HomeMy WebLinkAbout2.0 Water Supply StudyDEVELOR4E TT OF MTICHELL CREEK
PS A WATER SUPPLY
FOR TAE
WEST G F2MJOD SPRIMS WATER DISTRICT
January, 1984
Prepared by
Schmueser & Associates
1512 Grand Avenue
Suite 210
Glenwood Springs, Colorado
(303) 9455468
1
1
'1
i
TABLE OF CONTENTS
Page
INTRODUCTION 1
Scope of Study 1
Authorization 2
WATER REQUIREMENTS 3
Physical Water Supply 5
General 5
Diversion Records 7
Similar Watersheds 8
Physical Supply Conclusions 11
Water Quality 12
Legal Supply
14
TREATMENT ALTERNATIVES 17
General 17
Description of Alternatives 20
Conventional Filtration 20
Diatomaceous Earth 21
Capital Costs 23
Conventional Filtation Plant 24
Diatomaceous Earth Filtration Plant 29
Used Plant 35
Operation and Maintenance Costs 38
FINANCIAL REQUIREMENTS 45
General 45
Operating Revenues 47
Ability to Finance Future Long Term Debt 47
Purchasing City Water 57
0.5 mgd Conventional Filtration Plant 60
Summary and Conclusions 67
LIST OF FIGURES
Page
Figure 1 9A
Mitchell Creek and Possum Creek Drainages
Figure 2 20A
Schematic Flow Diagram
Proposed Conventional Filtration Plant
Figure 3 23A
Schematic Flow Diagram
Proposed DE Filtration Plant
Figure 4 23B
DE FIlter Plant Layout
Figure 5 25A
N/M Pictorial Trident Plant
1
1
1
1
1
1
1
1
1
1
1
LIST OF TABLES
Page
Table 1 3A
West Glenwood Springs Water District
Recorded Meter Readings
Table 2 8
1977 Diversion Records Reynolds and Cain Ditch
Table 3 9
Possum Creek Streamflow Data
Table 4 10
Estimated Low Flow Mitchell Creek
Table 5 13
Chemical Analysis Mitchell Creek
Table 6 24
Estimated Capital Costs 1 mgd
Conventional Filtration Plant
Table 7 30
Estimated Captial Costs 1 mgd
DE Plant
Table 8 35A
Estimated Capital Cost of Utilization
City of Rifle Pressure Sand Filters
Table 9 38
Estimated Operation and Maintenance Cost of
1 Neptune Microfloc Water Treatment Plant
1
Table 10 41
Estimated Operation and Maintenance Costs
of DE Water Treatment Plant
Page
Table 11 42
Estimated DE Requirements
and Cost for Body Feed
Table 12 48
West Glenwood Springs Water District
Estimated 1983 Operating Revenue
Table 13 50
Estimated Statement of Earnings
New 1 mgd Plant
Table 14 51
Estimate of Capital Available for
Reduction of Future Long Term Debt
Table 15 53
Debt Service Schedule $500,000 Bond Issue
Table 16 54
Debt Service Schedule $600,000 Bond Issue
Table 17 55
Debt Service for the 1980 General
Obligation Bond Issue
Table 18 58
Estimated Statement of Earnings
Assuming Water Purchased from
City of Glenwood Springs
Table 19 59
Estimated Change in Financial Position
Purchasing Water from City of Glenwood
Springs at $1.22/1000 Gallons and $.61/1000
Gallons
1
Page
' Table 20 61
Amount of Water to be Purchased from the
' City of Glenwood Springs if WGSWD Installs
a 0.5 mgd Plant
Table 21
62
11 Estimated Capital Costs 0.5 mgd
Conventional Treatment Plant
Table 22 64
Estimated Statement of Earnings
' New 0.5 mgd Plant
Table 23 65
Estimate of Capital Available for
' Reduction of Future Long Term Debt
with 0.5 mgd Plant
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
The West Glenwood Springs Water District (WGSWD) is a Special District as de-
fined in the Colorado Revised Statutes under the Special District Act. The
District supplies water for domestic, commercial and fire protection purposes.
Historically the District and the City of Glenwood Springs have contractually
agreed that the City would supply excess water to the District, maintain the
system and collect revenues. The City charges District users one and a half
times in -City users and returns approximately 30% of the revenues back to the
District. In addition, there is a 15% surcharge, 100% of which is returned to
the District. The Distric.- owns the physical facilities, provides for capital
improvements and has the taxing authority within the District boundaries.
Because of contractural problems and the potential for increased rates, the
Board of Directors of the WGSWD have initiated this study to determine the
feasibility of developing their own water supply from Mitchell Creek to meet
the present needs of the Water District.
Scope of Study
The purpose of this study is to determine whether or not it is feasible to
develop Mitchell Creek as a surface water source for the WGSWD. The District
has not authorized us to estimate future water requirements. It is our under-
standing that only the feasibility of supplying current demands is to be
evaluated.
The study reviews the physical supply that we feel is available in Mitchell;
Creek and evaluates several alternatives for treating the water from Mitchell
Creek. Capital costs, operation and maintenance costs and the practicality
Nrk
SCHMUESER 8 ASSOCIATES, INC.
of phasing the construction of the plant will be presented in the report. Once
capital costs and 0 & M costs have been determined, a financial analysis will
be performed to determine whether the current rate structure of the District is
capable of generating sufficient income to finance construction of the proposed
improvements.
Authorization
This study was prepared in accordance with a verbal and written Agreement be-
tween Schmueser & Associates and the WGSWD.
SCHMUESER & ASSOCIATES, INC.St
2
The water requirements of the WGSWD are a crucial part of determining whether
or not Mitchell Creek is a viable source for the District. The amount of water
used will also determine what size water treatment plant the District should
construct. Table 1 on the following page shows readings from the main meter
installed in West Glenwood. Over the time period December 3, 1982 to December
8, 1983, the District utilized approximately 141 million gallons of water,
which is an average day demand of approximately 380,000 gpd.
Maximum day demands are an integral part of water facility planning and design.
This maximum day demand would have to be the required capacity of the following
if the District were to have a source and plant on line capable of meeting cur-
rent water demands:
A. Mitchell Creek during low summer flows.
B. The raw water transmission facility.
C. The proposed treatment facility.
D. Transmission lines leading away from the treatment plant.
Since the current data from the West Glenwood, main meter readings do not allow
us to make a determination as to maximum day demands or peak hour demands, we
will utilize a factor of three to one for the ratio of maximum day demand to
average day demand. Thus, estimated current maximum day demands for the WGSWD
are 1.14 mgd. This is the equivalent of 790 qpm or 1.76 cfs. This
Sri
SCHMUESER & ASSOCIATES, INC.
1
1
1
1
TABLE 1
GEST Gly SPRIIMS WATER DISTRICT
RECORDED METER READINGS AND WATER USE
Main Sunny WGSWD WGSWD - Gallons AVG. WGSWD
# of Meter Acres Net Used Bataan, Readings Flaw
Date Days (Gallons) (Gallons) (Gallons) (Gallons) Gal./Day
'2/03/82
12/10/82
' 12/18/82
11 12/26/82
2/27/82 (1)
1u1/03/83
1 1/08/83
1 L/17/83
1
1
"?/11/83
02/25/83
'07/11/83
108/11/83
' u /27/83
I./15/83
./08/83
0 0
7 1,445,000 5,600
8 3,784,400 18,500
8 6,020,000 34,520
8 7,641,000 347,100
5 9,254,000 418,700
9 11,640,000 551,800
_/29/83 12 14,539,000 814,400
'./07/83 9 16,809,000 948,900
4 17,711,000 1,051,700
14 21,199,600 1,126,700
136 75,019,000 8,854,900
31 100,508,000 12,294,100
47 136,968,000 16,916,700
49 155,158,000 19,801,300
23 161,355,000 20,126,000
(1) Tank overflow
3A
1,439,400
3,765,900
5,985,480
7,293,900
8,835,300
11,088,200
13,724,600
15,960,000
16,659,300
20,072,900
66,164,100
88,213,900
120,051,300
135,356,700
141,229,000
1,439,400 205,629
2,326,500 290,813
2,219,580 277,447
1,308,420 163,552
1,541,400 308,280
2,252,900 250,322
2,636,400 219,700
2,235,400 248,378
699,000 174,825
3,413,600 243,828
46,091,200 388,905
22,049,800 711,284
31,837,400 677,391
15,305,400 312,355
5,872,300 255,317
Average day demand = 380,000 gpd
estimated maximum day demand would occur in the summer and appears to be a
reasonable estimate since the average day demand was 0.71 mgd during July and
August of 1983. The current winter maximum day demand is estimated to be 0.6
mqd.
Facilities which provided for continued growth in the West Glenwood area would
have to be sized for flows greater than this 1.14 mgd. Since the District has
requested that we not make projections relative to future demands we will eval-
uate Mitchell Creek and a treatment facility which are capable of supplying
current maximum day demands in the range of 1 mgd.
Note that 1 mgd is being used instead of 1.14 mgd, since the maximus day to
average day ratio of 3 to 1 is an estimated value and it is more practical to
size treatment facilities of this size range in 0.5 mqd increments. Thus, we
will evaluate Mitchell Creek in terms of meeting an estimated maximum day
sumer demand of 1 mgd and determine the costs of providing a 1 mgd water
treatment facility to meet these current demands.
SCHMUESER & ASSOCIATES, INC.
4
PHYSICAL WATER SUPPLY
General
This section evaluates whether there is sufficient physical supply available in
Mitchell Creek on a year round basis to meet the current maximum day demands of
the WGSWD. It must be noted that physical supply is only one of the parameters
which must be addressed in determining whether or not a surface water source is
a viable domestic water supply for any entity. Other items which are normally
• part of the evaluation of any surface water source which are beyond the scope
of this report (the District specifically requested they not be reviewed at
this time) include:
1. Whether the source can legally provide the quantity of water
required.
2. The quality of the raw water and the degree of treatment required to
meet drinking water standards.
3. What will be required to deliver the treated water from the source to
the area served, i.e. the location and elevation of the source with
respect to the service area.
Where water would physically be diverted from Mitchell Creek affects all three
of the items above. The quality of water obtained from Mitchell Creek would be.
SCHMUESER & ASSOCIATES, INC.
Sit
dependent upon the location of the diversion. Since upstream development tends
to reduce water quality, water quality generally improves as you go up stream.
Thus, the farther up stream a diversion is located the better the water quality
will be. The most significant developments affecting Mitchell Creek would be
the area north of Donegan Road which contains single family residences through
which Mitchell Creek flows and the Colorado Division of Wildlife's Mitchell
Creek Fish Hatchery located approximately a mile north of Donegan Road.
The diversion location has very significant impacts on the ability to deliver
treated water from the source to the area served. A diversion location and
treatment plant at an elevation above the West Glenwood Springs water storage
tank would allow water to be delivered to the District with very minimal pump-
ing costs. This alternative has a disadvantage of having to install a trans-
mission line up Mitchell Creek to an area which is high enough to provide grav-
ity flow into the District. On the other hand, locating a diversion and treat-
ment plant in lower Mitchell Creek, where it would be easy to pump directly
into the distribution system, has a disadvantage of having very high power
costs for pumping water from this low elevation up the District's storage tank.
These costs will be discussed in detail later in the report.
The diversion location is very critical in terms of legal supply because of the
water rights questions involved. Again, all of the above items with the excep-
tion of whether the Mitchell Creek can physically supply the District's needs
are beyond the scope of this report but are very critical factors which must be
evaluated in depth before a final determination can be made relative to
SCHMUESER & ASSOCIATES, INC.
6
1
1
1
1
1
1
1
1
1
1
I1i
1
the viability of utilizing Mitchell Creek as a source of supply for the WGSWD.
Diversion Records
Since there is no stream flow data from a gaging station 6n Mitchell Creek
other methods were utilized to make a determination relative to the minimum
water supply available from Mitchell Creek. Water Commissioner's records for
stream diversion are one source of information available for this evaluation.
A review of diversions on the Reynolds and Cain Ditch, which has an appropria-
tion date of April 19, 1883 for 5 cfa_and is the most senior water right on
Mitchell Creek, shows that records are available from water year 1942 through
1983. In general, this review was limited to looking at what the minimum
diversion was each year between May and September. Our conclusions from this
review are that the Reynolds and Cain Ditch has historically diverted greater
than 2 cfs during this time period, the exceptions being the August of 1964 and
August of 1966 diversions at 1.5 cfs and 1.1 cfs respectively. Mr. Earl
Warren, a 47 year resident of the Mitchell Creek area reports that the lowest
summer time flows he observed in Mitchell Creek occured in the summer of 1977.
Table 2 on the following page shows the diversion records for the Reynolds and
Cain Ditch in 1977:
St
SCHMUESER & ASSOCIATES, INC.
7
1
1
1
1
1
1
1
1
1
1
1
TABLE 2
1977 Diversion Records
Reynolds and Cain Ditch
Period Q cfs
4/21 - 4/26 4.8
4/27 - 5/15 1.65
5/16 - 5/23 2.20
5/24 - 5/31 2.45
6/01 - 6/30 2.65
7/01 2.65
7/02 - 8/21 3.10
8/22 - 10/11 3.00
10/12 - 10/24 2.80
As can be seen in the review of the 1977 dry year diversions, the Reynolds and
Cain were able to divert in excess of 2.0 cfs throughout the summer.
Similar Watersheds
A review of similar gaged watersheds is also a common method used for estimat-
ing flows in ungaged watersheds such as Mitchell Creek. Possum Creek, which
lies just northwest of Mitchell Creek, is a small tributary to Canyon Creek.
Possum Creek has a drainage area of 6.4 square miles at U.S.G.S. Gaging Station
09085400. Twelve (12) years of data from 1969 to 1980 were evaluated for Possum
Creek and are shown in Table 3.
SCHMUESER & ASSOCIATES, INC.
Table 3
Possum Creek
Streamflow Data
May -Sept Nov -April
High Flow Low Flow Summer Winter
Low Low
Year cfs Date cfs Date cfs cfs
1980 66 6-6 0.75 11-23 2.2 0.75
1979 70 6-7 1.00 11-28,12-3.3-10 3.9 1.00
1978 80 6-11 0.44 2-22 2.7 0.44
1977 85 8-25 0.79 9-26,27,28,29 0.8 0.80
1976 24 5-21 1.20 3-30 2.2 1.20
1975 82 6-8 1.20 9-25 2.4 1.20
1974 31 5-20 1.60 12-6,7,3-5 2.2 1.60
1973 67 6-10 0.98 2-12 3.5 0.98
1972 59 5-26 0.94 11-20 2.0 0.94
1971 35 6-8 1.20 2-4 3.0 1.20
1970 59 5-26 1.20 3-19 3.0 1.30
1969(1) 34 5-12 1.30 3-19,20 2.5 1.30
Average 1.05 cfs
(1) Data limited to period March - September
Our review of this data shows that the summertime low flaw occured in late
September of 1977 and the wintertime low occured in February 1978. These flows
were 0.79 cfs and 0.44 cfs for simmer and winter respectively.
Figure 1 shows the drainage area boundaries of Mitchell Creek and Possum Creek.
Our review of the two drainage areas show that they have similar percentages of
total drainage area within the elevation ranges of 8,000 to 9,000, 9,000 to
10,000 and above 10,000 feet. This is a good indication that the character-
SCHMUESER & ASSOCIATES, INC.
9
IMO =I NMI .- AIM -MI — MIMI a, RIM IIIIII NMI 111.11, MN MN IM. — MN ..
g
L.;
O
0
0
\ `w
•
0
1
1•
si , • !0
*3,
r
I '• :-
(��
•
v,
istics of the two drainage areas are very similar. Since the drainages are
adjacent to one another, the gaged Possum Creek drainage gives a good indica-
tion of what can be anticipated in terms of low flows for Mitchell Creek if the
Possum Creek flows are adjusted on a ratio which corresponds to the difference
between the size of the two drainage areas.
We have estimated that Mitchell Creek drainage has approximately 11.5 square
miles at a point at the mouth of the canyon. Thus, based on this ratio of
drainage areas it is our opinion that flows in Mitchell Creek should be rough-
ly 1.85 times the flows in the adjacent Possum Creek drainage. Utilizing this
1.85 factor, winter and sumer low flows were estimated for Mitchell Creek for
the available years of record of Possum Creek for 1969 to 1980 and are shown
below in Table 4:
TABLE 4
Estimated Low Flow Mitchell Creek
Year Winter Flow, cfs Sumner Flow, cfs
1980 1.38 4.07
1979 1.85 7.21
1978 0.79 5.00
1977 1.48 1.46
1976 2.22 4.07
1975 2.22 4.44
1974 2.36 4.07
1973 1.81 6.47
1972 1.73 3.70
1971 2.22 5.55
1970 2.22 5.55
1969 2.40 4.62
Table 4 shows the estimated sumer and winter low flows over the 12 year period
where 1.46 cfs and 0.79 cfs respectively. If it is assumed that 1.85 adjust-
ment factor for the two drainages is appropriate, it can be concluded that
NI
SCHMUESER & ASSOCIATES, INC.
10
Mitchell Creek would at times be incapable of meeting current maximum day
summer demands of 1.76 cfs and current winter day maximum demands of 0.93 cfs.
However, there is an inconsistency in our estimated 1977 summer low flow of
1.46 cfs and the amount that diversion records show was diverted in the
Reynolds and Cain Ditch during this time period. This basically means one of
two things, that the conversion factor from Possum Creek to Mitchell Creek of
1.85 is incorrect, or it may mean that the Water Commissioner's readings during
that time period are incorrect.
Physical Supply Conclusions
Based upon the above discussion and estimated current summer maximum day demand
and winter maximum day demands of 1.76 cfs and 0.93 cfs respectively, we reach
the following conclusions relative to the adequacy of the physical supply of
water available in Mitchell Creek.
1. If Mitchell Creek were to be the sole source of water supply for the
District, then the reliability in terms of meeting current summer and
winter maximum day demands is questionable. This is evidenced by our
Possum Creek/Mitchell Creek comparison which shows that in the summer
of 1977 and the winter of 1978, Mitchell Creek would not have been
able to supply the maximum day demands of the District for short per-
iods of time.
2. If a surface water diversion from Mitchell Creek were not the sole
S,
SCHMUESER & ASSOCIATES, INC.
source of supply for the District and either alluvial wells or the
ability to still obtain water from the City of Glenwood Springs on a
short term basis was provided, Mitchell Creek would be an acceptable
source in the terms of meeting physical supply requirements for cur-
rent water demands.
3. A source would have to be provided in addition to Mitchell Creek in
order to meet future maximum day demands of the District if the Dis-
trict is going to continue to grow.
4. Raw water storage to augment summer and winter low flows would be very
beneficial in increasing the reliability of Mitchell Creek for supply-
ing present and future demands.
Water Quality
An in-depth evaluation of the water quality of Mitchell Creek and the degree of
treatment required to meet State drinking water standards is beyond the scope
of this report. However, Table 5 on the next page presents a very limited
amount of water quality data for Mitchell Creek.
Review of this data shows that the water quality of Mitchell Creek on the dates
it was sampled is acceptable. The water is moderately hard but is in the range
of most surface waters within the area. One important parameter which is not
shown in the above data is the effect of spring runoff on water quality. This
is a very important consideration in the design of any treatment facility and
often controls the sizing of various treatment components. It is recommended
SCHMUESER & ASSOCIATES, INC.
12
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
'hemical
TABLE 5
CHEMICAL ANALYSIS
MIL CREEK
(All numbers in ppm unless otherwise noted)
Date Sampled - Day/Month/Year
9/27/73 1/24/74 3/20/74
4/17/74
4/23/74 5/3/74
Turbidity (JTU)
Color (Co/pt Units)
odor
pH
Total Solids
)il and Grease
Sodium
:a1cigm
Aagnes ium
Chloride
L.T. 1
L.T. 1
None
7.8
188
1.6
1.6
51
18.9
1.5
5.0
L.T.
None
8.2
180
1.2
1.0
46
18.5
5.0
9.0
1 L.T.
None
8.1
216
1.4
5.0
47
20
5.0
Sulfate 15.1 33 19.6
Sulfide
Phenol Alkalinity
3s(CaCo3) 6.0 0.00 15
rotal Alkalinity 192 170 170
Total Hardness 205 200 205
L.T. 0.1 L.T. 0.1 L.T.
k*ronon is
Phosphate
Nitrate
kluminum
Arsenic
Potassium
Barium
Cadmium
Cyanide
Chromium
Fluoride
Iron
Manganese
Selenium
Silica
Copper
Lead
0.7
0.18
1.18
L.T..001
0.5
0.25
5.7
0.03
L.T. .001
L.T. 1 ppb L.T. .001
L.T. 1 ppb L.T. .001
L.T. .005 L.T. .01
L.T. .005 L.T. .001
0.15 0.02
0.025 0.01
0.002 L.T. .001
L.T. .005 L.T. .001
8.5 7.0
0.004 L.T. .001
L.T. .001
L.T. 1
1 L.T. 1
None
7.9
186
0.2
1.0
42
10
5.0
10
0.1 0
5
185
185
L.T. 1 L.T. 1
L.T. 1 L.T. 1
None None
7.9 7.95
182 168
0.8 0.6
1.0 1.0
48 42
18 19
5.0 5.0
20 10.0
0 0
10 10
170 180
195 185
0.03 0.6 0.12
1.5 0.63 0.66
0.02 0.05 0.08
L.T. .001 L.T. .001 L.T. .001
0.35 0.8 0.7
L.T. 1 L.T. 1 L.T. 1
L.T. .005 L.T. .005 L.T. .005
L.T. .005 L.T. .005 L.T. .005
L.T. .005 L.T. .005 L.T. .005
0.14 0.1 0.16
0.10 0.01 0.01
L.T. .005 L.T. .005 L.T. .005
L.T. .005 L.T. .005 L.T. .005
6.0 6.0 5.0
L.T. .005 L.T. .005 L.T. .005
JTU = Jackson turbidity units
Co/pt Units = standard color units
L.T. = Less Than
R.L. = Recommended Limit
ppb = part per billion
ppm = part per million
*Source: "Glenwood Springs Master Plan for Water Supply
Development and West Glenwood System Improvements"
Eldorado Engineering Company
June 14, 1974.
13
0.08
0.79
0.05
L.T. .001
.65
L.T 1
L.T. .005
L.T. .005
L.T. .005
0.10
0.01
L.T. .005
L.T. .005
6.0
L.T. .005
that a thorough review of the water quality of Mitchell Creek during spring
runoff and the length of this runoff be evaluated in detail prior to the design
of any treatment facility for Mitchell Creek.
Another water quality consideration which should be reviewed in detail is what
effect, if any, the Colorado Division of Wildlife Mitchell Creek Fish Hatchery
has upon water quality. Mr. Dick Collard, with the Colorado Division of Wild-
life is in charge of the Mitchell Creek Hatchery. He reports that the facility
is just a hatchery and that the maximum size fish kept there was approximately
2 to 2 1/2 inches. Water is not diverted from Mitchell Creek to the hatchery
but comes from springs which run through the hatchery and then discharge to
Mitchell Creek. The only use in Mitchell Creek itself is a raceway in which
the Division keeps cutthroat trout. The Division will be constructing new
facilities within the next 12 months according to Mr. Collard. It is proposed
that water used in the first hatchery building will be run through the new
facility before it is released to Mitchell Creek. The facility has no dis-
charge permit from the Colorado Department of Health. From this preliminary
review of the hatchery it is anticipated that no significant water quality de-
gredation takes place as a result of the facility.
Legal Supply
Although an evaluation of Mitchell Creek water rights is beyond the scope of
this report, the WGSWD must be aware that the ability of Mitchell Creek to
physically supply the District's needs is of no value if adequate water rights
SCHMUESER & ASSOCIATES, INC.
can not be obtained to allow the water to be legally diverted and used. The
District has indicated that they may be able to purchase water rights from the
Reynolds and Cain Ditch which diverts from Mitchell Creek. Some considerations
which must be evaluated in detail prior to any purchase of water rights are
presented below:
1. What are the diversion requirements? Current maximum day demands are
1.76 cfs. If the District were to construct a water treatment plant
to meet this current demand, sufficient water rights to cover this
diversion would have to be obtained. If sinner flows in Mitchell
Creek are less than 5 cfs, which is the amount of water decreed to the
Reynolds and Cain Ditch, then the District would have to purchase more
than 1.76 cfs. For example, if Mitchell Creek were only flowing at
4.0 cfs and the District had to divert 1.76 cfs for its water treat-
ment plant, the District would have to own 44% (1.76/4.0) of the Rey-
nolds and Cain Ditch right or 2.2 cfs to legally make this diversion.
2. What is the historic consumptive use associated with the water riga
and is the consumptive use greater than the consumptive use of the
District?
3. Can the point of diversion for the water right be transferred to a new
point of diversion for the District's water supply intake?
SCHMUESER & ASSOCIATES, INC.
15
The City of Glenwood Springs had acquired a significant portion of the Reynolds
and Cain Ditch right through water rights dedication when taps are purchased.
In the 1977 report entitled "Glenwood Springs Master Plan for Water Supply
Development", this amount was estimated to be 2.44 cfs. The WGSWD may want to
negotiate with the City of Glenwood Springs as well as other parties for the
purchase of Reynolds and Cain water rights..
The District must determine if it is economical to purchase sufficient Reynolds
and Cain water rights to cover their full diversion requirements. If these
rights are expensive it may be more practical to only put in a small water
treatment plant and minimize the need for purchasing a large amount of the
Reynolds and Cain right. In this case, alluvial wells could possibly be dril-
led in lower Mitchell Creek for the remainder of the District's needs. Since
these wells would not affect any of the senior water rights on Mitchell Creek,
a legal supply would be easy to obtain by augmenting the Colorado River rights
(possibly with less expensive Ruedi water). If the District decided to proceed
in this manner, the critical factor is determining if successful alluvial wells
can be drilled along Mitchell Creek.
Si
SCHMUESER & ASSOCIATES, INC.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
TREATMENT ALTERNATIVES
General
In recent years the Colorado Department of Health has expressed strong concern
over the ability of water treatment plants to remove the parasite pathogen
Giardia lamblia which is a flagellated protozoa. This protozoa has two forms
of life. A free living form and an incapsulated or cyst form. Both forms can
be excreted by animal hosts. The cyst form is more resistant and tends to be
-the daminant.form outside of the host. In cold water these cysts can remain
viable for upwards of two months. Humans are not the only hosts for Giardia.
Other hosts include a variety of other mammals including dogs, cats, beavers
and muskrats. Beavers are of particular concern as animal hosts because they
have the potential to inhabit streams which are tributary to water supplies.
Thus, the potential for Giardia exists in water supplies which have no upstream
human activity. Several outbreaks of Giardiasis have been documented in the
State of Colorado in the last couple of years. These outbreaks do not indicate
an increase in the prevalence of Giardia in the state but instead, indicate
that surveillance programs and detection methods now make is possible to
determine that Giardia is in fact the source of the outbreaks. Giardia cysts
are normally associated with surface water, but have been found in well samples
that have been contaminated with sewage.
Dr. Charles Hibier, of Colorado State University, has conducted extensive re-
search on Giardia cysts and surface waters throughout the State of Colorado.
His research indicates wide spread presence of Giardia in surface waters in the
state. Although not every surface water has been sampled Athere is sufficient
SCHMUESER & ASSOCIATES, INC.
17
information available to indicate that all surface water sources are a risk.
Giardiasis has many symptoms, the most common of which is diarrhea. Other
symptoms include weakness, weight loss, cramps, greasy stool, nausea, vomiting,
belching and fever. Studies have indicated that patients can carry the
parasite for up to five years in their intestine. In these cases constipation
was common and was alternated with episodes of diarrhea. Thus, because of the
evidence of the presence of Giardia in the majority of surface waters
throughout the state and because of its somewhat severe symptoms the State
Health Department is now requesting that additions, expansions or upgrading of
existing water treatment facilities take a hard look at providing the most
effective treatment possible, not only for the removal of turbidity and
bacterial contamination, but also for the removal of Giardia cysts.
Based upon current research, the following conclusions have been drawn relative
to a treatment process's ability to remove Giardia cysts as well as turbidity
and bacterial contamination:
1. Facilities which provide complete conventional treatment consisting of
presedimentation, coagulation, flocculation, sedimentation, filtration
by gravity granular multi -media filters or sand filters and chlorina-
tion have been shown to be very effective in removing Giardia cysts.
2. Pressure filters which have been used extensively in the area in small
packaged water treatment plants have been found to be ineffective
SA
SCHMUESER & ASSOCIATES, INC.
in the removal of Giardia cysts. It is felt that the high rates of
filtration, which are customarily 2 to 4 times greater than that in
gravity filters, may be the cause of the ineffectiveness in removing
the cyst.
3. The research has shown that diatomacious earth filtration is a process
that is very effective in removing Giardia cysts.
4. The Colorado Department of Health is encouraging the use of slow sand
filters which have also proved to be very effective in removing
bacteria viruses and Giardia cysts. Slow sand filtration is a process
that simply filters water through 2 to 4 feet of sand at a rate 20 to
50 times slower than conventional sand or granular media filters.
Thus, slow sand filters require 20 to 50 times more filter area than
conventional sand or multi -media filters. Two factors affect the
viability of utilizing slow sand filters for municipal water treatment
today. One factor is land cost where land area is restricted and is
very expensive. The much larger area required for slow sand filters.
may add considerable capital costs to the construction of the
facility. Also, the effect of cold weather performance has not been
thoroughly evaluated, but it is believed that severe weather
conditions may adversely effect filter performance unless the filters
are covered. Because of the large area required for slow sand
filters, it is probably not cost effective to cover and heat the
filters for winter operation.
SA
SCHMUESER & ASSOCIATES, INC.
19
Description of Alternatives
Conventional filtration and diatomacious earth filtration are the two treatment
processes which appear to be the most viable for the treatment of water from
Mitchell Creek to effectively remove turbidity, bacterial contamination and
Giardia cysts. A description of these two alternatives is presented below:
Conventional Filtration. Figure 2 presents a schematic flow diagram for a
conventional filtration plant. This facility would consist of a diversion
structure to divert water from Mitchell Creek to a preliminary settling basin.
This preliminary settling basin would be sized to provide a minimum 24 hour de-
tention period for the flows being diverted from Mitchell Creek. The main pur-
pose of this basin would be to remove heavier suspended material which would be
carried by the stream particularly during spring runoff. Since a detailed site
evaluation of the treatment facility is beyond the scope of this report, we are
assuming that water after passing through the preliminary settling basin will.
flow to a wet well in the plant from which it will be pumped to a flocculator
clarifier. Prior to entering the flocculator clarifier alum and polymer will
be added and rapid mixed. The purpose of the alum and polymer will be to pro-
vide coagulation in the flocculator clarifier. (Coagulation is simply the
clumping together of fine colloidal particles to the extent that they will
rapidly settle out).
St
SCHMUESER & ASSOCIATES, INC.
20
N
I 1111II = MI I i i M N M — E
o'z011g
-'
u=N6=
I =mm
rn
air
rINm
1100,
{fl or
0 yo
N
0-1
p
00
0
WVy JDVIO MO1d 011b'1613HOS
T-1IdONV 7 01 S0110S >10fbi
1
r
1NV1t1N83d(1S
31.1-70810313K70d
r
NIS '8 JN1-7113S
.l b'VNIWi73dd
1
co
n
0,
FLOCULATOR
CLARIFIER
D
N011n
11
rn
0
z
n
Water which has then entered the flocculator clarifier will have coagulated the
colloidal particles to a state where a floc has formed and they will settle out
in this unit. Water leaving the flocculator clarifier will be greatly reduced
in terms of turbidity and fine suspended solids and will be ready for filtra-
tion. Water effluent frau the flocculator clarifier is then filtered through
the gravity multi -media filters and is discharged to a clearwell. High service
pumps will pump water from the clearwell through the distribution system to the
District's existing storage facility. The clearwell is used to provide a
volume of water for the backwashing of filters once they have started to clog,
and chlorine contact prior to pumping. Backwash water frau the filter
cleaning operation will discharge to the backwash ponds located adjacent to the
plant. These ponds will also receive the settled material from the flocculator
clarifier. Facilities would be provided to pump any supernatant or overflow
water frau the backwash ponds back through the preliminary settling basin in
order to avoid having to discharge any of this water back to Mitchell Creek.
This conventional filtration plant is the standard approach to water treatment
which has been utilized for many years and is a very effective process for the
removal of turbidity, bacterial contamination and Giardia.
Diatomaceous Earth. Diatomaceous Earth filters were developed in the
Sit
SCHMUESER & ASSOCIATES, INC.
21
1940's as a means of removing amoebic cysts (the cyst that is associated with
causing amoebic dysentery). Because amoebic cysts, are in the same size range
as Giardia cysts diatomaceous earth filtration has been found to be effective
in the removal of Giardia cysts. Diatomaceous earth (DE) is basically a fine
whiteish powder that is available in a wide range of gradations. D.E. in the
range of 10 to 25 microns is the most typical media used in water treatment
practice. This media is substantially smaller than the media in sand filters
and unlike the conventional flocculation/filtration process, straining is the
primary mechanism for particle removal in diatomaceous earth filters.
The filtration - process works by containing the filter in a pressure vessel and
inducing flow through the filter as a result of the pressure on the -inlet.
Operation of a diatomaceous earth filter consists of three phases:
1. Precoat. Prior to beginning a filter run the septum is coated with a
layer of diatomaceous earth to form the, filter media. Research has
indicated that the quantity of precoat has a significant impact on the
effectiveness of particle removal. Preapplication rates up to two
pounds per square foot are recamiended.
2. Filtration. During filtration water is passed through the layer of
diatomaceous earth which is held in place by the resulting force of
the water against the septum. As the filter run continues it is
advantageous to continue feeding diatomaceous earth through the
SCHMUESER & ASSOCIATES, INC.
22
1
1
1
1
1
1
1
1
1
1
1
1
addition of a (body feed) as this prevents accumulation of filter
material at the surface of the precoat layer. The dosage of this body
feed depends on the quantity of solids present in the raw water and
dosages are normally set using a body feed to turbidity ratio.
3. Backwash. At the completion of a filter run the diatdnaceous earth is
removed from the septum by a number of different processes depending
on which type of D.E. equipment is utilized. The used diatomaceous
earth is then wasted with the backwash water. The backwash is requir-
ed to adequately clean the septum as is the case with the granular
media filtration system. Figure 3 presents the schematic flow diagram
for a diatomaceous earth plant treating surface water from Mitchell
Creek. Figure 4 presents one manufacturer's layout for the specific
diatomaceous earth filtration equipment.
Capital Costs
Capital costs for a conventional filtration plant, A DE plant and a used plant
frau the City of Rifle are presented below. Capital costs of obtaining the
used DE plant frau the Town of Eagle could not be obtained because the Town of
Eagle is now without a Town Manager and the Tbwn Public Wbrks Director failed
to return any of our phone calls. A very important item which must be noted
with regard to capital costs is that the cost of purchasing the necessary water
rights for diversions and use of water from Mitchell Creek have not been inclu-
ded in this anlaysis.
SCHMUESER & ASSOCIATES, INC.
23
u�
11111 111111 MI U 111 111111
2 38nOld
z
11111 11111 I M N
cn
mm
mm
?1 O
Dzi
C �
mm
I13MJV31J
NOISSIW SNV8.1
1-1
Conventional Filtration Plant.
Table 6 below presents our estimated capital costs for a 1 mgd conventional
filtration plant:
TABLE 6
ESTIMTED CAPi'iOL COSTS
1 mgd OaNVENNONAL FILTRATION PLANT
1. Basic Equipment (1) $ 165,000
2. Building, Complete with Lights & Heating 45,,000
13. Clearwell, 41,000 gallons
25,Or►u
14. Diversion with Pretreatment Preliminary Settling Basin 27,250
15. Backwash pond 8,000
16. Raw Water Pumps 20,000
17. High Service Pumps 25,000
18. Chlorination Equipment 10,000
19. Plant Piping 25,000
10. Raw Water Piping 10,000
11. Finished Water Piping 10,000
12. Land 30,000
3. Site Improvements15,300
4. Electrical 25,000
5. N/M Installation 25,000
Subtotal $ 465,550
Plus 25% 116,400
Total 581,950
(1) Purchase of 1 mgd Neptune Microfloc package Trident Plant is assumed.
The use of these numbers shall not be construed as an endorsement for the purchase
of this equipment.
SCHMUESER & ASSOCIATES, INC. N,
24
The following is a list of the design criteria and assumptions which were
utilized in developing the costs shown above in Table 6:
1. Basic Neptune Microfloc Equipment. Because it is more economical in
the 1 mgd water treatment plant size range to provide a packaged
treatment plant as opposed to building each of the treatment plant
components from scratch, Item 1 in Table 6 is the cost of purchasing a
package Neptune Microfloc Model TR -210 Trident Water Plant. This is a
700 gpm or 1 mgd treatment facility and includes two tanks each with
an absorption clarifier and mixed media filters. Polymer and alum
feed equipment, air scour equipment, control valves. A backwash pimp
and a control panel for automatic operation of the facility are
included as a part of the package. A third module could be added to
the plant at a future date to expand the facility to a capacity of 1.5
mgd. Figure 5 presents Neptune Microfloc's pictorial presentation of
a Trident Plant.
2. Building. This item reflects the cost of an 1800 square foot metal
building which would be erected using slab on grade construction with
the exception of a clear well which will be discussed later. The
building is sized to house the initial two Neptune Microfloc treatment
units plus allow the installation of a third unit at a later date.
This would increase the plant capacity to 1.5 mgd. Heat and lights
are included in this cost estimate. A unit cost of $25.00 per foot is
assumed for construction of the building.
SCHMUESER & ASSOCIATES, INC.
25
I
0
CO
N
2
0
PICTORIAL
VI°
)=4 CC
K-LU
0
A wmEILAERATOA-FAr[
25A
1
1
1
11
1
1
O
3. CleatWell. A clearwell is necessary in a water treatment plant to
provide storage for backwash water and for chlorine contact time
before treated water is released into the distribution system. For a
.1 mgd treatment plant, we are estimating that approximately 41,000
gallons of clearwell volume would be required of which 21,000 gallons
would be for contact time and 20,000 gallons for backwash volume. It
is assumed that the clearwell would be located in concrete tankage
below the floor of the building.
4. Diversion and Preliminary Settling Basin. Diversion facilities will
consist of a concrete diversion structure in Mitchell Creek, the ap-
propriate screen and headgate which will discharge by pipeline to the -
preliminary settling basin. The Colorado Division of Health Regula-
tions require that preliminary settling ponds provide a minimum of one
day detention time at peak flows which in this alternative would be 1
million gallons of volume. With a pond having a depth of 7.5 feet,
sideslopes at 1:1 and 2 1/2 feet of freeboard, the outside dimensions
of this preliminary settling basin would be approximately 140 feet by
220 feet. This would require approximately 0.7 acre of land.
5. Backwash Porxi. The frequency of backwash during spring runoff will
be the major factor which will dictate the size of the backwash pond
that will be required. For this evaluation we have assumed that a
pond of approximately 20,000 cubic feet providing around 150,000 gal-
lons of storage will adequate. The outside dimensions of this pond
SCHMUESER & ASSOCIATES, INC.SA
26
will be approximately 90 'by 100'.
6. Raw Water Pumps. The Neptune Microfloc Trident system requires that
that the influent supply provide 20 feet of head to overcame static
head requirements. To allow for friction loss in the influent piping,
and to establish a conservative design criteria we have assumed that
the raw water pumps must be capable of supplying 700 gpm at 40 feet of
head. Assuming an 80% motor efficiency, a total of 10 hp would have
to be provided in vertical turbine pumps installed in the raw water
wet well at the head of the plant.
(any two pumps capable of supplying
It is assumed that three pumps
the
provided to assure reliable operation.
could provide for gravity flow into
the
maximum day demand) would be
Final design of the facility
Trident system if the diver-
sion and preliminary sedemintation basin are installed at a high
enough elevation to gravity feed the plant.
7. High Service Pumps. For the purpose of this estimate, it is assumed
that the water treatment facility is located on lower Mitchell Creek
and it is necessary to pump treated water from the clear well up to
the District's water storage tank. Design criteria are 700 gpm at 365
feet of head. With 80% efficient motors, this would require 80 hp
vertical turbine pumps. Again, for reliability of supply two pumps
would be installed. Final design of the facility could provide for
gravity flow into the system if it were feasible to locate the plant
at a high enough elevation on Mitchell Creek.
SCHMUESER & ASSOCIATES, INC.
27
8. Chlorination Equipment. This item covers the cost of the instal-
lation of a separate chlorine room meeting all of the reauirements of
the Colorado Department of Health. Included are two 150 pound chlor-
ine cylinders, automatic switch over system, emergency repair kit, gas
mask and tank, chlorine piping and chlorine diffuser.
9. Plant Piping. Basic Neptune MicroFloc equipment does not include
associated plant piping. Thus, the cost for this item in the above
table reflects influent piping, backwash piping, piping to the clear
well, air and surface wash piping and chemical feed piping.
10. Raw Water Piping, Outside Plant. It is assumed that 500 L.F. of 8"
raw water piping would be required.
11. Finish Raw Water Piping, Outside Plant. It was assumed that 500
L.F. of 8" pipeline would be required to connect the high service
pumps to the existing distribution system.
12. Land Requirements. It is assured that the treatment plant would
require approximately one half of an acre which would include the
backwash ponds and the treatment plant building. An additional 0.7
acre would be required for the installation of the preliminary set-
tling basin. Assumed land costs are S25,000 per acre.
SA
SCHMUESER & ASSOCIATES, INC.
28
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
13. Site Improvements. This item reflects the cost of fencing the water
treatment plant and providing an estimated 500 L.F. of graveled access
road into the treatment plant.
14. Electrical Service. This item includes the cost of providing 500
feet of primary underground electrical service line, and a 600 coop 225
KVA transformer. Additional items included are the cost of wiring the
pumps, connecting the control panel provided by Neptune Microfloc, and
the cost of tying the existing tank controls to the new facility.
15. Neptune Microfloc Installation. Neptune Microfloc supplies a con-
siderable amount of equipment which basically comes unassembled and
must be assembled at the job site by the contractor.
The 25% contingency added to the subtotal is intended to cover engineering -
design, contract administration, inspection, surveying, legal fees and a small
contingency for miscellaneous items which were not detailed in the above cost
estimate.
Diatomaceous Earth Filtration Plant. Shown in Table 7 on the following
page are the estimated capital costs for a diatomaceous earth filtration
plant.
St
SCHMUESER & ASSOCIATES, INC.
29
1
1
1
1
1
TABLE 7
ESTIMATED CAPITAL COSTS
1 mgd DE Plant
1. DE Equipment $ 185,000
2. DE Controls 30,000
3. Building, Complete with Lights & Heating 40,000
4. Clearwell, 25,000 gallons 20,000
5. Diversion Structure or Infiltration Gallery 27,250
6. Backwash Pond 2,000
7. Raw Water Pumps 20,000
8. Finished Water Pumps 25,000
9. Chlorination Equipment 10,000
10. Plant Piping 10,000
11. Raw Water Piping, Outside Plant 10,000
12. Finished Water Piping 10,000
13. Land 16,700
14. Site Improvements, Access Fuad and Fencing 13,500
15. Electrical Service and Wiring for Pumps and Plant
Equipment 20,000
16. Equipment Installation 5,000
Sub Total $ 444,450
Plus 25% 110,100
Total $ 555,550
J
SCHMUESER & ASSOCIATES, INC.
30
Listed below are the design criteria and design assumptions that were made in
comparing the estimates shown in Table 7 above:
1. DE Equipment. Information supplied by Johns Manville Corporation
who are suppliers of diatomaceous earth and also 'information from
various diatomaceous earth filter manufacturers indicate that diatoma-
ceous earth filtration plants can supply water at
mately 1 gpm per square foot of filter leaf area.
sumed that a 1 mgd plant must have 700 square feet of filter leaf
area. Our estimate assumes -that two 350 square foot filters would be
installed to provide operational flexibility.- The basic layout and
equipmentfurnished was shown previously in Figure 4,
a rate of approxi-
Thus,
pproxi
Thus, we have as -
2. DE t)ontrols.___.This_item_includes_ the purchase and installation of
the control panel and automatic valves for complete automated opera-
tion
peration of the diatomaceous earth plant.
3. Building, Complete with Lights and Beating. This item includes the
construction of a 1500 square foot prefabricated metal building which
would allow for the installation of the two 350 gpm filters plus.
provide for the installation of a future 350 gpm filter in the event
that the plant should be expanded to a capacity of 1.5 mgd. A
significant amount of space would have to be put aside in the building
for the storage of diatomaceous earth. Our estimate assumes that 500
square feet of storage would be provided for this purpose within the
building. Heating and lights are also included in this cost estimate.
SCHMUESER & ASSOCIATES, INC.NI
31
4. Clearwell. The clearwell will provide 30 minutes of chlorine con-
tact time at a flow of 700 qpm for a total chlorine contact volume of
21,000 gallons. 1,050 gallons are required for backwash of the
diatomaceous
earth filters.
Thus, we have proposed
a total clearwell
clearwell
treatment
volume under this alternative of 25,000 gallons. Again, the
would be concrete structure located beneath the floor of the
plant building.
5. Diversion Structure. This item includes the construction of a con-
crete diversion structure screen and headgate on Mitchell Creek which
will divert water to oval sand roughing filters installed adjacent to
Mitchell Creek. These roughing filters would basically consist of 2
feet of sand over 12 inches of clean rock with 4 inch perforated pipe
to collect the water beneath the sand. These small basins would be
approximately 10 by 20 feet in diameter. They are being proposed with
the diatomaceous earth plant, as an alternative to a preliminary
settling basin. The purpose of these roughing filters will be to
provide some treatment in addition to that which is normally received
in a preliminary settling basin because the DE plant does not include
chemical addition, coagulation, flocculation and sedimentation. Thus,
some form of treatment is required to get the raw water down to a
treatable turbidity range during spring runoff.
SCHMUESER & ASSOCIATES, INC.
32
6. Backwash Ponds. Diatomaceous earth plants generate a very small
amount of backwash water, containing the spent diatomaceous earth, in
comparison to the volume generated by conventional filtration plants.
It is assumed that two 20 by 40 ponds approximately 3 foot deep would
be designed as infiltration or percolation ponds for disposal of
backwash water. The ponds would be set up so that no discharge back to
Mitchell Creek would be allowed.
7. Raw Water Pins. Raw water pumping requirements would be 700 gpn at
140 -feet -of ZDH.4 This 140 feet of head is -necessary because diatoma-
ceous--earth -filters - are .pressure :: filters. -It is assured _that_ the
pressure filters would be operated at 50 psi. An additional 25 feet
of head is included for friction loss. 700 gpm at 140 feet of TDH
would require a total of 30 hp in pump motors.
8. Finished Water Pumps. The assumptions are the same as for the pre-
vious alternative.
9. Chlorination Equipment. The assumptions are the same as for the
previous alternative.
SCHMUESER & ASSOCIATES, INC.
10. Plant Piping. This item includes raw water piping to the dual fil-
ters, finished water piping to the clearwell and backwash piping.
11. Raw Water Piping, Outside Plant. It is assumed that 500 L.F. of 8"
raw water transmission line would have to be installed which is the
same as for the previous alternative.
12. Finished Water Piping, Outside Plant. The assumptions are the same
as for the previous alternative, i.e. 500 L.F. of 8" transmission
lines would be required to connect the plant to the existing distri-
bution system.
13. Lana Requirements. It is assumed that the water treatment -plant -and
roughing filters would require approximately 0.67 acres. Estimated
land costs are $25,000 per acre.
14. Site Improvements. This item includes fencing the water treatment
plant site, and providing 500 L.F. of access road into the treatment
plant.
15. Electrical Service. This item is the same as Electrical Service un-
der the previously discussed alternative, i.e. 500 L.F. of primary
underground with a 600 amp 225 KVA transformer. It also includes the
service drop, wiring of the control panel and the pumps within the
treatment facility.
SCHMUESER & ASSOCIATES, INC.NI
34
1
1
1
1
1
1
1
16. Equipment Tristal7aticn. This item is the estimated cost for the in-
stallation of the diatomaceous earth equipment.
A 25% contingency has been added to the subtotal in the above table to allow
for engineering, construction management, surveying, legal expenses and a small
contingency for miscellaneous items not included in the cost estimate.
Used Plant. The City of Rifle, Colorado has a 2 mgd water treatment plant
for sale. The plant consists of four pressure sand filters, with associated
piping and chemical feed equipment. Schmueser & Associates has in the past
looked at the purchase of this equipment for a new treatment facility for ano-
ther entity. The plant has a rated capacity of 2 mgd and was utilized to treat
water diverted from the Colorado River. The plant was abandoned in 1981 when
the City of Rifle built the new Graham Mesa Water Treatment Plant. Table 8
shown on the next page is the estimated cost of purchasing the old Rifle plant
and utilizing the salvagable equipment for the construction of a treatment
facility for the West Glenwood Springs Water District.
Listed below are the design criteria and assumptions that were utilized in de-
veloping the cost estimate shown on the next page on Table 8:
1. Basic Rifle Equipment. This item includes the cost of purchasing
the Rifle plant, removing the roof frau the existing building, disas-
sembling the plant piping, removal of the filters and raw water pumps,
and replacing of the existing . roof and repair of the
SCHMUESER & ASSOCIATES, INC.
35
TABLE 8
E ST I1ATED COST
OF UTILIZING CITY OF RIFLE
PRESSURE SAND FILTERS
1. Basic Equipment $ 130,000
2. Additional Equipment
a. Contact Tank
b. Chemical Feed Equipment and Piping
c. Trucking and Crane
3. Building
4. Clearwell
5. Diversion
6. BW Fond
7. Pumps, Raw and Finished
8. Chlorine Equipment
9. Plant Piping
10. Yard Piping, Raw and Finished
11. Land
12. Site Improvements
13. Electrical Service
50,000
8,000
10,000
45,000
25,000
27,250
8,000
50,000
10,000
10,000
20,000
25,000
15,300
35,000
Sub Total 448,550
Plus 25% 112,150
Total $ 560,770
SA
SCHMUESER & ASSOCIATES, INC.
35A
building as would be required by the City of Rifle. Pressure filters
normally operate at a rate of 8 gpm per square foot of filter area.
This normal design rate would only require two of the pressure sand
filters to be utilized for a 1 mgd capacity. However, since recent
research has shown that pressure filters at this high rate are not hi-
ghly effective in removing Giardia, we have assumed that a design rate
of 4 gallons per square foot per minute would effectively remove
Giardia and that all four filters would be required for a 1 mgd
plant.
2. Additional Equipment. Raw water could not be effectively treated by
the pressure filters alone. It is assumed that a coagulation/ floc-
culation/sedimentation process would have to be included. Thus, we
have included the cost of a contact tank and chemical feed equipment.
3. Building. This assumes a 2,000 square foot building including heat-
ing and lighting at a cost of $25.00 per square foot.
4. Clearwell. The assumptions here are the same as for the Neptune
Microfloc alternative.
5. Diversion The assumptions here are the same as for the Neptune
Microfloc alternative.
SCHMUESER & ASSOCIATES, INC.
36
6. Backwash Ponds. The assumptions here are the same as for the Nep-
tune Microfloc alternative.
7. Raw and Finished Water Pumping Systems. The assumptions here are
the same as those utilized for the diatomaceous earth alternative.
8. Chlorination Equipment. The assumptions here are the same as for
the Neptune Microfloc alternative.
9. Plant Piping Installation. Minimal new piping would have to be pur-
chased since the existing piping at the Rifle plant would be reinstal-
led in the same configuration. This item basically just includes the
labor for installation of plant
piping
10. Yard Piping, Raw and Finished. The assumptions here are basically
the same as for the Neptune Microfloc alternative.
11. Land Requirements. The assumptions here are the same as for the
Neptune Microfloc alternative.
12. Site Improvements. The assumptions here are the same as for the
Neptune Microfloc alternative.
13. Electrical Service and Control Panel for the Plant. The assumptions
here are basically the same as those for the Neptune Microfloc
SCHMUESER & ASSOCIATES, INC.
37
1
1
1
1
1
1
111
1
alternative with the exception that the purchase and installation of a
new control panel for the plant is included.
Again, a 25% contingency has been added to the subtotal shown in Table 8.
Operaticn and Maintenance Costs
Shown below in Table 9 are the estimated operation and maintenance costs for
the Neptune Microfloc Trident Plant.
TABLE 9
ESTIi-1AT D OPERATION AND HAINTMANCE COST OF
NEPTUNE MICROFLOC % TER TREATMENT PLANT
1. Chemical Costs
2. Raw Water Pumping
3. Finished Water Pumping
4. Plant Power
5. Building Electric
6. Demand Charge
7. Miscellaneous Plant Maintenance Materials
8. Plant Operator
$ 5,000
1 ,750
13,000
1,000
8,400
13,200
2,500
15,000
Total $ 60,000
SCHMUESER & ASSOCIATES, INC.
38
Listed below are the assumptions utilized in preparing the above estimates:
1. Chemical Costs. It is assumed that both alum and polymer will be
utilized for effective coagulation and flocculation. 20 mg per liter
and 0.2 mg per liter of alum and polymer respectively. will be applied.
Alum is assumed to cost $0.14 per pound and polymer $3.86 per pound.
It is estimated that with current flows, approximately 23,000 pounds
per year of alum will be utilized at a cost of $3,350. Approximately
231 pounds of polymer will be utilized per year at a cost of $900.00.
It is assumed that chlorine will be applied at 2 mg per liter at a
cost of $0.33 per pound or $750 per year. -
2. Raw Water Pumping. At current demands raw water pumping will con-
sume approximately 26,000 kWh per year. At a cost of $0.067 per kWh
the annual power costs for raw water pumping will be $1,750.
3. Finished Water Pumping. It is estimated that finished water pumping
will require approximately 200,000 kWh per year. At current water us-
age, the annual cost will be $13,500 assuming 6.74 per kWh.
4. Plant Power. It is estimated that $1,000 per year will be required
for miscellaneous power for operation of the plant including the
surface wash pump, the air blower for backwashing and for the
compressor for automatically controlled valve operation.
SCHMUESER & ASSOCIATES, INC.
39
Listed below are the assumptions utilized in preparing the above estimates:
1. Chemical Costs. It is assumed that both alum and polymer will be
utilized for effective coagulation and flocculation. 20 mg per liter
and 0.2 mg per liter of alum and polymer respectively will be applied.
Alum is assumed to cost $0.14 per pound and polymer $3.86 per pound.
It is estimated that with current flows, approximately 23,000 pounds
per year of alum will be utilized at a cost of $3,350. Approximately
231 pounds of polymer will be utilized per year at a cost of $900.00.
It is assumed that chlorine will be applied at 2 mg per liter at a
cost of $0.33 per pound or $750 per year.
2. Raw Water Pumping. At current demands raw water pumping will con-
sume approximately 26,000 kWh per year. At a cost of $0.67 per kWh the
annual power costs for raw water pumping will be $1,750.
3. Finished Water Pumping. It is estimated that finished water pumping
will require approximately 200,000 kWh per year. At current water us-
age, the annual cost will be $13,500 assuming 6.74 per kWh.
4. Plant Power. It is estimated that $1,000 per year will be required
for miscellaneous power for operation of the plant including the
surface wash pump, the air blower for backwashing and for the
compressor for automatically controlled valve operation.
St
SCHMUESER & ASSOCIATES, INC.
39
I
it
1
1
1
1
1
1
1
1
1
1
1
5. Building Electric. It is assumed that an average of $700 per month
will be required for heat and lighting and miscellaneous power within
the building.
6. Demand Charge. The Glenwood Springs Electric System is currently
charging $12.40 per kw in terms of a demand charge. Based upon the
proposed motors in the Neptune Microfloc Plant, we estimate that there
will be a maximum demand of approximately 89.5 kw each month. At
S12.40 per kw, the demand charge would be $1,100 per month or $13,200
per year.
-7. Miscellaneous Plant Maintenance Materials. This item is the estima-
ted cost for miscellaneous materials which will be required for pump
repair, valve repair, etc.
8. Plant Operator. We have included $15,000 for this item, assuming
that a half time operator would be sufficient for maintaining the
plant and performing miscellaneous maintenance duties on the
distribution system. The $15,000 provides for four hours per day of
operator salary at $10.00 per hour plus unemployment insurance, FICA,
and Workman's Compensation insurance.
Shown in Table 10 on the following page are the estimated O&M costs of
a DE filter plant.
SCHMUESER & ASSOCIATES, INC.
40
1
1
1
1
1
1
1
1
TABLE 10
ESTIMATED OPERATION AND MAINTENANCE CC TS
OF DE V7ATER TREATAERT PLANT
Item Estimated Cost
1. DE Cost $ 18,000
2. Raw Water Pumping 5,100
3. Finished Water Pumping 13,500
4. Building Electric 8,400
5. Demand Charge 13,200
6. Miscellaneous Plant Maintenance Materials 2,500
7. Plant Operator 15,000
8. Chlorine Cost 750
$ 76,450
Listed below are the assumptions utilized in preparing the above estimated
operation and maintenance costs for a diatomaceous earth filtration plant:
1. DE Costs. There are two uses of diatomaceous earth in a DE filter
plant. The first and most important in terms of the volume of DE used
is for body feed. Research has shown that the optimum use of
diatomaceous earth for body feed is to provide 3 mg/1 of DE
SCHMUESER & ASSOCIATES, INC.
41
for every mg/1 of suspended solids. Table 11 below shows the amount
and cost of DE at an assumed cost of 204 per pound based upon an esti-
mated average concentration of suspended solids and estimated average
flows for each month.
TABLE 11
ESTIMATED DE REQUERETERTS
AND COST rot BODY FEED
Est. Est.
Avg. SS Avg. Q Lbs.DE Cost for
Month mq/1 mgd for month @ 3:1 Month
January 10 .25 1,875 $ 375
Febuary 10 .25 1,875 375
March 10 .25 1,875 375
April 15 .25 2,815 563
May 50 .40 15,000 3,000
June 50 .50 22,500 4,500
July 15 .70 7,900 1,580
August 15 .75 8,450 1,690
September 10 .60 4,500 900
October 10 .30 2,250 450
November 10 .25 1,875 375
December 10 .25 1,875 375
Total 72,790/yr $14,558/yr
SCHMUESER & ASSOCIATES, INC.
42
The second use of diatomaceous earth is for precoating the filter af-
ter it is backwashed. For precoating operations it is assumed that 20
pounds of DE for each 100 square foot of filter would be utilized and
that 120 precoats per year would be required, utilizing a total of ap-
proximately 17,000 pounds per year. At a cost of 20 per pound, the
annual cost for precoating is $3,360.
2. Raw Water Peeping. It is estimated that approximately 76,000 kWh
per year would be required at current water usage for raw water pump-
ing. At 6.7(P per kWh, the annual cost for raw water pumping would be
$5,100.
3. Finished Water Pumping. The cost for finished water pumping for a
DE plant is the same as that for a Neptune Microfloc Plant, i.e.
200,000 kWh per year at an annual cost of $13,500, assuming a kWh cost
of $.067.
4. Building Electric. It is assumed that $700 per month would be
required for lighting and heating of the treatment plant and miscel-
laneous other power requirements.
5. Demand Charge. Demand charge for a DE plant is basically the same
as that for a Neptune Microfloc Plant, i.e. a demand of 89.5 kWh at
$12.40 per kWh or approximately $1,100 per month.
SA
SCHMUESER & ASSOCIATES, INC.
43
2.
The second use of diatomaceous earth is for precoating the filter af-
ter it is backwashed. For precoating operations it is assumed that 20
pounds of DE for each 100 square foot of filter would be utilized and
that 120 precoats per year would be required, utilizing a total of ap-
proximately 17,000 pounds per year. At a cost of 204 per pound, the
annual cost for precoating is $3,360.
Raw Water Ping. It is estimated that approximately 76,000 kWh
per year would be required at current water usage for raw water pump-
ing. At 6.7 per kWh, the annual cost for raw water pumping would be
$5,100.
3. Finished Water Pupping. The cost for finished water pumping for a
DE plant is the same as that for a Neptune Microfloc Plant, i.e.
200,000 kWh per year at an annual cost of $13,500, assuming a kwh cost
of $0.67.
4. Building Electric. It is assumed that $200 per month would be
required for lighting and heating of the treatment plant and miscel-
laneous other power requirements.
5. Demand Charge. Demand charge for a DE plant is basically the same
as that for a Neptune Microfloc Plant, i.e. a demand of 89.5 kWh at
$12.40 per kWh or approximately $1,100 per month.
SCHMUESER & ASSOCIATES, INC.
43
1
11
11
11
11
11
11
11
11
11
11
1111
I
SCHMUESER & ASSOCIATES, INC.
44
6. Miscellaneous Plant Maintenance Materials. The same assumptions
that were used in Item 7 in Table 9 are used here.
7. Plant Operator. A half time operator would be sufficient for plant
operation.
8. Chlorine. At an application rate of 2 mg/1 it is estimated that
approximately 2,300 pounds per year of chlorine would be utilized. At
a cost of $0.33 per pound, the annual cost for chlorine would be ap-
proximately $750.
11
1
1
1
1
I
11
11
11
11
11
11
11
11
1
11
1
1
f
1
1
1
F RANCIAL
General
•o•S
RIS
As can be seen from the construction cost estimates in the previous section, a
large investment will be required in order for the WGSWD to construct a new
water treatment facility. The ratio of dollars of investment to dollars of
revenue produced is usually great for any water utility in comparison to the
ratio of most other types of business enterprises including electric and gas
utilities. As a result of this, obtaining monies to finance the initial pur-
chase or construction of a water plant as well as to finance extensions, im-
provements and replacements is an important part of management planning and
controlling activities.
There are a number of alternate financing sources available to the WGSWD.
It is the responsibility of the District to employ a combination of funds from
various financing sources which, over the long run amortizes the cost of money
to the utility. There are constraints either of a legal or economic nature
which limit the use of each financing source. Merely attempting to minimize
the effective interest rate at all cost is not always the wisest decision in
the long run. Obtaining minimum effective interest rates may not be desirable
if it requires that the District place severe restrictions on the ability of
the utility to issue additional debt, to refinance, or to respond to changing
SCHMUESER & ASSOCIATES, INC.
45
1
`1
-111
1
11
11
11
11
u
11
11
11
11
11
11
11
market conditions in the future.
The purpose of this section will be to:
1. Estimate current operating revenues.
2. Prepare a statement of earnings which would show operating revenues
and operating expenses under the scenario that a new 1 mgd water
treatment plant has been installed. This statement of earnings will
show a net income or loss from this operation.
3. Estimate the amount of working` capital under the above scenario =that -
would be available for the reduction of future long term debt.
4. Qanpare the amount of capital available for reduction of future long
term debt with the cost of financing a new a 1.0 mgd water treatment
plant to determine if the construction of a plant is feasible.
5. Prepare an estimated statement of earnings assuming that water will
continue to be purchased from the City of Glenwood Springs and deter-
mine what effect this purchase would have on District's working
capital if the District were to take over the operation of the water
system. This discussion will be presented to show what the financial
implications of contracting for City water will be.
SCHMUESER & ASSOCIATES, INC.
46
1
1
1
1
1
1
1
1
1
w
1111
11
11
11
11
11
11
11
Operating Revenues
The first step in determining whether the WGSWD has the ability to finance a
new 1 mgd water treatment plant is to determine what operating revenues may be
available. Presented on the next page is Table 12, which shows the estimated
1983 operating revenues for the West Glenwood Springs Water District.
Table 12 shows the total monies that were collected by the City of Glenwood
Springs from flat rate services and metered services. These values represent
the funds that would be available to the District in 1983 from charges for ser-
vice if the current rate structure were to be maintained and the District col-
lected 100% of the revenue. The 15% surcharge added on by the District and
property taxes are also included as a part of the estimated operating revenue.
The table is derived from the summary of payment forms submitted by the City of
Glenwood Springs to the West Glenwood Water District for the period of February
thru November. No summary of payment forms were available for January or
December. Thus, these two months had to be estimated. Property tax revenues
were obtained from the December 31, 1983 unaudited financial statement of the
District.
Ability to Finance Future Icng Tenn Debt
To evaluate the ability of the WGSWD to finance future long term debt for the
construction of a new water treatment plant we have prepared Tables 13 and 14
SCHMUESER & ASSOCIATES, INC.
47
1
1
1
(t
4J
O VD N to LI) in O Cr) lD cr N N
O cr N r O N O Cr) r N 01 01
O CO N N N 01 O 01 N CO Cr) Cr)
O O N 0\ r cr LO N 01 d CO CO
Cr) O .- to O 01 = CO O LIl r
N r- to l0 N l0 r CO O r l0 l0
N
0
N
0 0 0 0 0 c 0 0 0 0 0
o O O c O o 0 0 0 0 0
N N N N N N N N N N N
- Cr) N 01 Cr)
l0 r- d' 01 01
• • 1 • .
I- N M r -
r
Cr) 01 Cr) O 'Cr
r co r l0 O
• • 1 1
O O M lo N
T- CO ( \I r
O N CO CO
tf) r cr d
cr N cr cr
Cr)
M r- N
O CO
CO
N N
r Cr) N N CO Cr r- N N O CO
N N N 01 'c O d V d cr
• •
r 1/40 o O 01 ▪ cr r 01 co • to to
1/40 'Cr N lD 4.0 l0 O O M to to
M (Y) if) tf7 to VD O r lD to to
r 4•1' N 01 cr O to N l0 O Co
CO r O l0 "G' N VD l0 Cr) m M
Lc") co co 01 lC N O N l0 C• r) C▪ r)
- O l0 M 01 m cr 01 to O O
d M d r- r Or M r N r
. . . . ► . . .
N N cr Cr) Cr) ` I' to 'Cr d' Cr) ▪ Cr)
V' N N r O 01 O O N O CO
O O N Q1 l0 r N N to 'Cr 'Cr
Cr) 0) N r O C▪ r) CO CO l0 r r
O O O O O 01 01 01 01 O O
r O' "7' LII d v v' Or v v
CA-
O O O d N N to r r cr r r
O in d' r- 'Q M 01 m M N O O
O M ▪ N 01 cr to to 01 01 O CO CO
CD tf) r r r N LI) co co r r I--
.- M co Q\ O 01 01 Q\ 01 01 co co
. . . . . . . . .
1/40 .- on 01 O 01 01 01 01 01 01 01
t- r r
rl
Si'El n:- S' -P i i
%r4 to
48
$205,868.73
�p
• 4-)
4-4 as
C7
O 4
4J
-4 a)
U
U)
M
co
6
IBJ
cNi
M
lD
N O
r 4.4
Vi
W O-
O UU
C N
(8
0-
m M
co 4-1
Q1
O
r) O
M
co l0
rn
(n -
cc II
3.7
LIl
3.7 •
0
U v
Q \
r G
• �>1
VD
• -inv
• KC
U •zr
(Li . •
U)
Sr O
• ao
Unaudited Financial Statement
4-I
41
4-1
t7j
O
co
M
CV 4-4
on the following pages. Table 13 shows the estimated statement of earnings
for the following scenario:
1. The WGSWD has constructed and has on line a new 1 mgd water treatment
plant.
2. The District has complete control and responsibility for the mainte-
nance and repair of the distribution system.
3. The District will charge for service at the current rate of structure
with the 15% surcharge and collect 100% of the operating revenues as
estimated in 1983. Tap fees will be the same as for 1983. Depreci-
ation of the new plant is ignored.
The bottom line from Table 13 is the District would have a net income of
approximately $50,000.
Table 14 estimates the capital available for the reduction of future long term
debt. This table is basically an analysis of working capital. The table
shows that in addition to the working capital provided from net income which
is approximately $50,000, the District would have working capital from depre-
ciation and amortization which are actually operating expenses not requiring
an outlay of working capital. In addition, 1983 tap fees of $17,290 were in-
cluded in working capital. Thus, the total estimated working capital would be
$87,685. Of this amount $20,000 goes for the reduction of current long term
debt and we have assumed that $3,000 would be required for miscellaneous
improvements to District facilities. The bottom line from Table 14 is that
the net working capital available for reduction of future long term
NA
SCHMUESER & ASSOCIATES, INC.
TABLE 13
FSTIi•!ATED STATEMENT OF EARNINGS
NEW 1 mgd PLANT
Operating Revenues
Charges for Service
Property Taxes - Net(1)
$ 191,400.00
14,400.00
Total Operating Revenues 205,800.00
Operating Expenses
Water plant O&M
Distribution System Repair & Maintenance
Amortization Expense
Accounting & Legal
Directors' Fees -
Depreciation (2)
Insurance
Office Expense
Meeting Room Rent
Telephone
Engineering Fees
Total Operating Expenses
Operating Income (Loss)
Nonoperating Revenue Expenses
Interest Income
Interest Expense
Net Income(Loss)
60,000.00
10,000.00
933.00
21,600.00
2,205.00
19,671.00
1,500.00
1,200.00
500.00
700.00
4,800.00
$ 123,109.00
82,691.00
11,200.00
(44,100.00)
49,791.00
(1) The Garfield County Assessors Office Reports that 1983 taxes
will increase to $19,425.
(2) Depreciation of new plant ignored.
SCHMUESER & ASSOCIATES, INC.
50
TABLE 13
ESTIMATED STATEMENT CF EARNINGS
GS
NEW 1 mgd PLANT
Operating Revenues
Charges for Service
Property Taxes - Net(1)
'S 191 ,400.00
14,400.00
Total Operating Revenues 205,800.00
Operating Expenses
Water plant O&M
Distribution System Repair & Maintenance
Amortization Expense
Accounting & Legal
Directors' Fees
Depreciation (2)
Insurance
Office Expense
Meeting Room Rent
Telephone
Engineering Fees
Total Operating Expenses
Operating Income (Loss)
Nonoperating Revenue Expenses
Interest Income
Interest Expense
Net Income/Loss (CR)
60,000.00
10,000.00
933.00
21,600.00
2,205.00
19,671.00
1,500.00
1,200.00
500.00
700.00
4,800.00
$ 123,109.00
82,691.00
11,200.00
(44,100.00)
49,791.00
(1) The Garfield County Assessors Office Reports that 1983 taxes
will increase to $19,425.
(2) Depreciation of new plant ignored.
SCHMUESER & ASSOCIATES, INC.
50
TABLE 14
ESTIlN OF CAPITAL AVAILABLE
FOR REDUCTION OF FUTURE
ICNG
TEMI4 DEBT FOR NEW 1 n d PLAINT
Working Capital Provided From:
(1) Net Income (Loss) $ 49,791.00
(2) Add Expenses Not Required Outlay of
Working Capital
(a) Depreciation 19,671.00
(b) Amortization 933.00
Working :_Capital ° Provided - From>
(a) Operations-
(b) Tap Fees
70,395.00-
17,290.00
Total Working Capital Provided 87,685.00
Working Capital Used For:
(a) Reduction of Current Long Term Debt
(b) Miscellaneous Improvements
20,000.00
3,000.00
Total Use of Working Capital 23,000.00
Net Working Capital Available for
New Long Term Dept for 1 mgd Plant $ 64,685.00
SCHMUESER & ASSOCIATES, INC.NA
51
debt would be approximately $64,685.
In order to determine how far this net working capital available for the re-
duction of new long term debt would go towards financing the construction of a
new treatment plant, Kirschner Moore and Company, underwriters of tax exempt
municipal bonds, were contacted and asked to prepare debt service schedules
for revenue bonds for both a $500,000 and $600,000 bond issue. Table 15 and
16 on the following pages present these debt service schedules.
Approximately $70,000 per year would be required to service the debt from a
$500,000 bond issue _ and approximately _ $85,000 , per year would _ be required_to
service a debt frau a $600,000 bond issue. Since the capital costs of -con-
struction for a 1 mgd filtration plant were estimated, to be approximately
$582,000, it is most appropriate to review the ability to finance the new
plant by comparing the estimated net working capital available for financing
new long term debt with the cost of servicing a $600,000 bond issue. This
comparison shows that the estimated $64,685 available for financing new long
term debt would not be sufficient to cover the $85,000 per year debt service
for a $600,000 bond issue.
If it were assumed that a low budget, no frills 1 mgd water treatment plant
could be installed for $500,000, the net working capital available for financ-
ing long term debt of $64,685 is within 10% of meeting the annual debt service
requirements of $70,000 for a $500,000 bond issue. The construction of a 1
mgd plant then appears viable considering .that the ability to service
SCHMUESER & ASSOCIATES, INC.
52
TABLE 15
II ISnn�rV ;+nQ
Jry
WEST GlENtiOOP SFPINFS WATEF: PISTF:ICT
wATc_a F:EVENUE FONDS
II
UATEU MCH 11 1984
PATE FRIH^_IPAL COUPON INTEFEST TOTAL ANNUAL
II9/ 1/1984 23675.04 23675.00 23675.00
3/ 1/1985 25000 7.000 23675.00 42675.00
II 9/ 1/1985 22800.00 22800.00 71475.00
31 1/1986 25000 7.500 22800.00 47300.00
9/ 1/1986 - 21862.50 21862.50 69662.50
II 3/
1/1987 30000 8.000 21362.54 51862.54
9/ 1/1987 20662.50 20662.50 72525.00
3/ 1/1988 30000 3.500 20662.50 50662.50
' 9/ 1/1988 19387.50 19387.50 70050.00
3! 1/1589 35000 9.000 19387,50 54387.50
9/ 1/1989 17812.50 17812.50 72200.00
II
3/ 1/1990 35000 9.250 17812.50 52812.50
9/ 1/1990 16193.75 16193.75 69006.25
3/ 1/1991 40000 9.500 16193.75 56193.75
9/ 1/1991 14293.75 14273.75 70487.50
II 3/ 1/1992 45000 9.750 14293.75 59293.75
91 1/1992 12100.00 12100.00 71393.75
II 1/1993 / 1/1993 50000 10.000 12100.00 62100.00
9/9600.00 9600.00 71700.00
3/ 1/1994 55000 10.200 9600.00 64600.00
II
9/ 1/1994 6795.00 6795.00 71395.00
3/ 1/1995 60000 10.400 6795.00 66795.00
9/ 1/1995 3675.00 3675.00 70470.00
II3/ 1/1996 70000 10.500 3675.00 . 73675.00 73675.00
II
SUBTOTALS 500000 377715.00 277715.00 877715.00
FF'EH• (DISC) .00 .00 .00
TOTALS 500000 377715.00 877715.00 877715.00
II PCC IF;T; •QQ
FATE• 9.9138
BOND TFs; 3810.44
AVE LIFE: 7.6200
FIRST PAYHEtT WAS NOT F:EDUCEA BT ACCF.UEA INTEF:EST
1
1
1
1/13/1924 AT 13:33:1?
53
1
TABLE 16
1
1
1
1
1
1
1
1
1
1
1
1
1
1600,000
WEST GLENWOOD SFRINGS WATER DISTRICT
WATER REVENUE BONDS
DATED
MARCH 1, 1984
DATE PRINCIPAL COUPON INTEREST TOTAL ANNUAL
9/ 1/1984 28415.00 28115.00 28415,00
3/ 1/1985 30000 7.000 28415.00 58115.00
9/ 1/1985 27365.00 27365.00 85790.00 '
3/ 1/1926 30000 7.500 27365.00 57365.00
9/ 1/1986 26240.00 26210.00 83605.00
3/ 1/1987 35000 8.000 26240.00 61240.00
9/ 1/1987 24840.00 24810.00 86080.00
3/ 1/1988 35000 8.500 24840.00 59810.00
9/ 1/1988 23352.50 23352.50 83192.50
3/ 1/1989 40000 9.000 23352.50 63352.50
9/ 1/192? 21552.50 21552.50 84905.00
3/ 1/1990 45000 9.250 21552.50 66552.50
9/ 1/1990 19471.25 19471.25 86023.75
3/ 1/1991 50000 • 9.500 19471.25 69471.25
9/ 1/1991 17096.25 17096.25 86567.50
3/ 1/1992' 55000 9.750 17096.25 72096.25
9/ 1/1992 14415.00 14415.00 86511.25
3/ 1/1993 60000 10.000 14415.00 74415.00
9/ 1/1993 11415.00 11415.00 85830.00
3/ 1/1994 65000 10.200 11415.00 76115.00
9/ 1/1994 8100.00 8100.00 84515.00
3/ 1/1995 75000 10.400 8100.00 83100.00
9/ 1/1995 4200.00 4200.00 87300.00
3/ 1/1996 80000 10.500 4200.00 84200.00 84200.00.
SUBTOTALS 600000 452925.00 1052925.00 1052925.00
PREM, (DISC) .00 .00 .00
TOTALS 600000 452925.00 1052925.00 1052925.00
ACC INT: .00
RATE: 9.9108
BOND YRS: 4570.00
AVE LIFE: 7.6167
FIRST PAYMENT WAS NOT REDUCED BY ACCRUED INTEREST
1/13/1984 AT 13:15:42
54
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
the long term debt would be possible because property tax revenue for 1983
taxes collected in 1984 will be $5,000 more than the amount shown in Table 12.
If operating revenues, operating expenses and debt service for the current
long term debt were to remain constant, then the construction of a 1 mgd water
plant in the $500,000 price range does appear to be a viable' option for the
District. However, nothing remains constant. It is reasonable to assume at
the present rate structure, operating revenues will increase somewhat due to
new taps. Operating expenses would probably increase in line with inflation
for the area. The major factor which changes in the future in this analysis
is the amount of working capital required for existing debt service. Table 17
below presents a debt service schedule for the 1980 general obligation bonds
issued by the District:
TABLE 17
DEBT SERVICE FOR THE
1980 GENERAL OBLIGATION BOND ISSUE
Total
Year Principal Interest Requirements
1984 $ 10,000 $ 23,375 $ 33,375
1985 10,000 22,525 32,525
1986 10,000 21,675 31,675
1987 60,000 18,700 78,700
1988 60,000 13,600 73,600
1989 65,000 8,287 73,287
1990 65,000 2,763 67,763
S 280,000 $ 110,925 $ 390,925
SCHMUESER & ASSOCIATES, INC.
55
The analysis which estimated a value of $64,685 for new working capital avail-
able for reduction of new long term debt included an interest expense of ap-
proximately $24,000 and a principal payment of $10,000 for a total of $34,000
debt service for the 1980 G.O. bond issue. As can seen from Table 17, the
total debt service requirements would remain in the $30,000 range until 1987
when the total debt service requirements would increase to $78,700.
(Please Note that the annual debt service requirements for the 1978 revenue
bond issue remain fairly constant throughout the life of the bonds.) The net
effect of this approximate $46,000 increase in debt service for the 1980 bond
issue is that in 1987 there would be a $46,000 reduction in the net working
capital available for financing new long term debt.- The conclusion which must
be drawn from this is that the WGSWD is not capable of financing a $500,000
bond issue unless the 1980 G.O. bonds can be refinanced in some manner to keep
the total debt service requirements around $32,000 per year. As an
alternative the District could provide for an increase in operating revenue
either by increasing service charges or increasing the mill levy to generate
additional property tax. An alternate source of providing an increase working
capital would be to increase tap fees.
If the WGST D wishes to pursue the financing of a $500,000 to $600,000 improve-
ment, it is recommended that a qualified bond counsel be retained to review
this report and to investigate the viability of new bond issues and the pos-
sibility of refinancing the 1980 G.O. bond issue. The possibility of generat-
ing additional operating revenue from service charges or mill levy should also
be reviewed in detail in conjunction with the increase in working capital that
SCHMUESER & ASSOCIATES, INC. Si
56
could be obtained by increasing tap fees.
Purchasing City Water
In March of 1983 Schmueser & Associates prepared a report for the WGSWD. The
purpose of this report was to assist the Board of Directors of the District in
determining the feasibility of entering into a contract with the City of Glen-
wood Springs for purchase of water from the City for distribution to users
within the District. The feasibility analysis included several projected fi-
nancial summaries and concluded that at a cost of $0.61 per 1,000 gallons with
the District assuming full operation maintenance responsibilities of the sys-
tem, the projected net income for 1983 would be $9,730. In order to arrive at
this net income, water use had to be estimated since only three months of
meter readings were available from the West Glenwood main meter vault.
Because the West Glenwood main meter has now been read for over one year,
we have a full year of operating revenue data from the City of Glenwood
Springs available. A much more accurate projection can now be made of the net
income that would be available to the WGSWD if they were to contract for water
from the City of Glenwood Springs and take over complete operation,
maintenance and accounting of their system. Tables 18 and 19 on the following
pages present an estimated statement of earnings and estimated change in
financial position assuming that the WGSWD purchases water from the City of
Glenwood Springs at a cost of $0.61 per 1,000 gallons or $1.22 per 1,000
SA
SCHMUESER & ASSOCIATES, INC.
57
1
1
1
1
1
1
1
11
I
TABLE 18
ESTIMATED STATEMENT OF EARNINGS
ASSUMM WATER PURL ASED FROM
CITY OF GLENWOOD SPRINGS
Operating Revenue
Charges for Service
Property Tax
Tbtal Operating Revenue
Operating Expense
Cost of Purchased Water
Distribution System Maintenance
Maintenance Supervision
Depreciation
Amortization
Legal and Accounting
Directors Fees - - -
Insurance
Office Expense
Meeting Room Rent
Telephone
Engineering Fees
Total Operating Expenses
Operating Income (Loss)
Nonoperating Rev.(Exp)
Interest Income
Interest Expense
Net Income (Loss)
Water Cost
$1.22/1000 gals.
$ 191,400
14,400
S 205,800
Water Cost
$.61/1000 gals.
$ 191,400
14,400
$ 205,800
$ 170,000 $ 85,000
10,000 10,000
9,600. 9,600
19,700 19,700
900 900
21,600 21,600
2,200 ----- 2,200
800 800
.1,200 1,200
500 500
700 700
4,800 4,800
$ 242,000
(36,200)
$ 11,200
(44,100)
(69,100)
SCHMUESER & ASSOCIATES, INC.
58
$ 157,000
48,800
$ 11,200
(44,100)
15,900
TABLE 19
ESTIMATED CSE IN FINACIAL POSITION
PURCHASING WATER FROM CITY OF GLEN40 JD SPRINGS
AT $1.22/1,000 GALLONS & $.61/1000 GALLONS
Working Capital Provided From:
(1) Net Income (Loss)
(2) Add Expenses Not Req.
Capital Outlay
(a) Depreciation 19,700
(b) Amortization 900
$1.22/1000
(69,100)
$.61/1000
$ 15,900
19,700
900
Working Capital Provided From:
(a) Operations (48,500) 36,500
(b) Tap Fees 17,290 17,290
Total Working Capital Provided (31,210) 53,790
Working Capitol Required For:
(a) Current Long Term Dept 20,000 20,000
(b) Miscellaneous Improvements 3,000 3,000
Increase (Decrease) in
Working Capital
Analysis of Annual Change in Working
Capital
(54,210) 30,790
(a) Increase (Decrease) Current
Assets (54,210) 30,790
(b) Increase (Decrease) in
Working Capital (54,210) 30,790
SCHMUESER & ASSOCIATES, INC. 1
59
gallons. A review of these tables shows that the current service charges,
mill levy and tap fees are not adequate to generate sufficient working capital
to purchase water at a cost of $1.22 per 1,000 gallons. At this cost, the
District would currently be operating at approximately a $54,000 per year
loss. Purchasing water at $0.61 per 1,000 gallons on the other hand, gener-
ates an annual net increase in working capital of approximately $31,000 per
year.
0.5 mgd Conventional Filtration Plant
The purpose of this discussion will be to evaluate the feasibility of con-
structing a conventional filtration plant capable of treating 0.5 mgd of water
from Mitchell Creek. Since this size plant will not be capable of supplying
the complete needs of the District on a full time basis, it will be assumed
that water use in excess of the 0.5 mgd capacity will be purchased frau the
City of Glenwood Springs. Table 20 on the following page shows our estimate
of the amount of water that would be required to be purchased from the City of
Glenwood Springs under this scenario. This amount is estimated to be approx-
imately 23 million gallons per year. Thus, at current demands, a 0.5 mgd wa-
ter treatment plant would supply over 80% of the water needed by the District.
At costs of $0.61 per 1,000 and $1.22 per 1,000 gallons the cost of purchasing
this water from the City of Glenwood Springs would be $14,000 and $28,000
respectively.
SCHMUESER & ASSOCIATES, INC.St
60
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
TABLE: 20
A[•]OUNP OF WATER TO BE PURCHASED
FRCM THE CITY OF GLENWOOD SPRTMS IF
14 D INSTALLS T S A 0.5 mgd PLANT(1)
Q Provided Total Def.
Est. Avg. By WDSWD Def.Avg. for for month Accum. Total
Month Q.mgd rngd Month mqd mg Def., mg
January 0.25 0.5 0.00 0.00 0.00
Febuary 0.25 0.5 0.00 0.00 0.00
March 0.25 0.5 0.00 0.00 0.00
April 0.25 0.5 0.00 0.00 0.00
May 0.40 , 0.5 0.00 0.00 0.00
June 0.65 0.5 0.15 4.50 4.50
July 0.70 0.5 0.20 6.20 10.70
August 0.75 0.5 0.25 7.75 18.45
September 0.65 0.5 0.15 4.50 22.95
October 0.30 0.5 0.00 0.00 22.95
November 0.25 0.5 0.00 0.00 22.95
December 0.25 0.5 0.00 0.00 22.95
(1) This is an estimate based on current 1983 demands.
X11
SCHMUESER & ASSOCIATES, INC.
61
1
1
1
1
1
1
1
1
1
1
Shown below in Table 21 are the estimated costs of 0.5 mgd conventional
filtration plant:
TABLE 21
ESTIMATED CAPITAL CON'S
0.5 mgd CONVENTIONAL TREATMENT PLANT
1. Basic Equipment $ 125,000
2. Building 25,000
3. Clearwell 15,000
4. Diversion 20,000
5. Backwash Ponds 3,000
6. Pumps, Raw and High Service 25,000
7. Chlorination Equipment 10,000
8. Plant Piping 15,000
9. Yard Piping, Raw and Finished 20,000
10. Land 25,000
11. Site Improvements 15,000
12. Electrical 20,000
13. Equipment Installation 20,000
Subtotal $ 338,000
Plus 25% 84,500
Total $ 422,500
SCHMUESER & ASSOCIATES, INC.
62
Design assumptions will not be listed for each of the items in the above
table. However, the same type of analysis was performed for this alternative
as was conducted for the analysis of the 1.0 mgd conventional and diatomaceous
alternatives. The cost estimate does not include any provisions for expanding
the plant to a larger size such as oversizing the building, clearwell,
diversion, piping, backwash ponds, etc. for a future larger facility. Since
this plant will annually produce approximately 80% of the water that a 1.0 mgd
plant will produce, it was assumed that operation and maintenance costs of the
0.5 mgd plant are 80% of those previously estimated for the 1.0 mgd
conventional filtration plant or ($60,000 x 0.8).
Tables 22 and 23 on the following pages present an estimated statement of
earnings and an estimate of the net working capital available for financing
future long term debt assuming a new 0.5 mgd conventional treatment plant is
installed. The tables also show how the cost of purchased water affects net
income and net working capital available for financing new long term debt. At
a cost of $0.61 per 1,000 gallons for purchased water from the City, $62,685
would be available to the District in terms of net working capital available
for financing new long term debt. At a cost of $1.22 per 1,000 gallons for
water purchased from the City, $48,685 would be available to the District in
terms of net working capital available for new long term debt. It is estima-
ted that approximately $55,000 to $60,000 would be required in terms of debt
service to finance a $420,000 bond issue necessary for the construction of a
0.5 mgd plant. Thus, it can be seen that at a cost of $0.61 per 1,000 gallons
the District could generate sufficient net working capital to finance
SCHMUESER & ASSOCIATES, INC. Si
63
r
' TABLE 22
ESTIMATED STATEMENT OF EARNINGS
NEW 0.5 mgd PLS
1
Operating Revenues
11 Charges for Services $ 191,400.00
Property Taxes - Net (1) 14,400.00
Total Operating Revenues $ 205,800.00
Operating Expenses @$0.61/1000 gal. @$1.2.2/1000 gal.
Water Plant O&M $ 48,000 $ 48,000
Cost of Purchased Water 14,000 28,000
II
Distribution System Repair
and Maintenance 10,000 10,000
Amortization Expense 933 933
Accounting & Legal 21,600 21,600
Directors' Fees 2.205 2,205
Depreciation 19,671 19,671
Insurance 1,500 1,500
Office Expense 1,200 1,200
Meeting Room Rent 500 500
Telephone 700 700
Engineering Fees 4,800 4,800
Tbtal Operating Expenses $ 125,109 $ 139,109
IIOperating Income (Loss) 80,691 66,691
II
Nonoperating Revenue (Exp.)
Interest Income 11,200 11,200
Interest Expense (44,100) (44,100)
i1
1
1
1
1
1
Net Income (Loss)
47,791 33,791
(1) The Garfield County Assessors Office reports that 1983 taxes will increase
to $19,475.
(2) Depreciation of new plant is not included.
SCHMUESER & ASSOCIATES, INC.
64
1
1
1
1
1
1
1
1
1
1
1
1
1
TABLE 23
ESTIMATE OF CAPITAL AVAILABLE
FOR REDUCTION of FoTURE
LONG TERM DEBT
WITH 0.5 mgd PLANT
@$0.61 /100 @$1.22/1000
Working Capital Provided from:
(1) Net Income (Loss) $ 47,791 S 33,791
(2) Add Expenses not requiring
outlay of Working Capital
(a) Depreciation 19,671 19,671
(b) Amortization
933 933
Working Capital Provided From:
(a) Operations
68,395 54,395
(b} Tap Fees
17,290 17,290
Total Working Capital Provided
85,685 71,685
Working Capital Used For:
(a) Reduction of Current Long Term
Debt 20,000 20,000
(b) Miscellaneous Improvements 3,000 3,000
Total Use of Working Capital
23,000 23,000
Net Working Capital Available For 62,685 48,685
New Long Term Debt for 0.5 mgd plant
SCHMUESER & ASSOCIATES, INC.
65
the debt service for a $420,000 bond issue. However, if the District had to
purchase water from the City at a cost of $1.22 per 1,000, gallons the $48,685
of net income generated would not be sufficient working capital for debt
service for the new $420,000 bond issue.
Although the construction of a new 0.5 mqd plant appears feasible if water
could be purchased at a cost of $0.61 per 1,000 gallons, it must be noted that
increases in the debt service requirements for the 1980 bond issue which will
occur in 1987, will require an additional $46,000 per year of debt service.
Thus, net working capital will be decreased by the same amount. The
construction of a 0.5 mgd plant would not be feasible unless additional
operating revenue were generated, unless additional working capital from tap
fees was generated or unless the 1980 bond issue could be refinanced to keep
debt service at approximately its same level.
SCHMUESER & ASSOCIATES, INC.
66
SUMARY AND CONC LUSIC S
Listed below is a summary of the findings of this report:
1. The WGSWD is currently using approximately 139 million gallons
per year of water. Current maximum day demands are estimated to
be approximately 1.0 mgd (700 gpm or 1.6 cfs) See Table 1.
2. If the WGS%'D were to construct a water treatment plant which in
itself would supply the complete current needs of the District, a
1 mgd plant would be necessary.
3. If Mitchell Creek were to be the sole source of water supply for
the District, the reliability of the source is questionable in
terms of continuously supplying current summer and winter maximum
day demands. If either alluvial wells and/or the ability to pur-
chase water from the City of Glenwood Springs on a short term
basis was provided, Mitchell Creek would be an acceptable source
in terms of meeting current maximum day demands.
4. A source in addition to Mitchell Creek will be necessary in order
to meet future maximum day demands of the District.
SCHMUESER & ASSOCIATES, INC.
67
5. A limited amount of raw water storage to augment summer and win-
ter low flows would be very beneficial in increasing the relia-
bility of Mitchell Creek for supplying present and future demands
of the District.
6. From a limited review of existing water quality data, Mitchell
Creek appears to be a high quality source. The effects of spring
runoff and the Mitchell Creek Fish Hatchery on water quality
should be investigated further if the 1CSWD intends to develop
Mitchell Creek as a source. See Table 5.
7. The ability of Mitchell Creek to physically supply the District's
needs is of no value if sufficient water rights cannot be obtain-
ed to allow water to legally be diverted and used. The cost to
obtain this legal supply must be evaluated if the WGSWD intends
to develop Mitchell Creek as a surface water source.
8. A conventional filtration plant and diatomaceous earth filtration
plant are the two treatment processes felt to be the most viable
for treatment of water from Mitchell Creek.
9. Estimated capital costs of a 1 mgd conventional plant and DE
plant with a 25% contingency are $581,950 and $555,550 respect-
ively. See Tables 6 & 7.
SCHMUESER & ASSOCIATES, INC.
68
1
1
11
111
u
111
111
10. The estimated cost of retrofitting the City of Rifle's old pres-
sure sand filters to treat water frau Mitchell Creek is estimated
to be $560,770. See Table 8.
11. Annual operation and maintenance costs of a conventional plant
and DE plant are estimated to be $60,000 and $76,450 respec-
tively. See Tables 9 & 10.
12.
At current service charges it is estimated that the WGS D would
have a current annual operating revenue of $205,868.00 if the
District collected all revenues. See Table 12.
13. Under the scenario of supplying their own water and having com-
plete operation and maintenance responsibility for the total wa-
ter system, the District would currently have approximately
$64,000 of net working capital available for financing new long
term debt. See Tables 13 & 14.
14. $500,000 and $600,000 bond issues would require annual debt ser-
vice of approximately $70,000 and $85,000 respectively. See
Tables 15 & 16. Thus, the revenue from existing service charges
and property tax along with the working capital frau tap fees are
not sufficient to offset estimated operating expenses and exist-
ing debt service and leave sufficient net incase to cover the
SCHMUESER & ASSOCIATES, INC.
69
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
the City of Glenwood Springs, sufficient working capital for new
debt service is currently generated only if water could be
purchased at $0.61/1000 gallons. However, the 1987 increase in
debt service for the 1980 G.O. Bond issue would again reduce
available funds by $46,000, making the ability to finance a 0.5
mgd plant difficult unless additional operating revenue is
generated.
SCHMUESER & ASSOCIATES, INC.
' 72
Tables 18 & 19.
18. If the WGSWD were to construct a 0.5 mgd water treatment plant,
the plant would supply approximtely 80% of the water currently
used by the District. The estimated capital cost of a 0.5 mgd
plant is $422,500. Annual operation and maintenance is estimated
to be $48,000. Assuming water used in excess of that produced
from the 0.5 mgd plant is purchased from the City of Glenwood
Springs, the annual cost of purchased water would be $14,000 and
$28,000 per year based on respective water costs of $0.61/1000
gallons and $1.22/1000 gallons. See Tables 20 & 21.
19. Based upon the estimated operating costs of an 0.5 mgd plant and
current revenue projections, the net working capital available
for financing new long term debt would be $62,685 if water not
supplied from the new plant was purchased from the City of
Glenwood Srrings at a cost of $0.61/1000 gallons. At a cost of
$1.22/1000 gallons $48,685, would be available. See Tables 22 &
23.
20. The estimated annual debt service requirements for a $420,000
bond issue for the construction of a new 0.5 mgd plant are
$55,000 to $60,000. Thus, under the scenario of constructing a
new 0.5 mgd plant and purchasing a limited amount of water from
SCHMUESER & ASSOCIATES, INC.
71
debt service for a new $500,000 to $600,000 1 mgd water treatment
plant.
15. 1983 property taxes will increase operating revenue by approxi-
mately $5,000 over that collected for 1982. This increase in
revenue would bring the current net working capital available to
finance new long term debt close to the total debt service re-
quirements for a $500,000 bond issue. However, in 1987 the an-
nual -debt service requirement of the 1980 General Obligation Bond
Issue will increase by $46,000. The net effect is that in 1987
there will be a $46,000 reduction of the net working capital
available for new long term debt.
16. At the current level of service charges, property tax and tap
fees, the WGSWD is not capable of financing a 1 mgd water treat-
ment plant (assuming a plant could be built for $500,000) unless
the 1980 G.O. bonds can be refinanced in some manner to keep the
total debt service requirements around $32,000 per year.
17. If the WGSWD were to negotiate a contract with the City of Glen-
wood Springs to purchase water and take over complete operation,
maintenance and accounting of the water system, it is estimated
that the District would have a net annual increase (decrease) in
working capital of ($54,210) and $30,790 if water were purchased
at $1.22/1000 gallons and $0.61/1000 gallons respectively. See
SCHMUESER & ASSOCIATES, INC.
70