HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-9-15-3913
Atlantic Aviation Services
Hangar @ GarCo Airport
375 CR 352 Rifle, Colorado
1) PRIOR TO CONSTRUCTION, PROVIDE A COPY OF THE STORMWATER DISCHARGE PERMIT.
2) STRUCTURE IS FULLY SPRINKLERED, TYPE IIB CONSTRUCTION, 5-1 AND B OCCUPANCIES.
3) ALL WORK MUST COMPLY WITH THE 2009 IBC, IMC, IPC, IFGC, IECC, IFC CHAPTER 11,
NFPA 409, AND THE MANUFACTURERS INSTALLATION SPECIFICATIONS.
4) APPROVED FOR THE STORAGE OF TRANSIENT AIRCRAFT ONLY PER NFPA 409.
5) LOCAL FIRE DISTRICT SHALL INSPECT THE FIRE SUPPRESSION SYSTEM, EXTINGUISHERS,
ALARMS, AND OTHER PERTINENT IFC REQUIREMENTS. FIRE DISTRICT FINAL APPROVAL
REPORT I5 REQUIRED FOR CERTIFICATE OF OCCUPANCY.
6) ENGINEER ON RECORD SHALL INSPECT ALL EXTERIOR CONSTRUCTION RELATED TO
INFRASTRUCTURE/CIVIL IMPROVEMENTS. A FINAL APPROVAL REPORT IS REQUIRED FOR
CERTIFICATE OF OCCUPANCY.
7) OPEN -HOLE SOILS REPORT IS REQUIRED AT FOOTING INSPECTION, 2000 PSF.
8) ALL HIGH STRENGTH BOLTING AND FIELD WELDING REQUIRES SPECIAL INSPECTOR.
APPROVAL REPORT I5 REQUIRED AT FRAMING INSPECTION.
9) STORAGE OF HAZARDOUS MATERIALS PER 2009 IBC AND IFC REQUIREMENTS.
10) PROVIDE A UL LISTING FOR A TWO (2) HOUR FIRE BARRIER FOR THE BOILER ROOM AS
REQUIRED PER IBC, SECTION 412.4.4 PRIOR TO FRAME INSPECTION.
11) BOILER INSPECTION BY THE STATE OF COLORADO, JOE BORGERDING, 970-712-7458.
FINAL APPROVAL REPORT REQUIRED FOR CERTIFICATE OF OCCUPANCY.
12) PENETRATIONS OF FIRE RATED ASSEMBLIES PER IBC SECTION 713.
13) ACCESSIBILTY REQUIREMENTS PER 2009 IBC, CHAPTER 11 AND ICC/ANSI A117.1-2003.
14) EGRESS THRU INTERVENING SPACES PER IBC, 1014.2, AN EXIT ACCESS SHALL NOT PASS
THROUGH A ROOM THAT CAN BE LOCKED TO PREVENT EGRESS, SPECIFICALLY AT ALL
BUSINESS OFFICE STORAGE ROOM/HANGER ACCESS DOORS.
15) ELECTRICAL PERMITTING AND INSPECTIONS THROUGH THE COLORADO STATE
ELECTRICAL BOARD. (303-869-3458)
16) VERIFY EXIT DIRECTIONAL SIGNAGE PRIOR TO ELECTRICAL ROUGH -IN INSPECTION,
SPECIFICALLY AT BUSINESS OFFICE/STORAGE ROOMS.
17) ELECTRICAL ROUGH IN APPROVAL 15 REQUIRED PRIOR TO FRAME INSPECTION.
18) ELECTRICAL FINAL APPROVAL IS REQUIRED FOR CERTIFICATE OF OCCUPANCY.
19) IECC, CH. 5 COMPLIANCE REPORT REQUIRED PRIOR TO FINAL MECHANICAL INSPECTION.
20) LOCKS, LATCHES AND LANDINGS PER 2009 IBC, SECTION 1008.
21) LIGHT AND VENTILATION PER 2009 IBC, CHAPTER 12.