HomeMy WebLinkAbout1.05 Landscaping and reclamation plansPart VII Landscaping and Reclamation Plans Landscaping/Post Construction Activities A. Disturbed areas. All disturbed areas will be final graded to as close as possible to its original condition. B. Erosion. Erosion control structures such as water bars or "kicker dikes" will be constructed. Water bars will be placed approximately every 25' on steep slopes to prevent erosion over the right-of-way. Steep slope breaks will also be made impassable to vehicular traffic by using deep waterbars, leaving them rough. C. Weed Control. EnCana shall be responsible for weed control on disturbed areas within the limits of the right-of-way. EnCana will be responsible for consultation with the authorized officer and/or local authorities for acceptable weed control methods (within limits imposed in the grant stipulation). D. Drainages. The banks of drainage crossings will be returned and stabilized to their original slope to avoid ramping and opening them to livestock and vehicle traffic. E. Visuals. Where applicable, the upper rim rock will be replaced to discourage traffic and mitigate visual scarring. F. Painting. All aboveground facilities will be painted with the Carlsbad Canyon 2.5 Y 6/2 color or similar color to blend in with the surrounding area. G. Seeding. EnCana will seed all disturbed areas along the pipeline corridor with the recommended seed mixtures as provided by the BLM, and summarized in the following table: Seed Mixes to be Used in Reclamation of EnCana Pipeline Routes. Drill Seeding Site Type Species Variety Rate' Upland Sites Total Saline Lowlands Total Other Lowlands Western wheatgrass Rosanna 6.0 Thickspike wheatgrass Critana 6.0 Indian ricegrass Nezpar 3.0 Shadscale saltbush2 3.0 Globemallow3 0.5 Western wheatgrass Bottlebrush squirreltail Gardner's saltbush Indian ricegrass Alkali sacaton Nebraska sedge Tufted hairgrass Alkali grass Rosanna 18.5 6.0 3.0 2.0 4.0 15.0 3.0 1.0 2.0 4.0 Total 10.0 Source: BLM (1997a). 1 Drill seeding rate = lbs/acre pure live seed (PLS). 2 Substitution for shadscale saltbush: Gardner's saltbush. 3 Substitution for globemallow: western yarrow or blue flax. Seed shall be planted using a drill equipped with a depth regulator to ensure proper depth of planting where drilling is possible. The seed mixture shall be evenly and uniformly planted over the disturbed area. Where drilling is not possible, seed shall be broadcast and the area shall be raked or chained to cover the seed. When broadcasting the seed, the pounds per acre will be doubled. Steep slopes will not be drill seeded so to avoid establishing rills. The seeding will be repeated until a satisfactory stand is established as determined by the authorized officer. Evaluation of growth will not be made before completion of the first growing season after seeding. The authorized officer will be notified a minimum of 5 days prior to the seeding of the project. Seeding will occur during spring or late fall seasons when ground frost is not present. Reclamation The expected life of the EnCana River Water Pipeline is 30 years. Reclamation will consist of the following: Removal of all surface equipment and appurtenances. - Restoration and re -contouring of grade to approximate original conditions. - Replacement of stockpiled topsoil. Compliance with all prevailing Colorado Oil and Gas Conservation Commission and Garfield County regulations governing final reclamation. - Prior to termination of the right-of-way, EnCana shall contact the authorized Federal officer to arrange a pre -termination conference. This conference will be held to review the termination provision of the grant.