HomeMy WebLinkAboutSoils ReportHEPWORTH-PAWLAK GEOTECHNICAL
1Ivhuurrh 1'.I 11i (k F1e ltrl> ,1I, Iu4.
5020 r't Ru.1,1 15-1
I i1vrn1 kI Brun: t:u1,•r.nf,i tilfl�l
r11ori, 970-'14i 0:,!..1
11 -"Ax q70 -94-1-84i 1
i' n III #y _rnirltl' rri1k..0111
SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED MCLELLAND RESIDENCE
LOT 50, FIRST EAGLES POINT
79 EAGLE RIDGE DRIVE
BATTLEMENT MESA, COLORADO
JOB NO. 114 526A
DECEMBER 22, 2014
PREPARED FOR:
GIARD HOMES
ATTN: ROGER GIARD
1431 AIRPORT ROAD
RIFLE, COLORADO 81650
(retard n rof.net)
.-irk r 303-,M41-7119 • l=.t}It,r,k111Springs 71t)-633.-55(2 * Sil‘crrhtirn 97(46.S -19S9
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY ............. ........ .... ............ ..... ....................... .....,, - 1 -
PROPOSED CONSTRUCTION -1 -
SITECONDITIONS............. .. ... ............. ........ .................. .............. ....,........................ - 2 -
} IF,LD EXPLORATION - 2 -
SUBSURFACE CONDITIONS ..�„ - 2 -
FOUNDATION BEARING CONDITIONS •*.,,.,.m - 3 -
DESIGN RECOMMENDATIONS - 4 -
FOUNDATIONS - 4
FLOOR SLABS ,................ ........ -5-
SURFACE DRAINAGE - 5 -
LIMITATIONS - 6 -
FIGURE 1 - LOCATION OF EXPLORATORY BORING
FIGURE 2 - LOG OF EXPLORATORY BORING
FIGURE 3 - LEGEND AND NOTES
FIGURE 4 - GRADATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
Job No. 114 526A Ggstech
PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed residence to be located
on Lot 50, First Eagles Point Subdivision, with a physical address of 79 Eagle Ridge
Drive, Battlement Mesa, Colorado. The project site is shown on Figure 1. The purpose
of the study was to develop recommendations for the foundation design. The study was
conducted in accordance with our agreement for geotechnical engineering services to
Giard Homes, dated November 26, 2014.
A field exploration program consisting of an exploratory boring was conducted to obtain
information on the subsurface conditions. Samples of the subsoils obtained during the
field exploration were tested in the laboratory to determine their classification and other
engineering characteristics. The results of the field exploration and laboratory testing
were analyzed to develop recommendations for foundation types, depths and allowable
pressures for the proposed building foundation. This report summarizes the data obtained
during this study and presents our conclusions, design recommendations and other
geotechnical engineering considerations based on the proposed construction and the
subsurface conditions encountered.
PROPOSED CONSTRUCTION
The proposed residence will be a 1 story structure with a structural floor over a
crawlspace in the living areas and an attached garage with a slab -on -grade floor. Grading
for the structure is assumed to be relatively minor with cut and fill depths between about
2 to 4 feet. We assume relatively light foundation loadings, typical of the proposed type
of construction.
If building loadings, location or grading plans change significantly from those described
above, we should be notified to re-evaluate the recommendations contained in this report.
Job No. 114 526A
-2 -
SITE CONDITIONS
The site is currently an undeveloped residential lot on the northwest corner of Eagle
Ridge Drive and Eagle Court in the First Eagles Point Subdivision. The lot had been
graded relatively flat and currently has a sparse coverage of grass and weeds. A mix of
undeveloped and developed lots surrounded the subject property with moderately sized
wood framed residential structures on the developed lots. Numerous medium to large
basalt boulders were observed to have been used as landscape material on the developed
lots.
FIELD EXPLORATION
The field exploration for the project was conducted on December 8, 2014. One
exploratory boring was drilled at the location shown on Figure 1 to evaluate the
subsurface conditions. The boring was advanced with 4 inch diameter continuous flight
augers powered by a truck -mounted CME -45B drill rig. The boring was logged by a
representative of Hepworth-Pawlak Geotechnical, Inc.
Samples of the subsoils were taken with 1% inch and 2 inch I.D. spoon samplers. The
samplers were driven into the subsoils at various depths with blows from a 140 pound
hammer falling 30 inches. This test is similar to the standard penetration test described
by ASTM Method D-1586. The penetration resistance values are an indication of the
relative density or consistency of the subsoils. Depths at which the samples were taken
and the penetration resistance values are shown on the Log of Exploratory Boring, Figure
2. A disturbed sample of the near surface soils was obtained from a depth of about 1 foot
below the surface. The samples were returned to our laboratory for review by the project
engineer and testing.
SUBSURFACE CONDITIONS
A graphic log of the subsurface conditions encountered at the site is shown on Figure 2.
The subsoils consist of about 2 feet of sandy silt and clay overlying clayey gravel and
Job No. 114 526A
-3 -
basalt cobbles and boulders with a fine-grained soil matrix. Drilling in the coarse
granular soils with auger equipment was difficult due to the cobbles and boulders and
drilling refusal was encountered in the deposit. The boring location was moved four
times in an attempt to achieve penetration of the basalt cobble and boulder stratum
without success.
Laboratory testing performed on samples obtained from the borings included natural
moisture content and gradation analyses. Results of gradation analyses performed on a
small diameter drive sample (minus 11/4 inch fraction) of the coarse granular subsoils are
shown on Figure 4. The laboratory testing is summarized in Table 1.
No free water was encountered in the boring at the time of drilling and the subsoils were
slightly moist to moist.
FOUNDATION BEARING CONDITIONS
The natural basalt cobble/boulder soils encountered below a depth of about 2 feet in our
exploratory boring should be suitable for support of the proposed residence on shallow
spread footings with some risk of movement. The depth and consistency of the basalt
cobble/boulder layer may vary across the building footprint. Areas of fine-grained soils
may be encountered during foundation excavation and should be evaluated by the
geotechnical engineer for bearing suitability at the time of construction. Boulder removal
during foundation excavation may leave substantial voids in foundation areas. Voids
created by boulder removal may be filled with lean mix "flow fill" concrete, properly
compacted structural backfill or structural concrete. Structural backfill in foundation
areas should consist of an imported granular material such as CDOT Class 6 base course,
placed in maximum 8 inch loose lifts and compacted to 98 percent of the standard Proctor
value for the material at a moisture content near optimum. Prior to placement of
structural fill the subgrade soils in foundation areas should be moisture conditioned and
compacted. A representative of the geotechnical engineer should observe the foundation
excavation for bearing conditions prior to the placement of structural fill or concrete.
Job No. 114 526A eggetech
-4 -
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory boring and the
nature of the proposed construction, we recommend the building be founded with spread
footings bearing on the natural cobble/boulder soils.
The design and construction criteria presented below should be observed for a spread
footing foundation system.
I) Footings placed on the undisturbed natural basalt cobble/boulder soils
should be designed for an allowable bearing pressure of 2,500 psf Based
on experience, we expect settlement of footings designed and constructed
as discussed in this section will be about 1 inch or less.
2) The footings should have a minimum width of 16 inches for continuous
walls and 2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided
with adequate soil cover above their bearing elevation for frost protection.
Placement of foundations at least 36 inches below exterior grade is
typically used in this area.
4) Continuous foundation walls should be reinforced top and bottom to span
local anomalies such as by assuming an unsupported length of at least 12
feet. Foundation walls acting as retaining structures should also be
designed to resist a lateral earth pressure corresponding to an equivalent
fluid unit weight of at least 50 pcf. Foundation wall backfill can consist of
the on-site soils or imported granular soil and should be placed in
maximum 8 inch loose lifts and be compacted to a minimum of 95 percent
of the standard Proctor value for the material at a moisture content near
optimum. An underdrain should not be needed around foundation walls if
Job No. 114 526A Gatech
-5 -
foundation wall backfill is properly compacted and the recommendations
in the Surface Drainage section of this report are %fowed.
5) The upper silt and clay soils and any loose or disturbed soils should be
removed and the footing bearing level extended down to the relatively
dense natural cobble/boulder soils. The exposed soils in footing area
should then be moistened and compacted.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to assess the bearing conditions.
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded garage
slab -on -grade construction. To reduce the effects of some differential movement, floor
slabs should be separated from all bearing walls and columns with expansion joints which
allow unrestrained vertical movement. Floor slab control joints should be used to reduce
damage due to shrinkage cracking. The requirements for joint spacing and slab
reinforcement should be established by the designer based on experience and the intended
slab use.
All fill materials for support of floor slabs should be compacted to at least 95% of
maximum standard Proctor density at a moisture content near optimum. Required fill can
consist of the on-site soils devoid of vegetation, topsoil and oversized rock.
SURFACE DRAINAGE
The following drainage precautions should be observed during construction and
maintained at all times after the residence has been completed:
3) Inundation of the foundation excavations and underslab areas should be
avoided during construction.
2) Exterior backfill should be adjusted to near optimum moisture and
compacted to at least 95% of the maximum standard Proctor density in
Job No. 114 526A
-6 -
pavement and slab areas and to at least 90% of the maximum standard
Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be
sloped to drain away from the foundation in all directions. We
recommend a minimum slope of 12 inches in the first 10 feet m unpaved
areas and a minimum slope of 3 inches in the first 10 feet in paved areas,
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
5) Landscaping which requires regular heavy irrigation should be located at
least 5 feet from foundation walls.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical
engineering principles and practices in this area at this time. We make no warranty either
express or implied. The conclusions and recommendations submitted in this report are
based upon the data obtained from the exploratory boring drilled at the location indicated
on Figure 1, the proposed type of construction and our experience in the area. Our
services do not include determining the presence, prevention or possibility of mold or
other biological contaminants (MOBC) developing in the future. If the client is
concerned about MOBC, then a professional in this special field of practice should be
consulted. Our findings include interpolation and extrapolation of the subsurface
conditions identified at the exploratory boring and variations in the subsurface conditions
may not become evident until excavation is performed. If conditions encountered during
construction appear different from those described in this report, we should be notified so
that re-evaluation of the recommendations may be made,
This report has been prepared for the exclusive use by our client for design purposes. We
are not responsible for technical interpretations by others ofour information. As the
project evolves, we should provide continued consultation and field services during
construction to review and monitor the implementation of our recommendations, and to
Job No. 114 526A "` Giggled,
-7 -
verify that the recommendations have been appropriately interpreted. Significant design
changes may require additional analysis or modifications to the recommendations
presented herein. We recommend on-site observation of excavations and foundation
bearing strata and testing ofstructural fill by a representative ofthe geotechnical
engineer.
Respectfully Submitted,
HEPWORTH - PAWLAK GEOTECHNICAL, INC.
James A. Parker, P.E., P.G.
Reviewed by:
Steven L. Pawlak, P.E.
JAPrIjf
cc: Westar Engineering - Stephen Kesler (westar a,ro£net)
Job No. 114 526A
Gegtech
APPROXIMATE SCALE
1"=30'
LOT 49
LOT 51
A
/ \
/ \
// LOT 50
L
EAGLE
COURT
•
s.
EAGLE RIDGE DRIVE
J
114 526A
HtchHC,o uKeC►L
LOCATION OF EXPLORATORY BORING
FIGURE 1
I-
LL..
G
a
co
in
0
5
BORING 1
-, WC=13.5
.J
' -200=92
W125 12
l�;d,
C�• 27/6,20/1
{' �■ WC=9.3
+4=20
-200=57
0
5
10 10
114 526A
NOTE: Explanation of symbols is shown on Figure 3.
HLPWORTH•PAWLAK GEOTECHNICAL
LOG OF EXPLORATORY BORING
FIGURE 2
LEGEND:
1
L
b
SILT AND CLAY (ML -CL); sandy, with gravel and occasional cobbles, soft to stiff, slightly
moist to moist, brown.
COBBLES AND BOULDERS (GC); with gravel and sandy clay matrix, medium dense to dense,
slightly moist to moist, brown, basalt rock.
Relatively undisturbed drive sample; 2 -inch I.D. California liner sample.
Drive sample; standard penetration test (SPT), 1 3/8 inch I.D. split spoon sample, ASTM -1586.
Drive sample blow count; indicates that 25 blows of a 140 pound hammer falling 30 inches were
25/2 required to drive the California or SPT sampler 2 inches.
T
Practical drilling refusal.
NOTES:
1 The exploratory boring was drilled on December 8, 2014 with a 4 -inch diameter continuous flight power auger.
2. Location of the exploratory boring was measured approximately by pacing from features shown on the site plan
provided.
3. The exploratory boring elevation was not measured and the log of exploratory boring is drawn to depth.
4. The exploratory boring location and elevation should be considered accurate only to the degree implied by the
method used.
5. The lines between materials shown on the exploratory boring log represent the approximate boundaries between
material types and transitions may be gradual.
6. No free water was encountered in the boring at the time of drilling. Fluctuation in water level may occur with time.
7. Laboratory Testing Results:
WC = Water Content (%)
+4 = Percent retained on the No. 4 sieve
-200 = Percent passing No. 200 sieve
114 526A
H
HEPWORTH-PAwwc GEO1ECHN11cA1.
LEGEND AND NOTES
FIGURE 3
1,
HYDROMETER ANALYSIS+ SIEVE ANALYSIS I
2pqq wp TIME READINGS U.S. STANDARD SERIES 1 CLEAR SQUARE OPENINGS
0 45 a.15 MIN. 60MINI9MIN.4 MIN. 1 MIN. #200 #100 #50 #30 #16 #8 #4 3/8' 3/4' 1 1/2' 3' 56' 8` 100
=a�.l..—aalaaaa
aaaaila-iia
10
20
30
40
50
6o
70
80
90
100
.001 .002 .005 .009 .019 .037 .074 .150 .300 .600 1.18 2.36
-ami—i
anal=
�a-M-arm-a
a�a-mama a-
�a'aaa�a— a= Maa�ailaaa
-i
i`ill gamma
a�-Mamma aaaal�=a--a--mama-a--aaaal___ as a+
Mamma i a /aaalaaa — aa.aM a--
arai —aaaa
a�aa,
_Ja-aMaa —Mama —mama
�Mal MI Mai
-+mar-"F �r �aaal
�— aa/a. a .mai ami —aaa—
wawa
alaimalala
�� Tama maia—a
aaa aaa=a— aaa�_aaaa-= mama
�laai rsaaa as=lama—aas� a
halal a—aa allai
�-a�� a�—a-�aaaMaaMat=
as
aaa�aa`i aWAI.—aaaa��aaMalla
Mr-ammo—�aaaa-aala-
MaawAMma
a-aaaas aaMMama=�Waallr l
=alaa-
ir��-waa as
a-arae-iaa-=Ma
a_aaMaa-aaa
a=Mamma:_Mama
a ma aaa
mama• -,a ms aa�
Maia
■iia aaaRaRaal lm lama =Ma
ala.
Mama^aaa@aa m Mama Mai Mama.—.Ra aaaa�r aa�l�llla>•aaa'� a� Mama `a'
—alaraaaa�iaaalaaaaalaaaal Mama aaam. aaa ai am Mama—Mama—Maas
aa-aaaaaeai aa-aaalA[ma: ll -aa lMama a --ll
aaaa11aaa-as—aiaaa alM'Alalll aaalaai
a—aa—aaM Ma- a— _a-llaal,-r
iaaal tam —r _•—Mlalla—Mai —Waal
aaa�aa—yam—i alaraaa` aaaa---- ----aaalll-a-ia a— a----
m aa-amara-aa iimaamial. Mama =�aaaaMlraa�a
Para
a--a�aia��aaa•IMIaa—ai ila ami aaaaa1aal
Mama Mamma—
+aa saaaa
fi >
r— aaaaaai ar
as-im aaaaNa
a"rmpaIN a=Mama aeras—aa i
a in saw
lama.-Illliaai -- --a__--
Mamma
ams a--- illi —aaa�
a ____Mama
=lam -aa�
a
a-aaaa
a aaaaiaaa
-a—aa--
=iaa---aa
aala--
a=�aa-aaaaa
Mamma
-aa
aaaaaaa —mama
a aaarrla--a Mama -a
aalala�
Cama—_a—
as -moi
sera -aha -a
ami
--mom aa—aaaaa
-aa am.
CaCC
a -ma aa -ii
�aaa-ala aa.
aa,
a•a-allaalai
— Mama 1=
aa-.IY.�as
Mamma
aaai err
--Mamma
laaaaala M���
alamma Baa -aa
Mama
aaa-,Mamma aaaaarsa_
aai.
a =allp a ---aa
aaa-m aaasaa—aa
as -rams
i
alma alma
aa- alma aaa
a=aaa--=aa-aa
1.1
aa—wla
a— Mama --aa as a
aaa
a=aaaasr��a
.111
ma-
Mala =
aallaaaa.a—
alaa
Mamma a—mi i
�aaa� i
Mama Mali as
--Ills Mala.
amara-aaaaaaa—
a Ma+a� Mai as arm
Mia Mama--Illlaai�aiaia=aa-, Mai s M a.=
Mai
DIAMETER OF PARTICLES IN MILLIMETERS
Mara aa
aIm a_a
aaa alaaa�alaa--
4.75 9.5 19.0 37.5
12.5
76.2 152 203
CCAYTO SO
GRAVEL 20 %
Flt+E 1 Mid I COARSE 1
Fig C 1 Olga I
mean
LIQUID LIMIT %
SAND 23 %
SILT AND CLAY 57 %
PLASTICITY INDEX %
SAMPLE OF: Gravelly Sandy Clay (Matrix) PROM: Boring 1 at 5 Feet
90
60
70
60
50
40
30
20
10
0
114 526A
HEPWORTFFPAWf..AK GBOTECHNICAL
GRADATION TEST RESULTS
FIGURE 4
Job No. 114 526A
{
Z
a w
c� IX
co
r w
v
a re
w 0
5w
-1O
m
a~J
= o
}
rto
a
w g
Z N
UNCONFINED
COMPRESSIVE
STRENGTH SOIL TYPE
(PSF)
Slightly Sandy Clay
Gravelly Sandy Clay (Matrix)
it
RG LIMB'S
PLASTIC
INDEX
w
a
O F-
3
• PERCENT
PASSING
NO. 200
SIEVE
N
I
o
a
a
z
.�
a
o
N
NATURAL
DRY
DENSITY
ipcfl
1
F
5-
zz0
�
Mt-1V7E
a;
11 SAMPLE LOCATION
Z
z
E
0 I
1.4
I