification
Notification will begin as soon as possib le after discovery of a re lease. The individual who
discovers the spi ll will contact a CGR Representative. If th e CGR Representativ e determines
that the spill meets the criteria for immediate verbal notification of government agencies and/or
de termines that the spill may threaten human health or the environment, CGR's Project Manager
will make the required agency notifications as described below. Prior to beginning the
notification process, the individual initiating notification should obtain as much information as
possible to clearly document and communicate the situation. See Section 5.3.2.1 for standard
information that will be requested by agencies . An Emergency Contact List is provided in
Appendix C.
The following mandatory verbal notifications will be made by CGR's Project Manager:
• 911-if an emergency
• BLM, G lenwood Spri ng s Fire Dispatch-(970) 257-48 00-if an emer ge ncy
• National Response Center-(800) 424 -8 80 2-for RQs
• Co lo rado Department of Health and Environment-(877) 5 18-56 0 8 emerg ency;
(303) 69 2-35 00 non-emergency-for RQs and any sp ill th at enters or may enter a waterbody
• Garfield Co unty Local Emergency P lanning Committee-(970) 945-9151-for RQs
• BLM, G lenwood Springs Field Office-(970) 947 -2 800-for any spi ll s over 1 gallon or
spi ll s that enter or may enter a waterbody on BLM-land
5.3.2.1 Agency Notification
The CGR Representative will provide the following information when notifying a regulatory
agency:
• current threats to human health and safety, including known injuries, if any;
• spill location (legal land desc1iption if available), including landmarks and neare st access
route;
• reporter's name and phone number;
• time the spill occurred;
• type and estimated amount of hazardous materials involv ed;
• potential threat to property and environmental resources (especially waterbodies); and
• status of response actions .
5.3.2.2 Landowner Notification
When a spi ll poses a direct and immediate threat to health and safety and/or property, the
landowners potentially affected by th e spill will be directly notified by the CRG. Immediate
notification oflandowners is required for all situation s in which the sp ill poses a direct and
immediate threat to h ealth and safety and/or property .
9
•
•
•
5.4 DOCUMENTAT ION
The Contractor will maintain records for all spi ll s . Agen ci es that CGR verbally notifi ed of a
release will be given written notification by CRG wi thin 30 days, or sooner, ifrequired . The
Co ntractor will provide a written report of all reportab le spi ll s requ irin g agency notification
within 24 hours.
The following is a list of items that should be included in the written report (as appropriate,
based on the spill incident):
• type and amount of material spilled;
• resources affected by spill;
• list of response actions taken, including re lative success;
• copies of letters, permits, or other communications received from government agencies
throughout the duration of the spill response;
• copies of all outgoing correspondence related to the spill; and
• photographs of the response effort (and surrounding baseline photographs if relevant) .
10
• APPENDIX A HAZARDOUS SUBSTANCES INVENTORY FORM
•
•
• HAZARDOUS SUBSTANCES INVENTORY FORM
Substance Expected Volume Intensity of Use Federal RQ State RQ
•
•
• APPENDIX B HAZARDOUS MATERIALS INSPECTION FORM
•
•
•
•
•
HAZARDOUS MATERIALS INSPECTION FORM
PORCUPINE LOOP
Are hazardous materials, petroleum products, lubricants, paints D YES
and coatings labeled?
Are hazardous materials, petroleum products, lubricants, paints DYES
and coatings stored in a secure area?
Are hazardous materials, petroleum products, lubricants, paints D YES
and coatings stored at least 100' from a waterbody?
Are hazardous materials, petroleum products, lubricants, paints DYES
and coatings stored in a container free of leaks?
Are hazardous materials, petroleum products, lubricants, paints DYES
and coatin gs stored 111 seco nd ary containment if storage
c ontain er i s 55-gallon s or great er?
Are MSDS sh ee ts avail abl e on s it e? D YES
Corrective act ions requ ired:
Comments:
Signature: _____________ _
Name of Inspector : _____________ _
Date: --------------
O NO
O NO
ONO
ONO
O NO
ONO
• APPENDIX C EMERGENCY CONTACT LIST
•
•
•
•
•
EMERGENCY CONT A CT LIST
Dial 911 for Emergency Response
Emergen cy Coordinator:
First Alternate:
Second Alternate:
Contractor
Address
EME R GENCY NUMBERS
Emergency Res pons e (Ambula nc e, F ire , P olice, Sheriff)
Poison Control Center
Toxic Information Center
Nearest Hospitals
C le anup C ontracto r --------------
Cou n ty S h eriff
State Patrol
AGENCY NOTIFICATIONS (Made by CGR Project Manager)
Colorado Department of Health and Environment
National Emergency Response Center
US Bureau of Land Management, Glenwood Springs Office
Garfield County Local Emergency Planning Committee
O ther:
Day Pho ne:
Night P h one:
Da Phone:
Night Phone:
Telephone Number
911
800-332-3073
800 -233 -3360
970 -945-0453
800-315-7623
877-518-5608
800-424-8802
970-947-2800
970-945-9151
-----------------------------····--··---
• APPENDIX D FIRE PREVENTION AND SUPPRESSION PLAN
•
•
•
•
•
PORCUPINE LOOP
PIPELINE PROJECT
FIRE PREVENTION and
SUPPRESSION PLAN
July 2004
Applicant:
Canyon Gas Resources, LLC
7400 East Orchard Road, Suite 3025
Englewood, CO 80111
Prepared By:
Trigon EPC
592 South Main Street, Suite 23
Meeker, CO 81641
•
•
•
TABLE OF CONTENTS
1.0 Introduction ......................................................................................................................... 1
1 .1 Purpose ............................................................................................................................ 1
1.2 Responsibilities and Coordination .................................................................................. 1
2.0 Fire Prevention Measures ................................................................................................... 2
2.1 Pipeline Construction ...................................................................................................... 2
3.0
4.0
5.0
2.1.1 Training ....................................................................................................................... 2
2.1.2 Smoking ...................................................................................................................... 2
2.1.3 Spark Arresters ............................................................................................................ 2
2.1.4 Parking, Vehicle Operation, and Storage Areas ......................................................... 2
2.1.5 Equipment ................................................................................................................... 2
2.1.6 Road Closures ............................................................................................................. 3
2.1. 7 Refueling ..................................................................................................................... 3
2.1.8 B u rning ....................................................................................................................... 3
2.1.9 Fire Guard ................................................................................................................... 3
2.1.10 We ldi ng ................................................................................................................... 3
2.1.11 Restric ted Operat io n s .............................................................................................. 3
2.1.12 Mo ni tori ng .............................................................................................................. 3
P ip eline Operati on .............................................................................................................. 3
P ip e lin e Mainten ance .......................................................................................................... 4
F ire Su ppression .................................................................................................................. 4
5 .1 S up p ression ..................................................................................................................... 4
5.2
5.3
Monitoring ...................................................................................................................... 4
Notification ..................................................................................................................... 4
• 1.0 INTRODUCTION
•
•
The following Fire Prevention and Suppression (Fire) P lan provides th e fire prevention and
suppression practi ces to b e implemented during pipeline co n s truction activitie s for th e Canyo n
Gas Resources, LLC (CGR) Porcupine Loop project in western Colorado.
This Fire P lan identifies measures to be taken by CGR and its contractors (Contractor) to ensure
that fire prevention and suppression techniques are carried out in accordance with federal, state,
and local regulations. Measures identified in this plan apply to work wi thin the project area
defined as the right-of-way, access roads, temporary use and disturbed areas, and other areas
used during construction of the project.
CGR and contractor personnel are to be thoroughly familiar with this plan and its contents prior
to initiating construction on the Porcupine Loop project.
1.1 PURPOSE
The risk of fire danger during pipeline construction is related to smoking, re fueling activities,
operating vehicles and other equipment off roadways, we ldin g activities, and the use of
explosive materials and flammable liquids . During pipelin e operation, risk of fire is primarily
from unauthorized entry onto the right -of-way. During maintenance operations, risk of fire is
from vehicles and pipeline maintenance activities that require welding .
This plan establis h es standards and practices that will minimi ze the risk of fire dang er and, in
case of fire , provid e for immediate suppression .
1.2 RESPONSIBILITIES AND COORDINATION
This plan will be implemented by CGR and the Contractor on the project. CGR and the
Contractor have the responsibility for providing all necessary fire-fighting equipment on the
project site to their respective employees and operating under the requirements of this plan . Prior
to construction, CGR will contact the appropriate authorities to establish communications, obtain
permits (if applicable), and/or fulfill other obligations as directed by fire control authorities . In
addition to the above, CGR will:
• Ensure that prevention, detection, pre -suppression, and suppression activities are in
accordance with this Fire Plan and federal, state, and county laws, ordinances, and
regulations pertaining to fire.
• Accompany agency representatives on fire tool and equipment inspections and take
corrective action upon notification of any fire protection requirements that are not in
co m p lian ce .
The fire prevention and suppression measures described in this plan will be in effec t until the end
of construction .
• 2.0 FIRE PREVENTION MEASURES
Method s and proce dures th at will b e impl emented p rio r to and du ring th e constructi on period to
mi ni mize th e risk o f fire are descri bed b elow . The Contrac tor w ill be respons ib le for an y fire
started by their employees or subcontractors.
2.1 PIPELINE CONSTRUCTION
2.1.1 Training
The Contractor will train all personnel about the measures to take in the event of a fire . The
Contractor will also inform each construction crewmember of fire dangers, locations of
extinguishers and equipment, and individual responsibilities for fire prevention and suppression
during regular safety briefings. Smoking and fire rules will also be discussed with the Contractor
and all field personnel during the project's environmental training program .
2.1.2 Smoking
Sm okin g i s p ro hi b ite d except in are as cl eare d and gra ded a mi n im um o f 10 fee t in diam eter to
min eral soil. A ll burn in g tob acc o and mat ch es w ill b e ex tingui sh ed be for e di sc ardin g. Smokin g
is al so prohibited whil e operatin g equipm ent or vehi c l es, excep t in en cl osed cab s or vehi c l es.
• 2.1.3 Spark Arresters
•
Durin g c onstruction, op eratio n , and maintenan ce o f th e right -of-way, all C ontrac to r and CGR
eq ui p m ent operatin g w ith an int ernal co mbu stion engi n e wi ll b e equi p p ed w ith federa ll y
ap proved spark anesters . Spark anesters are not req u ired on trucks, buses, and passenger
ve hic l es that are eq u ipped with an unaltered muffler or on di ese l engines equipped with a
turbocharger. A BLM fire prevention officer will have full authority to inspect spark arresters on
project equipment prior to its use on the project on federal lands and periodically during the
construction project.
2.1.4 Parking, Vehicle Operation, and Storage Areas
In no case will motorized equipment, including worker transportation vehicles be driven or
parked outside of the designated and approved work limits. The right -of-way and temporary use
and disturbed areas will be cleared of all flammable material, as necessary and if required by the
BLM. Clearing will extend a minimum of 10 feet beyond the edge of the area to be occupied, but
not beyond the boundaries of the approved right -of-way or temporary use areas. Glass containers
will not be used to store gasoline or other flammables .
2.1.5 Equipment
A ll mo tor ve hi c les an d equip m ent will carry one lon g-han d led, ro un d-p oint sh ove l, an d one 5-lb
minimum size dry ch emi cal fir e ex tin gui sh er. Indi vidual s u sin g po wer s aw s and grind er s w ill
al so h av e a sh ovel and fir e extinguish er as de scrib ed abov e imm edi atel y availab le. A ll equipment
wi ll b e k ept in a se rv ice ab le condition and r eadi ly av ailab le.
2
• 2.1.6 Road Closures
•
•
The Contractor wi ll notify the appropriate fire suppression agency of the scheduled closures
prio r to th e open-cut crossin g o f a road . If re qui re d , th e Contractor will construct a bypass prior
to th e open -c ut in st a ll ati on of a road cross in g, un less a co n veni ent detour can b e es t ab li sh e d o n
existing proj ect approved roads or wi thin project approved work limits. All bypasses will be
clearly marked by th e Contractor. Th e Co ntrac tor w ill minimize, to th e ex tent possib le, the
duration of road closures.
2.1.7 Refueling
Fuel trucks will have a minimum size 35-lb dry chemical fire extinguisher charged with the
appropriate chemical to control electrical and gas fires.
2.1.8 Burning
No burning of s lash, brush, stumps, tras h , or other proj ect debris wi ll be permitted on the project.
No op en fi res w ill be allowed ay any tim e on th e proj ect.
2.1.9 Fire Guard
Th e Contractor will comply with B LM requirem ents outlin ed in th e stipulati on s attach ed to th e
BLM R ight -of-Way Grant.
2.1.10 Weld ing
On e 5-gallon b ackpack pump and on e 2 0-lb dry ch emi cal fire ex tin gui sh er will be req ui red wi th
each welding uni t in addi tion to th e stan dard fire eq ui pment requ ired in all vehicles. All
equipment wi ll be kept in a serviceab le condition and readi ly avai lab l e.
2.1.11 Restricted Operations
The Contractor will restrict or cease operations on federal lands during periods of high fire
danger at the direction of the BLM. Restrictions may vary from stopping certain operations at a
given time to stopping all operations . The Company may obtain approval to continue some or all
operations if acceptable precautions are implemented .
2.1.12 Monitoring
CRG Representatives will inspect the job site and the Contractor's operations for compliance
with all provisions of this plan . In addition, federal, state, and local fire control agencies may
perform inspections in areas under their jurisdiction at their discretion .
3.0 PIPELINE OPERATION
During pipeline operation, the risk of fire danger is minimal. The primary causes of fire on th e
right -of-way resu lt from unauthorized entry by individuals utilizing the right -of-way for
recreatio n a l purposes and from fires started outside of the right-of-way . In the latter cas e, the
3
•
•
•
right -of-way can be used by authorities as a potential fire break. During pipeline operation,
access to the iight -of-way will be restricted , in accordance with BLM and fee -landowner
requirements, to minimize recreational use of th e ri ght -of-way.
4.0 PIPELINE MAINTENANCE
During maintenance operations, CGR and its Contractor will equip personnel with basic fire-
fighting equipment including fire extinguishers and shovels as described in Section 2.1 .5.
Maintenance crews will also carry emergency contact numbers.
5.0 FIRE SUPPRESSION
5.1 SUPPRESSION
The Contractor will be responsible for suppression of fires started by the construction crews or
subcontractors. The Contractor will take the following actions should a fire occur within the
project area during construction:
•Take immediate action to suppress fires u sing all available manpower and equipment.
•Immediately notify the nearest fir e suppression agency of th e fire location , action taken, and
status. Emergency contact numbers are provided in Sec tion 5.3 .
•Immediately notify CGR of the fire location and ac tion taken.
• Relinquish the direction of fire suppression activities to agency fire management officers upon
their arrival.
A company employee will remain at the fire scene until it is fully extinguished. The extinguished
fire will be monitored in accordance with procedures described in Section 5.2 below.
5.2 MONITORING
The Contractor will mark the location and boundaries of all extinguished fires . The extinguished
fire site will be monitored by the Contractor for a minimum of 24 hours .
5.3 NOTIFICATION
Construction personnel will report all fires, whether extinguished, controlled or uncontrolled, to
a CGR Representative . If the fire is uncontrolled, the Contractor or th e CGR Representative will
call the nearest fire suppression agency (refer to Emergency Contacts in Table 5.3 below). Fires
on BLM lands will be reported to the BLM and fires on fee-lands wi ll be reported to Garfield
Co unty . Information regarding the location of the fir e, prop erty ownership, and closest access
roads should be provided to the fire suppression agency.
4
•
•
•
T bl 5 3 E a e -mergency c t t on ac s
Agency Phone Number
GSFO BLM F i el d Office 97 0 -947-28 00
GSFO BLM Fire Dispatch 970 -257-4800
Garfie ld County Emergency Services 911
Any fires that are controlled will be reported to the BLM on BLM-administered lands and the
fee-landowner on fee-lands. A CGR Representative will be responsible for reporting contro lled
fires to the respective landowner.
5
• APPENDIX E STORMWATER POLLUTION PREVENTION PLAN
•
•