HomeMy WebLinkAboutStructural Engineer Report 01.10.2013THUNDER MOUNTAIN TESTING
2970 Ronlin Avenue, Grand Junction, Colorado 81504
Office (970) 256-9965 CeII (970) 210-7008 Fax (970) 314-7067
Encana Oil & Gas
2717 CR 215. Suite 1000
Parachute, CO 81635
ATTN: Mr. Rick Barnett
RE: Encana Story Gulch Compressor Station
Generator Building
8801 Sprague Gulch Road
Rifle, Colorado
Dear Mr. Barnett,
January 10, 2013
Permitf` BLCO-8-I 1-2164
As requested structural steel special inspection was conducted per the IBC 2009 Edition - Ch,p Ter
17: Structural Tests and Special Inspection and Garfield County requirements. I arrived on site at 12:00
PM. I met with you to review project requirements and high strength bolting specifi, - Vons. Thc pre -
manufactured metal building fabricator for this project is Clear Creek Construction in Oklahoma City, OK.
The steel erector for this project is Clear Creek Construction in Oklahoma City, OK. Prin- to my arrival 1
received and reviewed a copy of an engineering clarification report dated 11-30-12 from Mr. Bill Rose P.E.
with Group W Engineering, Inc. in Lakewood, CO. referencing acceptance of the "tack" welds on the crane
rail beams as referenced in my 10-26-12 report. Please refer to the attached report for project
documentation.
Visual re -inspection was conducted at the Roof Framing Plan level on the repairs to the 3'4" &
7/8" ASTM A325 High Strength beam to beam and beam to column bolted connections as referenced in
my 10-26-12 report. Project bolt tension requirements indicate "turn -of -the -nut' method as referenced in
the AISC 9`s Edition: Specification for Structural Joints using A325 or A490 Bolts and also the project
drawings provided Clear Creek Construction: Job No. 60300 dated 7-18-11: Sheet CI of 1, Bolt
Tightening. As a minimum, 10% of all connections, but not less than two bolts per connection were
inspected for proper bole tension requirements and match marking techniqucc. as stated in 113C requirements
for periodic inspection: Table 1704.3. Item 2.b Inspection was conducted at grid line A — D & 1 - 4.
Duri g Inspection I observed 2 column to beam connections to have hand tight bolts and therefore
unacceptable. I informed Mr. Marty Ruggles with Encana on site that re -tensioning of all A325 bolts shall
be conducted prior to re -inspection by Thunder Mountain Testing.
Res. ct j./S but' ed,
r r4
N uxN 1
AWS CW1 #91040201
ICC Certified 80863569-S1 & S2
Thunder Mountain Testing
Scott L Maxwell
CWI 91040201
0C1 EXP 41112015