HomeMy WebLinkAboutCorrespondenceP.C. ARCHITECTS, INC.
DATE: 19 January 2015
PO Box 217 435.673.6579
St. George, UT84771-0217 pcarch@infowest.com
TO: Garfield County Community Development Department
To whom it may concern,
This letter is concerning the church facility for the Church of Jesus Christ of Latter Day
Saints that was recently construction on parcel #2407-171-17-001, 3.154 acres of the
Battlement Mesa Block #3 Subdivision, by Building Permit BLCO-4-14-3167.
It is our intent to provide decorative planting and re -vegetation of the church site.
However, with this project being finished during the winter months, we would request that
this planting and re -vegetation be allowed to happen in the spring to allow the plants and
grass seed mixes to grow properly. The approved planting plan calls for a SPMX grass
mix to be installed in the re -vegetation area per manufacturer's specifications. This grass
mix is provided by Applewood Seed Company and their recommendations call for this to
be installed in the late spring or summer months.
We plan to install these plants and the re -vegetation of the site per the Amended Land
Use Change Permit for the above mentioned parcel number. This was an Amendment to
Resolution 2014-18 (CUPA776B) that was approved on July 10th 2014 and recorded on
July 17th 2014. The narrative and drawings submitted with the Amendment indicate the
building and site will be developed in two phases. The landscaping that will be installed in
the spring consists of decorative plants, grass and rock mulch around the church building
and parking lot entrance with native grass/flower seed mix being planted on the
remainder of the site. Trees will also be planted along Sipprelle Drive.
Dennis Patten, Architect
P.C. Architects, Inc,
P.O. Box 217
St. George, UT 84770
Jim Wilson
From: Jeremy Simmons [Jeremy@warnerconst.com]
Sent: Wednesday. January 21, 2015 3:53 PM
To: Jim Wilson
Subject: FW: Letter to Garfield County
Attachments: GARFIELD COUNTY COMMUNITY DEVELOPMENT DEPARTMENT - LETTERHEAD,pdf
Jim, here is the vegetation letter you requested. I should have the commissioning letter from the
mechanical engineer hopefully sometime today as he was here yesterday and inspected the HCVAC
and plumbing and the HVAC system was tested and balanced by Air Pro. I have already sent you
Norm's final electrical inspection. Yesterday the church facility management team met with all
pertinent subcontractors for training: electrical, fire suppression, fire alarm, HVAC and plumbing.
Acme alarm signed a monitoring contract with the church and will send the NFP72? letter to state
electrical. It is my understanding that this document is part of the electrical final sign off according
to ACME Fire Alarm as proof of monitoring. Contact information is Clint Bartels 970 625 5535
clint@acmealarm.com. I will call him and request he copy you with this info. My number is 385 223
0680 if you think of anything else you require. As soon as I see the mechanical engineer's letter I
will forward it, then call for a final as we discussed so we can hopefully get the CO process complete
asap. Thanks for everything it has been a pleasure working with you on this LDS church in Parachute
permit # 3167
Thanks,
Jeremy Simmons
Warner & Associates Construction
146o North Main *IA Spanish Fork, UT 84660
(0) 8o1-794-ooz4 (F) 801-794-0042 (C) 385-223-0680
From: PC Architects [mailto:pcarch@pcarchinc.com]
Sent: Tuesday, January 20, 2015 12:28 PM
To: Jeremy Simmons (ieremywamerconst.com)
Subject: Letter to Garfield County
Jeremy,
Will you print this letter out so Dennis can sign it when he gets there.
Thanks,
Alison Hinton
P C Architects, Inc
301 E Tabernacle Ste 206
St. George, UT 84770
435 673 6579
pcarchericarchinc.com
This email is free from viruses and maiware because avast! Antivirus protection is active.
1
.111ROBONSON
f2111:515Vet
date' January 22. 2015
attn.
re
Gentlemen,
P.C. Architects
301 East Tabernacle
St. George, UT 84770
Michael Bradshaw
Parachute 2013 IND -130
R13075
All mechanical systems have been installed and commissioned and are functioning properly. We see
no reason from a mechanical stand point that would prohibit the building from being occupied.
Regards,
Robinson Engineering
Brandant Robinson
8504 N. 59th Ave., Glendale, AZ a -mail: pfaflUrobenq..00rea
mail P.O. Box 5519, Glendale, AZ 85312-5519
So. Utah Office: 1135 N. Main. Bldg. "B", Cedar City, Utah 84721
phone: (623) 930-1770
fax: (623) 435-2120
ph: (435) 867 1702
Jim Wilson
From: Jeremy Simmons [Jeremy@warnerconst.com]
Sent: Friday, August 29, 2014 11:09 AM
To: Jim Wilson
Cc: pcarch@pcarchinc.com
Subject: FW: inspection coordination with Garfield county inspector
Attachments: ESR -1232 Dryvit Outsulation.pdf; DSC01507.JPG; DSC01513.JPG; DSC01504.JPG
Jim, per our discussion will Bill the Drivet system inspector/rep, you were going to defer to Bill's inspection of the
system here at the parachute church permit #3167. Here is what I believe you were asking for...otherwise let me know.
Thanks,
Jeremy Simmons
Warner & Associates Construction
1460 North Main #iA Spanish Fork, UT 8466o
(0) 801-794-0024 (F) 801-794-0042 (C) 385-223-0680
From: Billy Petefish[mailto:petefish@outwestdrywall.com]
Sent: Thursday, August 28, 2014 12:01 PM
To: 'Jeremy Simmons'; 'Anthony Meadows'
Cc: bgroves@ascomasonry_.com; rmd34rd@gmaiI.com
Subject: RE: inspection coordination with Garfield county inspector
As the Dryvit rep for Outwest Drywall Supply I will be observing the application of the Outsulation System weekly to
insure Dryvit warranty of the project.
On August 27, 2014 I observed the application of Dryvit's Aqua Flash and Backstop and approve. Also attached is a copy
of the ESR report the inspector requested and a few photos of the project. Please feel free to contact me with any
questions or concerns.
Regards
Billy
Outwest Drywall Supply
970.248.9800
petefish@outwestdrvwall.com
From: Jeremy Simmons [mailto:ieremv@warnerconst.coml
Sent: Wednesday, August 27, 2014 1:45 PM
To: petefish@outwestdrvwall.com
Cc: joel@warnerconst.com
Subject: inspection coordination with Garfield county inspector
Bill, as Drivet rep/inspector, just a note to confirm our conversation with Jim Wilson bldg. inspector, You will provide
code approvedspecification report and on each phase of drivet system inspections you will perform on site, which will
be forwarded to Jim Wilson bldg. inspector. He will defer to your inspection reports.
Thanks,
Jeremy Simmons