Project Address Parcel No. Subdivision
4400 CR 200
DEBE QUE, CO 81635-
244309100001
Owner Information Address Phone
P.O.Box 200
De Beque CO 81635
Contractor(s) Phone
Mountain Estates Builders (970)926-4780
Proposed Construction I Detatls
7/1/09, Per Fred he is issuing the SUP Reso today, is ok to issue permit
Julie.
FEES DUE FEES PAID
Primary Contractor
Yes
Valuation: $ 283,373.82
Total Sq Feet: 5276.25
Amount llriv Total Paytype
Commercial Building Fee
Plan Check Fee
Total:
Wednesday, July 1, 2009
$2,024.15
$1,315.70
$3,339.85
lnv # BLC0-7-09-19526
$ 3,339.85 Check# 1981
Check# 1988
$1,315.70
$2,024.15
$0.00
Section Township Range
9 8 98
.
Cell
Required Inspections:
Fodo.pootloooo•ll' 1 {970)384-5003
Inspection IVR
See Permit Record
Building Department
Copy
2
GARFIELD COUNTY BUILDING PERMIT APPLICATION
108 8ili Street, Suite 401, Glenwood Springs, Co 81601
Phone: 970.945-8212 I Fax: 970-384-3470 I lospection Line: 970-384-5003
www.garfield~countv.com
Authority. This application for a Building Permit must be signed by the Owner of the property, described above, or an authorized agent. If the signature below is not that of the Owner, a separate
letter of authority, signed by the Owner, must be provided with this Application.
Legal Acs;m A Building Permit cannot be issued without proof oflegal and adequate access to the property for purposes of inspections by the Building Department.
Other Permits Multiple separate permits may be required: (I) State Electrical Penn it, (2) County ISDS Permit, (3) another pennit required for use on the property identified above, e.g. State or
County Highway/ Road Access or a State Wastewater Discharge Permit
Void Permit. A Building Pennlt becomes null and void if the work authorized is not commenced within 180 days of the date of issuance and if work is suspended or abandoned for a period of 180
days after commencement.
CERTIFICATION
I hereby certifY that I have read this Application and that the infonnation contained above is true and correct. I tmderstand that the Building Department accepts the Application, along with the plans
and specifications and other data submitted by me or on my behalf(submittals), ba~ed upon my certification as to accuracy.
Assuming completeness of the submittals and approval of this Application, a Building Penn it will be issued granting pennission to me, as Owner, to construct the structure(s) and facilities detailed on
the submittals reviewed by the Building Department.
In consideration of the issuance of the Building Pennit, I agree that I and my agents will comply with provisions of any federal, state or local law regulating the work and the Garfield Cmmty Building
Code, lSDS regulations and applicable land use regulations (County Regulation(s)). I acknowledge that the Building Pennit may be suspended or revoked, upon notice from the County, if the location,
construction or use of the structure(s) and fucility(ies), described above, are not in compliance with Cotmty Regulation(s} or any other applicable Jaw.
I hereby grant permission to !he Building Department to enter the property, described above, to inspect tbe work. I further acknowledge that tl1e issuance oftl1e Building Permit does not prevent the
Building Official from: (1) requiring the correction of errors in the submittals, if any, discovered after issuance; or (2) stopping construction or use of the structure(s) or facility(ies) if sucl1 is in violation
of County Regulation(s) or any other applicable law.
Review of this Application, including submittals, and inspections of the work by the Building Department do not constitute an acceptance of responsibility or liability by the CoUilty of errors, omissions
or discrepancies. As the Owner, I acknowledge that responsibility for compliance with federal, state and local laws and County Regulations rest with me and my anthorized agents, including witlmut
limitation my architect designer, engineer and! or builder.
I HEREBY ACKNOWLEDGE THAT I HAVE READ AND UNDERSTAND THE NOTICE & CERTIFICATION ABOVE:
STAFF USE ONLY
.II> ('
spe•:c:·nt2ao42 x«2Jt .6?t] "'f1757~~< ~'58.~]
6 ~~
/ p(J . ~q'l·'l
Adjusted Valuation: Plan Check Fee: Permit Fee: Ma/eFee: Mise Fees:
~e;~~7:;.8Z t'!J(5"· 70 2ot.t .rs
ISDSif'''·''" Total Fees: Fees Paid: Balance Due: , / BP No & Issue Date: ISDS No & Issued Date: ~r~"~w ~4il2·~5' J ?215 [O 2LJ<i7· IG' f:liD-1-()q-ltDd. -[[03
Setbacks: OCCGroup: Cons! Type: z~{<( L B V-B
B~DEPT:~ , ()l/fto/~ p~:\\~' (!)/~t1 A~--~~ DATE APR~ ,-~~ DATE
The following items are required by Garfield County for a final Inspection:
1) A final Electrical Inspection from the Colorado State Electrical Inspector.
2) Permanent address assigned by Garfield County Building Department and posted at the
structure and where readily visible from access road.
3) A finished roof; a lockable building; completed exterior siding; exterior doors and windows
installed; a complete kitchen with cabinets, sink with hot & cold running water, non-absorbent
kitchen floor covering, counter tops and finished walls, ready for stove and refrigerator; all
necessary plumbing.
4) All bathrooms must be complete, with washbowl, tub or shower, toilet, hot and cold running
water, non-absorbent floors, walls finished, and privacy door.
5) Steps over three (3) risers, outside or inside must be must have handrails. Balconies and decks
over 30" high must be constructed to all IBC and IRC requirements including guardrails.
6) Outside grading completed so that water slopes away from the building;
7) Exceptions to the outside steps, decks, grading may be made upon the demonstration of
extenuating circumstances., i.e. weather. Under such circumstances A Certificate of
Occupancy may be issued conditionally.
8) A final inspection sign off by the Garfield County Road & Bridge Department for driveway
installation, where applicable; as well as any final sign off by the Fire District, and/or State
Agencies where applicable.
A CERTIFICATE OF OCCUPANCY (C.O.) WILL NOT BE ISSUED UNTIL ALL THE
ABOVE ITEMS HAVE BEEN COMPLETED.
A C.O. MAY TAKE UP TO 5 BUSINESS DAYS TO BE PROCESSED AND ISSUED.
OWNER CANNOT OCCUPY OR USE DWELLING UNTIL A C.O. IS ISSUED.
OCCUPANCY OR USE OF DWELLING WITHOUT A C.O. WILL BE CONSIDERED AN
ILLEGAL OCCUPANCY AND MAY BE GROUNDS FOR VACATING PREMISES
UNTIL ABOVE CONDITIONS ARE MET.
I understand and agree to abide by the above conditions for occupancy, use and the issuance of a
C.O. for the building identified in the Building Permit.
DATE
FEE ESTIMATE
FOR SIF STICK BUILT HOMES
(ALL FEES ARE ESTIMATES UNTIL FINAL PLANS ARE REVIEWED)
Applicant: :1:/ /IJ [;vb/4N J&f /& M4&fltmr' Mt,{ /LC.
JobAddress: f!!{ ~,(J.i~= ~~-C# iff
Subd-Lotlblock: _$/. _,( ¢.-'2. ___ ;_ (!,. _'(__..:fJ
FINISHEDLIVINGSPACE:~~w()/~tJ:~x~ ff V/. (pj_ /
· 1>?-rerz. {(4i;1 ~ v
UNFINISHED BASEMENT: rt!£. c.4,1.J..t,. ir.rt: sf X · - / f<0 fQ
CRAWLSPACE: sf X 9.00= ------------------
GARAGE: sf X 18.00= --------------------~ -------------
UNCOVERED PATIO/DECK: sf X 12.00= -----------------------
COVERED PATIO/DECK: sf X: 24.00= --------~ -------------
MISC: --------------------------
MISO ________________________ __
TOTAL VALUATION:
THIS SECTION WILL BE DETERMEND BY GARFIELD COUNTY BUILDING & PLANNING
PLAN REVIEW FEE: cB)~
PERMIT FEE: 2D2YI5
TOTAL:
PERMIT: t f) 3' cfD
SEPTIC=
PERC:
GARFIELD COUNTY BUILDING AND PLANNING
970-945-8212
MINIMUM APPLICATION REQUIREMENTS
For
SINGLE FAMILY DWELLING CONSTRUCTION
Including
NEW CONSTRUCTION
ADDITIONS
ALTERATIONS
And
MOVED BUILDINGS
In order to understand the scope of the work intended under a permit application and expedite the
issuance of a permit it is important that complete information be provided. When reviewing a plan and
it's discovered that required information has not been provided by the applicant, this will result in the
delay of the permit issuance and in proceeding with building construction. The owner or contractor shall
be required to provide this information before the plan review can proceed. Other plans that are in line
for review may be given attention before the new information may be reviewed after it has been
provided to the Building Department.
TWO (2) SETS OF CONSTRUCTION DRAWINGS & TWO (2) SITE PLANS MUST BE
SUBMITTED FOR ALL APPLICATIONS.
Please review this document to determine if you have enough information to design your project
and provide adequate information to facilitate a plan review. Also, please consider using a design
professional for assistance in yonr design and a construction professional for construction of your
project. Any project with more than ten (10) occupants requires the plans to be sealed by a
Colorado Registered Design Professional.
To provide for a more understandable plan in order to determine compliance with the building, plumbing
and mechanical codes, applicants are requested to review the following checklist prior to and during
design. Applicants are required to indicate appropriately and to submit the completed checklist at
time of application for a permit.
Plans to be included for a Building Permit, must be on drafting paper at least 18"x24" and drawn
to scale.
1
Plans must include a floor plan, a concrete footing and foundation plan, elevations all sides with decks,
balcony, steps, hand rails and guard rails, windows and doors, including the finish grade line and
original grade. A section showing in detail, from the bottom of the footing to the top of the roof,
including re-bar, anchor bolts, pressure treated plates, floor joists, wall studs and spacing, insulation,
sheeting, house-rap, (which is required), siding or any approved building material. Engineered
foundations may be required.
A window schedule. A door schedule. A floor framing plan, a roof framing plan, roof must be
designed to withstand a 40 pound per square foot up to 7,000 feet in elevation, a 90 M.P.H. wind speed,
wind exposure B or C, and a 36 inch frost depth.
All sheets to be identified by number and indexed. All of the above requirements must be met or your
plans will be returned.
All plans submitted must be incompliance with the 2003 IRC.
1. Is a site plan included that identifies the location of the proposed structure or addition and distances to
the property lines from each comer of the proposed structure(s) prepared by a licensed surveyor
and has the surveyors signature and professional stamp on the drawing? Properties with slopes of
30% or greater must be shown on the site plan. (NOTE Section: 106.2) Any site plan for the
placement of any portion of a structure within 50 ft. of a property line and not within a previously
surveyed building envelope on a subdivision final plat shall be prepared by a licensed surveyor
and have the surveyor's signature and professional stamp on the drawing. Any structure to be
built within a building envelope of a lot shown on a recorded subdivision plat shall include a
copy of the building envelope as it is shown on the final plat with the proposed structure located
within the envelope.
Yes V
2. Does the site plan also include any other buildings on the property, setback easements and utility
easements? Please refer to Section 5.05.03 in the Garfield County Zoning Resolution if the
property you are applying for a building permit on is located on a comer lot. Special setbacks do
apply.
Yes ~
3. Does the site plan include when applicable the location of the l.S.D.S. (Individual Sewage Disposal
System) and the distances to the property lines, wells (on subject property and adjacent
properties), streams or water courses?
Yes V
4. Does the site plan indicate the location and direction of the County or private ro\ld accessing the
property? v'
Yes ____ _
2
5. Are you aware that prior to submittal of a building permit application you are required to show proof
of a legal and adequate access to the site? This may include (but is not limited to) proof of your
right to use a private easement/right of way; A County Road and Bridge permit; a Colorado Dept
of Highway Permit, including a Notice to Proceed; a permit from the federal government or any
combination. You can contact the Road & Bridge Department at 625-8601. See phone book for
other agencies
Yes V"
6. Do the plans include a foundation plan indicating the size, location and spacing of all reinforcing steel
in accordance with the IRC or per stamped engineered design?
Yes ._.........
7. Do the plans indicate the location and size of ventilation openings for under floor crawl spaces and the
clearances required between wood and earth?
Yes No ._...,-
8. Do the plans indicate the size and location of ventilation openings for the attic, roof joist spaces and
soffits?
Yes V' No -----
9. Do the plans include design loads as required by Garfield County for roof snow loads, (a minimum of
40 pounds per square foot up to & including 7,000 feet above sea level), floor loads and wind
loads? .........---Yes _____ _
10. Does the plan include a building section drawing indicating foundation, wall, floor, and roof
construction?
Yes ~
11. Does the building section drawing include size and spacing of floor joists, wall studs, ceiling joists,
roof rafters or joists or trusses?
Yes ~
12. Does the building section drawing or other detail include the method of positive connection of all
columns and beams?
Yes ~
13. Does the elevation plan indicate the height of the building or proposed addition from the
undisturbed grade to the midpoint between the ridge and eave of a gable or shed roof or the top
of a flat roof? (Building height measurement usually not to exceed 25 feet)
Yes ...........--
14. Does the plan include any stove or zero clearance fireplace planned for installation including make
and model and Colorado Phase II certifications or phase II EPA certification?
Yes No ~
3
15. Does the plan include a masonry fireplace including a fireplace section indicating design to comply
with the IRC?
Yes. __________ No. ____ ~~~-----
16. Does the plan include a window schedule or other verification that egress/rescue windows from
sleeping rooms and/or basements comply with the requirements ofthe IRC?
Yes ~
17. Does the plan include a window schedule or other verification that windows provide natural light and
ventilation for all habitable rooms?
Yes ..._......--
18. Do the plans indicate the location of glazing subject to human impact such as glass doors, glazing
immediately adjacent to such doors; glazing adjacent to any surface normally used as a walking
surface; sliding glass doors; fixed glass panels; shower doors and tub enclosures and specify safety
glazing for these areas?
Yes ~ No ____________ _
19. Is the location of all natural and liquid petroleum gas furnaces, boilers and water heaters indicated on
the plan?
Yes ~
20. Do you understand that if you are building on a parcel ofland created by the exemption process or the
subdivision process, are building plans in compliance with all plat notes and/or covenants?
Yes ........-----
21. Do you understand that if you belong to a Homeowners Association (HOA), it is your responsibility to
obtain written permission from the association, if required by that association, prior to submitting
an application for a building permit? The building permit application will be accepted without
it, but you run the risk of the HOA bringing action to enforce the covenants, which can result in
revocation of permit issued. Additionally, your Plan Review fee is not refundable if the plans
have been reviewed by the Building Department prior to any action by the HOA that requires either
revocation or substantial modification of the plans. \
1
~ 1/-""" o-
Yes ll//l ~"b-·
22. Will this be the only residential structure on the ~
Yes No ~ ~~~~~xplain: ___________ _
23. Have two (2) complete sets of construction drawings been submitted with the application?
Yes 1/
24. Do you understand that the minimum dimension a home can be on a lot is 20ft. wide and 20ft. long?
Yes. ____ """-----
4
25. Have you designed or had this plan designed while considering building and other construction code
requirements?
Yes ~
26. Do your plans comply with all zoning rules and regulations in the County related to your properties
zone district?
Yes __ -'-"""-----
27. Does the plan accurately indicate what you intend to construct and what will receive a final inspection
by the Gar~unty Building Department?
Yes ____ _
28. Do you understand that approval for design and/or construction changes are required prior to the
application of these changes?
Yes ~
29. Do you understand that the Building Department will collect a "Plan Review" fee from you at the
time of application submittal and that you will be required to pay the "Permit Fee" as well as any
"Road Impact~r "Septic System" fees required, at the time you pick up your building permit?
Yes_--'....,.....-'----
30. Are you aware that you must call in for au inspection by 3:30 the business day before the
requested inspection in order to receive it the following business day? Inspections will be
made from 7:30a.m. to 3:30p.m. Monday through Friday. Inspections are to be called in
to 384-5003._.......
Yes .....,...-Noc _____ _
31. Are you aware that requesting inspections on work that is not ready or not accessible will result in a
$50.00 re-inspes9~m fee?
Yesc __ _..{L<O_ ___ _
32. Are you aware that you are required to call for all inspections required under the IRC including
approval on a final inspection prior to receiving a Certificate of Occupancy and occupancy of the
building?
Yes ~
33. Are you aware that the Permit Application must be signed by the Owner or a written authority being
given for an A~nt and that the party responsible for the project must comply with the IRC?
Yes __ .:::v ___ _
5
34. Do you understand that you will be required to hire a State of Colorado Licensed Electrician and
Plumber to perform installations and hookups, unless you as the homeowner are performing the
work? The license number of the person performing the work will be required at time of
applicable inspection.
Yes ·~
35. Are you aware, that on the front of the Building Permit Application you will need to fill in the
Parcel/Schedule Number for the lot you are applying for this permit on prior to submittal of a
building permit aJlPlication? Your attention in this is appreciated.
Yes ._...........-------=-----
36. Do you know that the local fire district may require you to submit plans for their review of fire safety
issues?
Yes ~ (please check with the building department about this requirement)
37. Do you understand that if you are planning on doing any excavating or grading to the property prior
to issuance of a building permit that you will be required to obtain a grading permit?
Yes ~
38. Are you aware that if you will be connecting to a public water and/or sewer system, that the tap fees
have to be paid and the connections inspected by the service provider prior to the issuance of a
Certificate of Occupancy?
Yes /114
I hereby acknowledge that I have read, nnderstand and answered these questions to the best of
my ability.
Phone: fly. 'Z 1'3, 9t/.Hl (days);
Project Name: hjf ,KfiY/11-t! L
Project Address: '-(t/PtJ f.< J.Ra
6
Date
---9~112.,__· :h,.,'P.._."-2-' /~'/_Jc..cP __ ( evenings)
Notes:
If any required information is missing delays in issuing the permit are to be expected. Work may not
proceed without the issuance of a permit. If it is determined by the Building Official that additional
information is necessary to review the application and plans to determine minimum compliance with the
adopted codes, the application may be placed behind more recent applications for building permits in the
review process and not reviewed until required information has been provided and the application rotates
again to first position for review, delay in issuance of the permit or delay in proceeding with
construction.
BpminreqDec2007
7
BUI DING
GARFIELD COUNTY, COLORADO
~NSPEClfiOI\i U\fn! .. L NOT BE ftt1AO!:: U£\lltE5S
THiS CP•IRO !S 9l'OSTED ON TIHIE JOB
Date Issued _ _,_1_-0-=-t0____,9,____ __ Permit No.fl!lr J..OQ-no'-=-~--
AGREEMENT
In consideration of the issuance of the permit, the applicant hereby agrees to comply with all laws and regulations
related to the zoning, location; construction and erection of the proposed structured for which this permit is
granted, and further agrees that if the above said regulations are not fully complied with in the zoning, location,
erection and construction of the above described structure, the permit may then be revoked by ilotice from the
County Building department and IMMEDIATELY BECOME NULL AND VOID.
Use___q r"'na
AddressorLegaiDescription~OO {!,~4)0 q l)e8f.'~lf
owneritlO fwaJtpr~ . contractor _PfiD 1)1016 001\df~
Building Permit Type ~'-"M_,_,_,f.._U"""'"''"'Q..,l., ____________________ _
This Card Must Be Posted So It Is Plainly Visible From The Street Until Final Inspection
INSPECTION RECORD
Footing Driveway
I~<£
Foundation I Grouting lnsulation/Jf?-/3-D'J 0 w
Jl/) I-e-f)1 N111 --r~
Underground Plumbing Drywall {)wl :J-/o-6<( ;(}nL t/-!"6-0q
;:;c .
Rough Plumbing A'; Electric r.o~.,;; s'"'Z fa/ Llj 0
/1-j,J-ty:}J)m ~ tK G ;o [Pclo<to Fino I) fl! 1f" · / ///~
Rough Mechanical Septic Final "'/
I;~ 1:3-o? /JrJ1 k~K ~.&!~cPA tt/u-o?f
Gas Piping FINAL 1/)'/'5
!o-t&.-oq ~ /l--J..!fr-O'J ;{)11{
Elec'?ll£~ (by State Inspector) {You Must Cal! For Fina\1nspection)
(PriortoFam\ g) 1 Notes
Framing 11-::~o-~"'/ ft/1'1~3 !15
Cj-fy D 1 IYr1\ -JA12if:. _f!Ah,
{to include Roof in place & Windows & Doors installed &rireSYJPping in place} -f-C(j/(;lf5-?;"Ci!-;;J 0 (,., THIS PERMIT!$ NOTTRANSFERABLE
For lnspedion Call 970-384-5003 Ofiice 970-945-8212
108 8th Street, Suite 401 Glenwood Springs, Colorado 81601
DONOTDESTR
(DO NOT LAMINATE)
'
DATE t -!f-?J 'f 32-61-1110
I I
i
$ -.16 !
13 0-' ~~ I.
~ D._,_
DOLLARS L!J =""'""'-
!
Cathi Edinger
From: Fred Jarman
Sent: Wednesday, July 01, 2009 9:46AM
To: Ken Smith
Cc: Cathi Edinger, Jena Thompson; Julie Taylor; Andy Schwaller
Subject: RE: Check in on status of High lonesome Ranch dog kennel building permits-
Go ahead and issue the Building Permit. 1 am finalizing the Land Use Change Permit so they are good to go.
Thanks-
Fred
From: Ken Smith
Sent: Wednesday, July 01, 2009 9:40AM
To: Fred Jarman; Andy Schwaller
Subject: RE: Check In on status of High Lonesome Ranch dog kennel building permits --
Fred,
Page 1 of 1
The building permit review was completed on 6!25 but evidently there was a problem with the Parcel Number which has since been resolved. Referring to Cathi's notes on the Excel Spread Sheet, it
appears the SUP still has not been issued, therefore a building pem1it has not been issued.
Koo
From: Fred Jarman
Sent: Wednesday, July 01, 2:009 9:31AM
To: Andy Schwaller; Ken Smith
Subject FW: Check In on status of High lonesome Ranch dog kennel building permits-·
Fe!las-
Just wondering on what's happening with the building permits for the kennel. Any help Is appreciated.
From: Dolan, Jeff [mallto:jjdolan@hhlaw.com]
Sent: Tuesday, June 30, 2009 4:34PM
To: Fred Jarman
Subject: Check !non status of High lonesome Ranch dog kennel building permits --
Hello Fred!
Sorry to have to check back in with you, but we'd heard from our High lonesome Ranch client that they still hadn't gotten the building permits needed to begin construction of the dog kennel approved
by the BOCC on June 8th. We'd thought we'd given your office everything it needed to get those issued. Can you either respond or call me with a status update so we understand what the hang up
is?
Thanks In advance, Fred-· as always, we will appreciate your assistance on this !at est hurdle,
Best,
J•ff
303.454.2484
From: Fred Jarman [mallto:fredjarman@gatfle!d-county.com]
Sent: Monday, June 08, 2009 7:43AM
To: Dolan, Jeff
Subject: RE: written opinion regarding no presence of protected/historical resources on Kennel property
Thanks very much Jeff. Good work on a!! of this. I'll see you on Monday at 1:OOPM.
Regards-
Fred
From: Dolan, Jeff [mailto:jjdolan@hhlaw.com]
Sent: Friday, June OS, 2009 2:52PM
To: Fred Jarman
Subject: written opinion regarding no presence of protected/hlstorlcal resources on Kennel property
Fred· .
In sa!lsfaction of condition #15 (p. 21) of your report, please find attached a written report from Metcalf Archaeological Consultants confirming that there are no historical resources on the
property where the kennel is going in. let me {or Metcalf) know if you have any questions. {Also, we are compiling answers to the other open items too, and at a minimum. wil! have most of
them ready lor you before the hearing even starts on Monday).
Thanks, see you Monday.
sest,
J•ff
From: Fred Jarman [mallto:fredjarman@gatfleld-county.com)
Sent: Wednesday, June 03, 2009 4:43PM
To: Dolan, Jeff
Subject: Kennel Engineering Comments
Jeff,
Here are the County project Engineer's comments that you will want to forward to your engineer.
Thanks·
Fred
"EMF <HHLAW.COM>" made the follo.,dng annotations.
This electronic message tr<'lnsmission contains info:tmation !:tom this law firm which may be confidential or privileged. The information is inten<
copying, distribution or use of the contents of this information is ·prohibited.
U' you have received this electronic transmission in error, please notify us by telephone (+1-202-637-5600) or by electronic mail (PostMast•n@l
7/1/2009
1111 Wt. ~:I'W.A'1L'A~r~·~ N\111'li'r:!IW'It'~r¥1,~1RU~ 'IIIII
Receptlon#: 771782
07/21/20e9 09:25:50 AM Jean Alberico
1 of 1 Rec Fee:$0.0C!:i Doc Fee:0.012l GARFiELD COUNTY CO
LAND USE CHANGE PERMIT
for
A 40-ACRE PARCEL OF LAND OWNED BY #10 ENTERPRISES (AKA HIGH
LONESOME RANCH) LOCATED 4.6 MILES WEST OF THE INTERSECTION OF
COUNTY ROADS 200 AND 2041N THE SW ~ NE ~OF SECTION 9, TOWNSHIP
8 SOUTH, RANGE 98 WEST OF THE 6TH PM, GARFIELD COUNTY LEGALLY
DESCRIBED ON A WARRANTY DEED RECORDED IN BOOK 2125PAGE 6681N
THE MESA COUNTY CLERK AND RECORDER'S OFFICE
PARCEL NO# 2443-101-00-009
In accordance with and pursuant to the provisions of the Garfield County Unified
land Use Resolution of 2008, as amended, and Resolution No. 2009 -39 of the
Board of County Commissioners of Garfield County, State of Colorado, hereby
authorizes, by land Use Change Permit, the following activity:
uKenner (LIRA2909)
The land Use Change Permit is issued subject to the conditions set forth in the
above-mentioned resolution, and shall be valid only during compliance with such
conditions and other applicable provisions of the Garfield County Unified land Use
Resolution of 2008, as amended, Building Code, and other regulations of the Board
of County Commissioners of Garfield County, Colorado.
ATTEST: BOARD OF
GARFIELD
STATE OF COLORADO )
)ss
County of Garfield )
At a regular meeting of the Board of County Commissioners for Garfield County,
Colorado, held in the Commissioners' Meeting Room, Garfield County Courthouse, in Glenwood
Springs on, Monday, the 8th day of June A.D. 2009, there were present:
John Martin , Commissioner Chairman
,_M""ik,e,_S""arn""'-'s"'o""n'--------'------• Commissioner
;.Tr'""e"'sr'-'· 1'-':I,_o u,p"'t-'('-"a""bs"'e=n,.,_,t) _________ , Commissioner
""D"'eb,o""'r-"'ah"-'"Q"'u,inn-"-'------------• Assistant County Attorney
,_,J e"'an"'-'-A""l,.be"'n_,· c~o'---------------' Clerk of the Board
=Ed~G,r"'ee"'n"-("'a"'b""se"'n""tl,__ _________ , County Manager
when the following proceedings, among others were had and done, to-wit:
RESOLUTION NO. 2009-39
A RESOLUTION CONCERNED WITH THE APPROVAL OF A LAND USE CHANGE
PERMIT FOR A KENNEL ON A PARCEL OF LAND OWNED BY #10 ENTERPRISES
(AKA HIGH LONESOME RANCH) LOCATED 4.6 MILES WEST OF THE
INTERSECTION OF COUNTY ROADS 200 AND 204 IN THE SW '!. NE 1/. OF
SECTION 9, TOWNSHIP 8 SOUTH, RANGE 98 WEST OF THE 6TH PM, GARFIELD
COUNTY
PARCEL NO# 2443-101-00-009
Recitals
A. The Board of Cotmty Commissioners of Garfield County, Colorado, received an
application for a Land Use Change Permit to allow for the construction and operation of a
"Kennel" to house hunting dogs on a 40-acre tract of land that is part of the larger 13,000-acre
ranch known as the High Lonesome Ranch, located on CR 200.
B. The 40-acre tract is located approximately 4.6 miles west of the intersection of County
Roads 200 and 204 in the SW V. NE V. of Section 9, Township 8 South, Range 98 West of the
6th PM, Garfield County.
C. The subject property is contained within the Resource Lands: Gentle Slopes I Lower
VaJ!ey Floor zone district and a Land Use Change Permit for a Kennel requires a Limited Impact
Review Process by Garfield County.
1
IIIII W• ~:J'WIM•.'/Vfilrl& 1\l'lll'iil'!wh'lrill'!+llr,\.PJ.~"l till ill
Receplion#: 769617
06{16/2009 11:37:13 Al'\ Je;;~n Alberico •
2 of 5 Reo F~e:$0,00 Doc FCe:0.00 GARFIELD COUNTY CO
D. The Board is authorized to approve, deny or approve with conditions a Land Use
Change Permit for a Kennel pursuant to Section 1-301 and 4-105 of the Garfield County Unified
Land Use Resolution of2008, as amended.
E. The Board of County Commissioners opened a public hearing on the gth day of June,
2009 upon the question of whether the Land Use Change Permit application for a Kennel should
be granted or denied, during which hearing the public and interested persons were given the
opportunity to express their opinions regarding the application.
F. The Board of County. Commissioners closed the public hearing on the gth day of June,
2009 to make a fmal decision.
H. The Board on the basis of substantial competent evidence produced. at the
aforementioned hearing, has made the following determinations of fact:
1. Proper posting and public notice were provided as required for the public hearing
before the Board of County Commissioners.
2. The public hearing before the Board of County Commissioners was extensive and
complete, that all pertinent facts, matters and issues were submitted and that all
interested parties were heard at that hearing.
3. The above stated and other reasons, the proposed Land Use Change Permit for a
Kennel has been determined to be in the best interest of the health, safety, morals,
convenience, order, prosperity and welfare of the citizens of Garfield County.
4. The application has met the requirements for a Limited Impact Review (Article IV)
and associated applicable Standards (Article VII) of the Garfield County Unified
Land Use Resolution of 2008, as amended.
RESOLUTION
NOW THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Garfield
County, Colorado, that:
A. The forgoing Recitals are incorporated by this reference as part of the resolution.
B. The Land Use Change Permit to allow for the construction and operation of a Kennel on
a 40-acre tract of land that is part of the larger 13,000-acre ranch known as the High
Lonesome Ranch, located on CR 200 is hereby approved subject to compliance with the
f()llowing conditions:
2
1. That all representations made by the Applicant in the application, and at the public hearing
before the Board of County Commissioners, shall be conditions of approval, w1less
specifically altered by the Board of County Commissioners.
2. All lighting associated with the property shall be directed inward and downward. towards the
interior of the property.
3. The Applicant shall provide a Revegetation I Reclamation Plan to the Building & Planning
Department that addresses the following points prior to issuance of a Land Use Change
Permit:
a. Areas disturbed during.development shall be restored as natural-appearing landforms that
blend in with adjacent undisturbed slopes.
b. Contouring and Revegetation. Abrupt angular transitions and linear placement on visible
slopes shall be avoided. Areas disturbed by grading shall be contoured so they can be re-
vegetated, and shall be planted and shall have vegetation established and growing based
on 70% coverage as compared with the original on-site vegetation within two (2)
growing seasons, using species with a diversity of native and/or desirable non-native
vegetation capable of supporting the post-disturbance land use.
c. Revegetation of Disturbed Areas. To the maximum extent feasible, disturbed areas shall
be revegetated to a desired plant community with composition of weed-free species and
plant cover typical to that site.
d. Application of Top SoiL Top soil shall be stockpiled and placed on disturbed areas.
e. Retaining Walls. Retaining walls made of wood, stone, vegetation or other materials that
blend with the natural landscape shall be used to reduce the steepness of cut slopes and to
provide planting pockets conducive to revegetation.
f. Slash AroW1d Homes. To avoid insects, diseases and wildfire hazards all vegetative
residue, slushiness, branches, limbs, stumps, roots, or other such flammable lot-clearing .
debris shall be removed from all areas of the lot in which such materials are generated or
deposited, prior to final building inspection approvaL
g. Removal of Debris. Within six months of substantial completion of soil disturbance all
brush, stumps and other debris shall be removed from the site.
h. Time Line Plan. Every area disturbed shall have a time line approved for the reclamation
oftbe site approved by the County and a security shall be provided to Garfield County in
an amount of $2,500 per disturbed acre to be reclaimed prior to the issuance of a Land
Use Change Permit
3
IIIII ~'!'''.!. ¥:1/IIrJ,If,:*.'JI*h I!WI.V1!,1l:~k~~~~~lrH'II'IU"~ IIIII
Recepf:.iontt: 769.617 .
06/16/2009 11:37:13 ~M Jean RlberlCO
4 of 5 Rec Fee:$0,00 Doc Fee:0.00 GARFIELD COUNTY CO
4. Prior to the issuance of a Land Use Change Permit, the Applicant shall obtain a lei"ter from
the Debeque Fire Protection District that indicates the District can and will serve the property
and that there is an adequate water supply for fire protection at the site or recommend
improvements to meet that requirement.
5. That based otl the water quality testing results, the proposed water system shall be modified
with a water treatment component to include manganese removal and softening for all water
pumped from the well plus reverse osmosis treatment for all water used as potable water for
humans as recommended by Resource Engineering.
6. Prior to the issuance of a Land Use Change Permit, the Applicant shall provide the County
Building and Planning Department with a copy of all the required permits required by the
State of Colorado Department of Agriculture.
7. This kennel shall be completely enclosed with a building that prevents any sounds from
emanating from the property boundary in excess of the Residential Zone District standards
contained in CRS § 25-12-103, with the exception of CRS § 25-12-103 (2) & (3), that no
noise in excess of 55 db(A) from sunrise to sunset and 50 db( A) from sunset to sunrise will
be allowed. Sunrise and sunset shall be based on the official time determined by the Old
Farmers Almanac charts of sunrise and sunset for the location of the kennel. A kennel may
have dogs outdoors if the noise from the kennel does not exceed the noise standards cite
previously and complies with other Garfield County regulations as provided.
8. Prior to the issuance of a Land Use Change Permit, the Applicant shall provide an engineered
ISDS system to the County to review that meets the following standard:
"Individual sewage disposal system shall be capable of handling all feces and urine waste
from the kennel, or the feces and urine waste shall be stored in a sealed container capable
of being pumped for disposal by a commercial hauler to dispose of the feces and urine
waste at ru1 approved solid waste disposal site."
9. Special events that aliract more than twenty-five (25) participants shall be prohibited on-site.
10. Animal and food wastes, bedding, debris and other organic wastes shall be disposed of so
that vermin infestation, odors, disease hazards and nuisances are minimized. Such wastes
shall be removed at least weekly, or more frequently, from the facility and hauled by a
commercial hauler to an approved solid waste disposal site.
1 1. Prior to the issuance of a Land Use Change Permit, the Applicant shall provide the Building
and Planning Department with an engineered water system design that meets the required
standards in Section 7-105 and 7-106 of the ULUR.
4
12. The County shall not issue a building pennit for the kennel facility until and unless all of
these conditions have been met with the understanding that the Applicant cannot obtain the
State of Colorado Department of Agriculture pennit until the structure is constructed.
Therefore, the County will not issue the Land Use Change Pennit until the Applicant
provides the Building & Planning Department with the appropriate permits from the State of
Colorado Department of Agriculture.
13. The Applicant shall provide an opinion to the County Building and Planning Department
from the Colorado Division of Wildlife or a qualified wildlife biologist that the proposed
facility will not result in an adverse impact to wildlife I migration routes prior to the issuance
of a Land use Change Permit.
14. The Applicant shall provide documentation to the Building and Planning Department to
satisfy the following questions raised by the County staff Engineer prior to the issuance of a
Land Use Change Pennit regarding the water system and waste-water system:
a. Storage Tank Volume: The last plan sheet gives the sizes of the two water storage
tanks. Tank #I that serves the duplex is 4700 gallons (10' diameter and 8' tall).
Tank #2 that serves the kennels is 6, 770 gallons (12' diameter and 8' tall).
b. Duplicate Water Lines: 1 see no reason why they have two diffirent water systems for
the kennel and duplex. Some State requirement? Why have two sets of pump
controls and double the length of pipe?
c. ISD:O!Water Line Separation: The water lines are too close to the drain field.
According to the ISDS regulations, a 25' separation is needed
d. Pipe Route on Hillside: I also disagree with running the water lines straight up the
hillside.· The propose PVC pipe needs to be buried to prevent freezing. I think that.
it would. be a lot easier (and much less visually impacting) to bury the pipe on the
tank access road.
e. Solid Waste: Presumably they will be manually removing the solid waste and sending
it to the landfill.
f Recycle Water Storage Tank: The submitted plans don't provide adequate detail to
know how the system works. If they are going to recycle the treated wastewater, they
need some sort of storage tank to hold the effluent until it's needed
g. Sludge: The treatment system will produce a sludge. What do they plan to do with
the sludge? Send it to the septic tank?
5
h. Treatment System Drain. The treatment schematic shows an ari·ow from the treatment
system to the drain. What is this flow? Where does this drain go? To the septic
tank?
Dated this /5"' day of ~ ,A.D. 2009 .
ATTEST: GARFIELD COUNTY
COMMISSIONERS,
COUNTY, COLORADO
BOARD OF
GARFIELD
Upon motion duly made and seconded the fo as adopted y the
following vote:
COMMISSIONER CHAIR JOHN F. MARTIN e
~C~OM~M~I~SS~I~O~N~ER~M~I~K~E~S~A~M~S~O~N~--------------------''Aye
f:OMMISSIONER TRESI HOUPT (ABSENT) , ABSENT
STATE OF COLORADO )
)ss
County of Garfield )
I, , County Clerk and ex-officio Clerk of the Board of
County Commissioners, in and for the County and State aforesaid, do hereby certify that the
armexed and foregoing Resolution is truly copied from the Records of the Proceeding of the
Board of County Commissioners for said Garfield County, now in my office.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of said
County, at Glenwood Springs, this __ day of , A.D. 20 __ .
County Clerk and ex-officio Clerk of the Board of County Commissioners
6
288(.7~
' -------9
1
I : , iio
---------~ ---:--1-' -----
Ooo o!
2(.4# 22(.4# 8(.7# ; 4(.: #I
.,.
' \. __ J
I J-11 !M'OFTPNF!EPH!LFOOFM"
BE KITI.N FOU!LP !N FDI I!CI\.E H !liP DBUP 0
Qrh!Obn f;
teDL TPO!' !SZBO!BSDI JJFDUT
3481!SJ)F!CPVM'VIBSE-!I PV1UPO-!UFYBT!88116
8(.3!4(1)#
1 ' I ______ _
( 1#.y!8(. 1 #
ES!' GSN
' DM'B<ro
TS\/ID! ~ T.DL ' 00 ---r-,-
DPOU!USFODI !ESB.D 1
I I , 4(. 1#.y!8( 1#
GS!-__ , __ ---1-NUME§!' GSN
YUOHTI S
ES>x o!Cz; SF;!12(J33
HIIU
Tdbrti;
2(1;#>2(. 1#
Tl.2 Ebtf;
180!601:
JACKSON & RYAN ARCHITECTS
28 July 2009
Mr. Dick Gilbert
Mountain Estate Builders
0137 Main Street, Suite 0-203
Edwards, Colorado 81632
970-926-4780
dick@mountainestatebuilders.com
Re: High Lonesome Kennel
De Beque, Colorado
plumbing fixture modifications
Mr. Gilbert,
RECEIVE])
JUL 2 9 2009
GARFIELD COUNTY
BUILDING & PLANNING
Please utilize this letter as a Supplemental instruction to modify the following plumbing fixture items
proposed in the 08 June 2009 High Lonesome Kennel Permit set:
1
Remove the originally proposed wall-mounted hand sink located between the (2) dog grooming stations
along the Grooming Vestibule's south wall.
2
Because the occupancy load for the building is low, anticipated use of a public water fountain is negligi-
ble. As an acceptable alternate to the code's requirement that the project include a water fountain, the
Owner shall provide free, readily available, bottled water in lieu of the originally proposed wall mounted
water fountain.
Regards,
Christopher Craig, AlA
Associate Principal
CDC/cdc
copy:
Mr. Ken Smith
Garfield County Building and Planning Department
108 8th Street, Suite 401
Glenwood Springs, Colorado 81601
970-945-8212
ksmith@garfield-county.com
2370 Rice Blvd, Suite 210 Houston, Texas 77005 713-526-5436 fax 713-526-4241
1229 North 23'" Street, Suite 201 • Grand Junction, Col.orado 81501
(970) 241-6027 • Fax: (970) 256-7992
www .. rhlnoengineers.com ~email: reinc23@qwest.net
September 22, 2009
Garfield County Building and Planning Department
I 08 81h Street, Suite 40 I
Glenwood Springs, CO 81601
Re: Individual Sewage Disposal System
Kennels Facility
The High Lonesome Ranch
Garfield CR #200
To Building and Planning Department:
RE(""1E· '· '·'ll.'P .1 · • .i ~ ~-W.~J .~.1
SEP 2 § 2009
GARFIELD COUNTY
BUILDING & Plf.i,NNING
The purpose of this letter is for final approval of the individual sewage disposal system for the kennels
facility, located at The High Lonesome Ranch, accessed via Garfield County Road #200, north of
Debeque, Colorado. The site is located about 2 miles east of The High Lonesome Ranch Headquarters.
The design included a seepage bed design with 4 feet of imported soil materiaL
Final inspection of the system was conducted on August 19,2009. The system was constructed and
installed in accordance with the specifications and drawings of Rhino Engineering, Inc. 's ISDS design,
the permit, and current ISDS regulations. The ISDS accepts wastewater from the food preparation area,
staff employees, visiting clients, and dog grooming. Wastes from the kennels are not part of the ISDS
system.
The as-built drawing for the ISDS system is attached, showing the dimensions to the septic tank and
distribution box from the northeast and sontheast corners of the duplex building.
If you have any questions, please call me at 970-241-6027.
Sincerely,
RHINO ENGINEERING, INC.
By: John E. Kornfeld, P.E.
Project Engineer
Enclosures
xc: Collin Kenny, Project Manager for The High Lonesome Ranch
John No lop, Mountain Estates Builders
File: Wastewater Design/Duplex Unit The High Lonesome Ranch
FINAL INSPECTION DATE: 8-19-09
AS-BUILT DRAWING DATE: 9-22-09
ABSORPTION FIELD
2 LATERALS OF PERC PIPE
DISTRIBUTION BOX
2500 GAL SEPTIC TANK \
<0 g
CLEANOUT
MAINTENANCE BUILDING
DOG KENNELS
SCALE: 1" 40'
AS-BUILT SEWAGE DISPOSAL SYSTEM
!SDS SITE LAYOUT
HIGH LONESOME DUPLEX
THE HIGH LONESOME RANCH
KENNELS
GARFIELD COUNTY
RHINO ENGINEERING, INC.
1229 N. 23rd STREET SUITE 201
GRAND JUNCTION, CO 81501
SHEET
/,
West Slope Testing & Inspection LLC
3177 Glendam Dr.
Grand Junction, CO 81504
Phone:970-434-6988
Cell: 970-260-2844
Date: 9-4-09
Inspection Report
Client: Buckhorn Geotech (job #2009-019)
Project: Dog Kennel Mechanical Building
Address: 4400 County Rd. 200 De Beque, CO
Building Permit No.: BLCO-7-09-1102
General Contractor: Mountain States Builders
Inspection of shop fabrication or field work at job site: Field
Report#1
Page 1 of 1
Report: Visually inspected the high strength bolting at the main frame & end wall
frame column & rafter connections. Also randomly tested some of the high
strength bolts for proper tightness at the main frame column & rafter connections.
Verified that the cable & flange bracing was installed.
The high strength bolting inspected as outlined above appeared to be in
conformance with the plans for bolt size & grade, and the A325 high strength bolts
appeared to be sufficiently tightened.
Note the main building will need to be inspected at a later date before a final
report can be issued.
Inspector/Technician: Douglas E Young
RECEIV~~D
SEP 21zoog
GARFIEL ·
BUILDING f PCLAOUNTy
NNING
GEOTE~
Mr. John Nolop
Mountain Estate Builders
0137 Main Street, Suite 0-203
Edwards, Colorado 81632
Civil, Structural & Geotechnical Engineers
October 7, 2009
Re: High Lonesome Ranch Dog Kennel Building, 4400 County Road 200, DeBeque, Colorado
Project# 2009-019-STR
Dear John:
Attached are the Inspection Rep01ts (Report #1 and Report #2) from our sub-contractor, West
Slope Testing & Inspection LLC, of the structural bolts, bracing, and welding of the rigid frame
building for the above referenced project on the High Lonesome Ranch.
The reports are dated September 4 and 24, 2009. These reports reflect that the building has
met the manufacturer's specifications for proper assembly.
Please contact me if you have any questions.
Yours truly,
m~+r--
William M. Ungerer, PE'
·---~--
Huddleston-Berry
Engineering & Testing, LLC
Mountain Estate Builders
0137 Main St. 0-203
Edwards, CO 81632
Attention Mr. Jolm Noloy and/or Mr. Jason Frey
Subject: Construction Materials Testing and Inspections
Dog Kennel
High Lonesome Ranch, Colorado
Dear Mr. Noloy and/or Mr. Frey,
640 White Avenue
Grand Junction, CO 81501
Phone:970-255-8005
Fax:970-255-6818
HuddlestonBerry@bresnan.net
September 4, 2009
Project No. 00881-0002
As requested, a representative of Huddleston-Berry Engineering and Testing, LLC (HBET)
observed and tested the soil compaction, observed the placement of reinforcing steel.
Periodic inspections and testing for the Dog Kennel located at High Lonesome Ranch on the
soils and reinforcing steel are complete and meet applicable building code. Any exceptions have
been corrected.
HBET appreciates the opportunity to offer services to your project. If you have any questions
please call. (970) 255-8005.
Respectfully Submitted:
~Engineering and Testing, LLC
Jesse Lueras
Project Manager
Corporate Office
18933 Aldine Westfield
Houston, Texas 77073
Tel (281} 443-9065
Fax (281) 443-9064
Toll Free (888) 467-4443
May29,2009
Maves Construction Inc.
1168 E. Via Le Paz
Fruita, CO. 81521
Attn: Mr. Mike Maves
Subject: High Lonesome R!lllch Kellllels
RBS Job Number 28905
Dear Mr Maves,
Western Sales Office
10 Inverness Drive East, Suite 220
Englewood, CO 80112
Tel (303) 799-4579
Fax (303) 799-4803
Toll Free (800) 658-2885
This letter is in regards to the location of the wall bracing along line A. The wall bracing can be
relocated from bay 7-8 to bay 6-7. The structural integrity of the building will be maintained as long
as the wall bracing will be installed per the supplied details at the new braced bay location.
If you have any questions, feel free to give me a call to discuss.
Yours truly,
WEST SLOPE TESTING & INSPECTION LLC
3177 Glendam Dr
Grand Junction, CO 81504
Phone: 970-434-6988
Cell: 970-260-2844
9-29-09
Garfield County Building Inspection Dept.
108 8th St., Suite 40 I
Glenwood Springs, CO 81601
Page 1 of 1
Please find enclosed special inspection report for Dog Kennel building.
Thank You; Doug Young
West Slope Testing & Inspection LLC
3177 Glendam Dr.
Grand Junction, CO 81504
Phone:970-434-6988
Cell: 970-260-2844
Final Inspection Report
Date: 9-24-09
Client: Buckhorn Geotech (job #2009-019)
Project: Dog Kennel Main Building
Address: 4400 County Rd. 200 De Beque, CO
Building Permit No.: BLC0-7 -09-1102
General Contractor: Mountain States Builders
Inspection of shop fabrication or field work at job site: Field
Report#2
Page 1 of 1
Report: Visually inspected the high strength bolting at the main frame & end wall
frame. column & rafter connections. Bolts were match marked & tightened per the
turn of the nut method, as called out for in the building manufactures plans. Also
visually inspected the welding that was performed on site at the additional column
& rafter reinforcing plates added for increased loading. Verified that the cable &
flange bracing was installed.
The high strength bolting & field welding inspected as outlined above appeared
to be in significant conformance with the plans & details, and appeared to meet the
quality requirements of the A WS D 1.1 Structural Welding Code & the AISC
Specification for Structural Joints Using ASTM A325 or A490 Bolts.
To the best of my knowledge this completes the special inspections of the on site
welding & high strength bolting as outlined in reports # 1 & #2.
Parcel Detail Page 1 of 4
Garfield County Assessor/Treasurer
Parcel Detail Information
Asscssgr/Trcilllurcd'mp_i)J:tX:3c£~rch I b~scssor SubllcLQJ.\ciY I Asll~ssor S"l!~s Searc"h
Cl.crk_&_RcQ..ordcr"R~ccp!iQlLSc_axch
l'm:c_clDct!!il I YJllucD~;;Jail I Salcs".DcJillJ I Resid~ntiaJ/CQillillerciflUmnmYcl11entD~!ail
LandD_ctail I l'hotogmphs I Mili_Lc:yy__ReYenuesJ2~ail
I Tax Area II Account Number II Parcel Number II 2008 Mill Levy I
I o29 II R290151 II 2443o91oooo1 II 32.108 I
Owner Name and Mailing Address
1#10 ENTERPRISES, LLC
!ATTN: ANNETTE FRISBIE
15701 WOODWAY DRIVE, STE 300
!HOUSTON, TX 77057
Assessor's Parcel Description
(Not to be used as a legal description)
!SECT,TWN,RNG:9-8-98 DESC: SEC. 9
IW1/2NE, SENE SEC. 10 SWNW, NESW
IBK:0579 PG:0869 BK:1780 PG:312
IRECPT:694070 BK: 1780 PG:307
IRECPT:694069 BK:0930 PG:0534
IBK:0926 PG:0984 BK:0861 PG:0348
IBK:0858 PG:0317 BK:0839 PG:0343
IBK:0834 PG:0193 BK:0834 PG:0186
IBK:0805 PG:0129 BK:0802 PG:0838
IBK:0801 PG:0765 BK:0800 PG:0340
IBK:0728 PG:0435 BK:0715 PG:0620
IBK:0715 PG:0584
Location
http://www.garcoact.com/assessor/Parcel.asp? AccountNumber=R290 151
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
6/24/2009
Parcel Detail Page 2 of4
I Physical Address: 114400 200 COUNTY RD DEBEQUEI
I Subdivision: I
I Land Acres: I 200
I Land Sq Ft: I 0
I Section II Township II Range I
9 II 8 II 98 I
2009 Property Tax Valuation Information
II Actual Value II Assessed Value I
I Land: II 7,820[1 2,2701
I Im~rovements: II ojj 0
I Total: II 7,82oll 2,2701
Most Recent Sale
Sale Date: )[12/29/1987
Sale Price: 1)1,854,000
Basic Building Characteristics
Number of Residential 0 Buildings:
Number ofComm!lnd 0 Buildings:
No Building Records Found
Tax Information
I Tax Year II Transaction TyEe II Amount I
I 2008 II Tax Payment: Second Half II ($34.36)1
I 2008 II Tax Payment: First Half II ($34.36)1
I 2008 II Tax Amount II $68.721
I 2007 II Tax Payment: Second Half II ($30.90)1
I 2007 II Tax Payment: First Half II ($30.90)1
I 2007 II Tax Amount II $61.801
II II
http:/ /www.garcoact.com/assessor/Parcel.asp? AccountNumber=R290 151 6/24/2009
Parcel Detail
I 2006 II Tax Payment: Second Half II ($28.62)1
I 2006 II Tax Payment: First Half II ($28.62)1
I 2006 II Tax Amount II $57.241
I 2005 II Tax Payment: Second Half II ($36.48)1
I 2005 II Tax Payment: First Half II ($36.48)1
I 2005 II Tax Amount II $72.961
I 2004 II Interest Payment II ($0.41 )I
I 2004 II Interest Charge II $0.411
I 2004 II Tax Payment: Second Half II ($41.21)1
I 2004 II Tax Payment: First Half II ($41.21)1
I 2004 II Tax Amount II $82.421
I 2003 II Tax Payment: Second Half II ($50.37)1
I 2003 II Tax Payment: First Half II ($50.37)1
I 2003 II Tax Amount II $100.741
I 2002 II Tax Payment: Second Half II ($50.56)/
I 2002 II Tax Payment: First Half II ($50.56)1
I 2002 II Tax Amount II $101.121
I 2001 II Tax Payment: Second Half II ($50.13)j
I 2001 II Tax Payment: First Half II ($50.13)1
I 2001 II Tax Amount II $100.261
I 2000 II Tax Payment: Second Half II ($51.56)1
I 2000 II Tax Payment: First Half II ($51.56)1
I 2000 II Tax Amount II $103.121
I 1999 II Tax Payment: Second Half II ($63.88)/
I 1999 II Tax Payment: First Half II ($63.88)/
I 1999 II Tax Amount II $127.761
Mill Leyy_RevenuesJ2etf!il
Top_qfl'l\ge
Asse~~oLRfltf!base_S.e.m:£ll.Qptions. I IreasnreL!la.t.ahase_SeaLGb._Qption~
Clerk ~Res:_ordecD_atfl.\JaseSearLILQp.tions
Page 3 of 4
The Garfield County Assessor and Treasurer's Offices make every effort to collect and maintain
accurate data. However, Good Turns Software and the Garfield County Assessor and Treasurer's Offices
are unable to warrant any of the information herein contained.
http:/ /www.garcoact.com/assessor/Parcel.asp? AccountNumber=R290 151 6/24/2009