Loading...
HomeMy WebLinkAbout3.0 Staff Report BOCC 12.15.15 - Pipeline• ,Q- E4 4Q I BOCC December 15, 2015 PDPA-08-15-8378 PROJECT INFORMATION AND STAFF COMMENTS REQUEST Special Use Permit APPLICANT Ursa Operating Company LLC PROPERTY OWNER Battlement Mesa Land Investments & Battlement Mesa partners PROJECT SIZE Approximately 13 acres of surface area will be disturbed by the Pipeline Construction reflected by a 50 ft. temporary construction easement and several Temporary Work Areas and Staging Areas. EXISTING ZONING The property is zoned Planned Unit Development (PUD) for the Battlement Mesa PUD Map: This shows the two well pads in blue squares with the pipeline route as the yellow dashed line ® I. GENERAL PROJECT DESCRIPTION Ursa Operating Company (Ursa) is requesting a Special Use Permit for a 2.5 mile steel pipeline (varying from 12" and 16" in width) that will gather natural gas from two proposed well pads (B Pad and D Pad) and transport it to a location just outside Battlement Mesa PUD. In addition to the gas pipeline will be two 8" high density polyethylene water pipelines collocated in the same trench as the natural gas pipeline. The pipelines are to be located in an easement that will be 50 feet wide while the pipeline is installed then reduced to a permanent 25 foot easement once the project is completed. The trench will have a minimum coverage of 48 inches in depth. Generally, the Pipeline will begin at the B Pad located below County Road (CR) 307 and north of the Battlement Mesa RV / Boat Storage area and will be bored underground in a NE direction under CR 307 (River Bluff Road) to the D Pad. From the D Pad, it will continue eastward to the NW corner of Valley View Village and then proceed southward along the west Valley View Village boundary then southeasterly to cross Stone Quarry Road and CR 300 (via bore action), then westerly along CR 302 where it will tie into the Battlement Mesa Metropolitan District water connection on CR 302 (Underwood Lane), then continues westerly to cross CR 308 (via bore action) then heads due south to tie into an existing water and gas line. The purpose of the twin 8 inch water lines is to be able to provide water to the drilling and completions activity on the proposed B and D Pads (proposing 25 and 28 wells respectively) as well as conveying produced water for disposal from the completed pads. The entire pipeline length crosses lands owned and controlled entirely by Battlement Mesa Land Investments and Battlement Mesa Partners. All crossings with County roads are to be bored underneath the roads with a substantial bore from the B Pad to the D Pad. The pipeline construction will take 18 weeks to complete (assuming a 5 day work week) beginning in 2016, if approved. II. REFFERAL AGENCY COMMENTS Public Notice was provided for the public hearing in accordance with the Garfield County Land Use and Development Code as amended and the Garfield County Zoning Resolution of 2008. Notice included publication, mailing and posting. The Applicant has provided evidence of compliance with the notice requirements. Comments from formal referral agencies and County Departments specific to the pipeline are summarized below and attached as Exhibits. Other comments are also attached as Exhibits. 1. Garfield County Consulting Engineer, Chris Hale, Mountain Cross Engineering: a) The Applicant should include fittings or transition necessary to transition from a 12" pipe to a 16" pipe at station 47+00. b) There are two horizontal bends proposed in an area of pipeline that is proposed to be bored beneath Stone Quarry Road, station 59+37 to station 61+87. The Applicant should discuss the feasibility of constructing 459 and 879 bends in borings. c) The Applicant should provide a detail for the proposed valve sets. • 2 d) The typical trench section should be revised to match the Garfield County conditions for pipeline installations. The note on the cover should be revised to reference these conditions also. e) The "Integrated Vegetation and Noxious Weed Management Plan" prepared by West Water Engineering identified locations along the pipeline that had riparian areas and wetlands. The Applicant should identify if any permitting was obtained and/or necessary and the mitigation that was implemented. Specific construction mitigation necessary should be included on the plan sheets. 2. Grand Valley Fire Protection District, Rob Ferguson Deputy Fire Chief: Commented that the District does not have any objections or further requirements for the pipeline special use permit. 3. CDPHE, Ingrid Hewitson, Air Quality Planner, Air Pollution Control Division: Provided general information on the CDPHE permitting requirements. 4. Garfield County Road and Bridge, District 3 Superintendent, Dan Goin: a) Noted that if the bores are not successful they will need to get road cut permits and patch roadways. b) Indicated that the Applicant will be responsible for repairing any damage to roadways or curbs. c) Noted that construction must be done to maintain current drainage and allow for future maintenance ofdrainage. 5. Town of Parachute, Michael Erion Water Engineer/Consultant noted that the project is not located within the Town's Watershed Protection District and had no objections to the project. 6. Garfield County Vegetation Manager, Steve Anthony: a) Indicated that the Noxious Weed Inventory and Management Plan and proposed seed mixes are acceptable. b) Recommends treating all inventoried weeds within the 30 foot survey prior to October 31, 2015. c) Recommended a $32,500 security for re -vegetation (based on 13 acres of disturbance). 7. Garfield County Oil and Gas Liaison: a) Suggests that given the pipeline proximity to residential and other development, appropriate nuisance and safety best management practices (BMPs) should be considered as conditions of approval. 0 3 b) Suggest operator be encouraged to thoughtfully plan the pipeline construction to minimize night-time disturbance to nearby residences and to ensure area residents are well informed about whom they may call at URSA if nuisance issues arise. c) Also encourage thoughtful planning for the location of any pipeline maintenance structures and pressure relief valves such that they do not create a long-term, intermittent nuisance issue for nearby residents. 8. Colorado Parks and Wildlife, Scott Hoyer, District Wildlife Manager, Parachute: Noted that the scope and actions of this project are addressed in the 2010 Wildlife Mitigation Plan (WMP) between CPW and Ursa. 9. Battlement Mesa Oil and Gas Committee, Chuck Hall: Commented in support of the installation indicating that it should reduce truck traffic. III. STAFF COMMENTS AND ANALYSIS — PIPELINE REVIEW CRITERIA The following excerpts are from Article 9, Section 9-104 Review Criteria for Pipeline Land Use Change Permits. 9-104 REVIEW CRITERIA. An application for a pipeline shall be approved, conditionally approved, or denied in accordance Swith the following standards and criteria: A. Located Along Perimeters. As a general guide, rights-of-way and any associated facilities shall be located along the perimeters of surface property ownerships and not within areas of agricultural crop production. Nonperimeter locations will be acceptable if the surface owner agrees and there is no adverse impact on adjacent properties. Response: The pipeline alignment is located primarily along County Road alignments where possible and does not cross any areas with active agricultural crop production. The alignment does run along the west and south perimeter of the Valley View Village neighborhood (a linear distance of approximately 1,300 feet) along the backyard lines of some 22 single-family and multi -family dwelling units. It is estimated to take approximately 3 weeks to construct this portion of the • pipeline. Due to the close proximity 4 • 0 with the homes in Valley View Village, Staff suggests the Operator construct that portion of the pipeline using a more aggressive schedule in order to get beyond these properties more quickly. Consider the comments provided by the County Oil & Gas Liaison: a) Suggests that given the pipeline proximity to residential and other development, appropriate nuisance and safety best management practices (BMPs) should be considered as conditions of approval. b) Suggest operator be encouraged to thoughtfully plan the pipeline construction to minimize night-time disturbance to nearby residences and to ensure area residents are well informed about whom they may call at URSA if nuisance issues arise. c) Also encourage thoughtful planning for the location of any pipeline maintenance structures and pressure relief valves such that they do not create a long-term, intermittent nuisance issue for nearby residents. B. Noise Abatement. 1. Any equipment used in construction or operation of a pipeline must comply with either the COGCC Rules and Regulations in regards to noise abatement or C.R.S. Article 12 of Title 25, as appropriate for the type of pipeline. 2. All power sources used in pipeline operations shall have electric motors or muffled internal combustion engines. Response: Compliance with COGCC rules regarding noise abatement shall be required as a condition of approval. That COGCC Rule is Light Industrial Level measured at the nearest building unit: 802(b)(1) Except as required pursuant to Rule 604.c.(2)A., operations involving pipeline or gas facility installation or maintenance, the use of a drilling rig, completion rig, workover rig, or stimulation is subject to the maximum permissible noise levels for industrial zones. ZONE 7:00 am to next 7:00 7:00 pm to next 7:00 604(c)(2)(A) Noise. Operations involving pipeline or gas facility installation or maintenance, or the use of a drilling rig, are subject to the maximum permissible noise levels for Light Industrial Zones, as measured at the nearest Building Unit. Short-term increases shall be allowable as described in 802.c. Stimulation or re -stimulation operations and Production Facilities are governed by Rule 802. 5 pin am Residential/Agricultural/Rural 55 db(A) 50 db(A) Commercial 60 db(A) 55 db(A) Light industrial 70 db(A) 65 db(A) Industrial 80 db(A) 75 db(A) 604(c)(2)(A) Noise. Operations involving pipeline or gas facility installation or maintenance, or the use of a drilling rig, are subject to the maximum permissible noise levels for Light Industrial Zones, as measured at the nearest Building Unit. Short-term increases shall be allowable as described in 802.c. Stimulation or re -stimulation operations and Production Facilities are governed by Rule 802. 5 . Once the pipeline is completed, it will comply with the Residential / Agricultural / Rural Zone in the COGCC rules. The pipeline does not propose any compressor stations or pump stations along the alignment. A condition should be added to require that any future pumping equipment located along the alignment or within well pads serving the pipeline shall utilize electric motors or muffled internal combustion engines. The Applicant's construction schedule anticipates work Monday— Friday with the option for 7 days a week if necessary. While this schedule raises some concerns regarding impacts on neighboring properties it is mitigated by the limitation of work to daylight hours only. The Planning Commission proposes the following Condition of Approval: The construction of the Pipeline shall be limited to the hours of 7:OOAM to 7:00PM, Monday through Saturday. If inclement weather conditions or field conditions require schedule changes, construction may occur on Sundays to meet construction schedule. Ursa will notify Garfield County and affected residents if Sunday work is necessary. C. Visual Impact. Pipeline operations shall be located in a manner to minimize their visual impact and disturbance of the land surface. Response: The pipeline construction is planned to utilize a maximum of a 50 ft. wide • construction easement. The alignment follows existing disturbed and re -vegetated areas along County Roads, private roads, and existing pipeline corridors. The plans propose three bores under county roads to further minimize impacts. Compliance with the re -vegetation and weed management plans shall be required by conditions of approval. D. Access Points to Public Roads. Access points to public roads shall be reviewed by the County Road and Bridge Department. All access and oversize or overweight vehicle permits must be obtained from the County Road and Bridge Department prior to beginning operation. All proposed transportation rights-of-way to the site shall also be reviewed and approved by the County Road and Bridge Department to minimize traffic hazards and adverse impacts on public roadways. Existing roads shall be used to minimize land disturbance unless traffic safety, visual or noise concerns, or other adverse surface impacts clearly dictate otherwise. Any new roads created as a result of the pipeline construction, intended to be permanent for maintenance and repair operations, shall be placed behind a locked gate or other barriers, preventing use by Recreational Vehicles. Any gates or barriers need to be consistent with the surface owner's preferences. Response: Compliance with Road and Bridge requirements including access permits, bore permits, and Oversize/Overweight permits shall be required. Limited areas of new road construction are proposed for the corridor as the primary access is by existing County Roads and private ranch access roadways. Access and private roadways are addressed in the Surface Use Agreements. Several gates limiting access are currently in place. E. Air Contaminant Emissions. Air contaminant emissions shall be in compliance with the applicable permit and control provisions of the Colorado Air Pollution Prevention and Control Act, C.R.S., Title 25, Article 7. Response: Referral comments from the CDPHE noted general information on CDPHE permitting requirements. The Applicant shall be required to provide evidence of permitting with CDPHE if required and ongoing compliance with any conditions of the permits. Current estimates are for 13 acres of disturbed area. Dust control plans and implementation of re -vegetation plans are anticipated to minimize air quality impacts during construction. F. Water Quality Control Standards. All operations shall comply with all applicable CDPHE Water Quality Control Standards. Response: The proposed pipeline is not located within the Parachute Watershed Protection District and the Applicant has applied for a Town Watershed Permit. Issuance of the permit and compliance with the terms of the permit should be required as a condition of the County approvals. Water used for pressure testing will be properly disposed of pursuant to the Applicant's representations. The Applicant has overall Stormwater Permitting in place with CDPHE. The pipeline construction plans contain Best Management Practices to avoid impacts to water quality during construction. Re -vegetation plans and site reclamation are designed to avoid impacts on water quality. The Application contains a valid Stormwater Management Plan • that contains a variety of BMPs that will be implemented in the construction of the pipeline. The Sensitive Area Survey in the application prepared by WestWater Engineering indicates potential conflicts with wetlands (particularly around the B pad location) and Waters of the US for small drainage crossings along the proposed pipeline route. The report recommended consultation with the US Corps of Engineers to determine in wetlands and Waters of the US are present thereby require any permitting or avoidance action. This is suggested as a condition of approval. G. Reclamation Plan. The proposed Reclamation Plan shall provide for a reasonable reclamation schedule in light of the specific surface use and surrounding land uses, and may require recontouring and revegetation of the surface to pre -disturbance conditions. The Director may also approve a plan for an alternative post -disturbance reclamation, provided the surface owner and the Applicant agree. Response: The Application submittal contains reclamation and re -vegetation plans including details on timing, interim reclamation, use of BMP's to avoid soil erosion, seed mix, final reclamation, minimum vegetative cover, and soil treatment to avoid compaction. Pursuant to referral comments from the Garfield County Vegetation Manager compliance with County • 7 Standards for re -vegetation shall be required along with security for re -vegetation at $32,500. • The terms and conditions of the revegetation plan shall be considered conditions of approval. H. Removal of Abandoned Pipeline. Should an abandoned pipeline be removed, it will be subject to the original revegetation and weed management requirements in the original application. Response: Abandonment of the pipeline would be subject to COGCC Regulations. Should it be removed current re -vegetation plans, standards, and representations along with the provision of appropriate security shall apply. IV. STAFF ANALYSIS — SPECIAL USE PERMIT CRITERIA The Special Use Permit Criteria from the Garfield County Zoning Resolution of 1978 are outlined below. (1) Utilities adequate to provide water and sanitation service based on accepted engineering standards and approved by the Board of County Commissioners shall either be in place or shall be constructed in conjunction with the proposed use. Response: Short term demand for potable water and sanitation facilities during construction will be provided by portable facilities typical for construction projects and in compliance with OSHA requirements. No long term facilities will be required for operation of the pipeline. Battlement Mesa Metropolitan District will provide non -potable water for the pressure testing of the lines as evidenced by their contract. (2) Street improvements adequate to accommodate traffic volume generated by the proposed use and to provide safe, convenient access to the use shall either be in place or shall be constructed in conjunction with the proposed use. Response: The Applicant has provided a traffic assessment that addresses adequacy of access and any impacts on adjacent County Roads. The report includes estimates on traffic generation, timelines for when it will be generated, and types of vehicles. The report concludes that "... the increase traffic during construction of the proposed pipeline is not expected to be significant on roads generally used by the public" and that the pipeline construction traffic does not increase existing volumes to levels required for State or County permits. An excerpt from the Traffic Report showing estimated traffic generation is shown below. 0 8 • Table 3: Construction Traffic Proiections Roadway Bkgd. Traffic Maximum Daily Construction Traffic Percent Increase Total 18 Week Construction Traffic CR 215 720 12 2% 840 CR 30OW 4770 16 <1 % 570 CR 30ON 6840 12 <1 % 420 CR 300E 670 12 2% 420 CR 300 500 20 4% 310 CR 3000 240 20 8% 310 CR 302 120 20 17% 730 CR 303 470 20 4% 310 CR 307 270 16 6% 200 CR 308 360 20 6% 730 The report indicates that most intersections will be adequate while noting a sight distance concern at the County Road 308 and East Valley Road (County Road 300E) intersection. A condition of approval should require coordination with the County Road and Bridge Department regarding any needed sight distance improvements such as vegetation removal that may be required at that location. (3) Design of the proposed use is organized to minimize impact on and from adjacent uses of land through installation of screen fences or landscape materials on the periphery of the lot and by location of intensively utilized areas, access points, lighting and signs in such a manner as to protect established neighborhood character. Response: Mitigation of impacts are addressed in the Application submittals reflecting day light hours for construction, no lighting, noise compliance, and no long term compression or pump stations located on the alignment. Limiting construction to six days a week is recommended by staff with allowance for the applicant to request construction on Sundays subject to approval by the Board of County Commissioners at a public meeting. Due to the temporary nature of the construction impacts no screening is proposed. The use of boring in key sections and the alignment itself minimizes impacts along with a short total construction timeline. Section 5.03 (1) The applicant for a permit for industrial operations shall prepare and submit to the Planning Director two (2) copies of an impact statement on the proposed use prescribing its location, scope, design and construction schedule, including an explanation of its operational characteristics. The impact statement shall show that the use shall be designed and operated in compliance with all applicable laws and regulations of the County, State and Federal Governments, and will not have a significant adverse effect upon: (a) Existing lawful use of water through depletion or pollution of surface run-off, stream flow or ground water; (b) Use of adjacent land through generation of vapor, dust, smoke, noise, glare or vibration, or other emanations; (c) Wildlife and domestic animals through creation of hazardous attractions, alteration of existing native vegetation, blockade of migration routes, use patterns or other disruptions; Response: The Application contains an adequate Stormwater Management Plan; however, given the proximity to potential wetlands and potential waters of the US, consultation with the US Corps of Engineers was conducted and a Nationwide Permit 12 is required. Ursa delivered this information (Exhibit UUUU) to the County on December 4, 2015 in response to an existing condition of approval #4 which is: "Prior to construction, the Applicant shall provide copies of any permits required by the Army Corps of Engineers." Staff recommends keeping the condition as proposed. There will be limited dust generation possible vibration could occur from heavy machinery from the installation of the pipeline. This activity is expected to be very short in duration and a dust mitigation plan is contained that shall be implemented as a condition of approval. There are limited and temporary impacts to wildlife; however, the Colorado Parks and Wildlife has entered into a management plan with Ursa to manage these short term impacts. (2) Truck and automobile traffic to and from such uses shall not create hazards or nuisance to areas elsewhere in the County; • Response: As mentioned above, the Applicant has provided a traffic assessment that addresses adequacy of access and any impacts on adjacent County Roads. The report includes estimates on traffic generation, timelines for when it will be generated, and types of vehicles. The report concludes that "... the increase traffic during construction of the proposed pipeline is not expected to be significant on roads generally used by the public" and that the pipeline construction traffic does not increase existing volumes to levels required for State or County permits. The report indicates that most intersections will be adequate while noting a sight distance concern at the County Road 308 and East Valley Road (County Road 300E) intersection. Once constructed, there will be virtually no traffic associated with the pipeline. A main desire for the pipeline is to eliminate traffic on the road. (3) Sufficient distances shall separate such use from abutting property which might otherwise be damaged by operations of the proposed uses; Response: As noted earlier, the pipeline construction will occur over an aggressive 18 week duration. However, the alignment does run along the west and south perimeter of the Valley View Village neighborhood (a linear distance of approximately 1,300 feet) along the backyard lines of some 22 single-family and multi -family dwelling units. This is the section that is the closest to any residential uses and is expect to take approximately 21 days along the Valley View Village neighborhood. While short in duration along this section, there will be noise, dust and • 10 possibly fume impacts associated with the construction. Once the pipeline is completed, these impacts will discontinue for the life of the pipeline. It is suggested the Operator meet with these residents of Valley View Village prior and during construction to inform them of their plans, timing, and what to expect during the construction portion adjacent to their homes. This may include a website so that residents can monitor progress on a daily basis. (4) At the discretion of the County Commissioners additional information supplementing the impact statement may be required. Such request for additional information shall be in writing and shall be given to the applicant not later than forty-five (45) days after the filing of the impact statement. (5) Permits shall be granted for those uses only with the provisions that a satisfactory rehabilitation plan for the affected land be submitted prior to commencement of such use; (a) The plan for site rehabilitation shall be submitted to the Planning Director with the impact statement, and must be approved by the County Commissioners before a permit for conditional or special use will be issued; (b) The County Commissioners may require security before a permit for special or conditional use is issued, if required. The applicant shall furnish evidence of a bank commitment of credit, or bond, or certified check or other security deemed acceptable by the County Commissioners in the amount calculated by the County • Commissioners to secure the execution of the site rehabilitation plan in workmanlike manner and in accordance with the specifications and construction schedule established or approved by the County Commissioners. Such commitments, bonds, or check shall be payable to and held by the County Commissioners: Response: The Application submittal contains reclamation and re -vegetation plans including details on timing, interim reclamation, use of BMP's to avoid soil erosion, seed mix, final reclamation, minimum vegetative cover, and soil treatment to avoid compaction. Pursuant to referral comments from the Garfield County Vegetation Manager compliance with County Standards for re -vegetation shall be required along with security for re -vegetation at $32,500. The terms and conditions of the revegetation plan shall be considered conditions of approval. Section 5.03.08 Industrial Performance Standards: All industrial operations in Garfield County shall comply with applicable County, State, and Federal regulations regulating water, air and noise pollution and shall not be conducted in a manner constituting a public nuisance or hazard. Operations shall be conducted in such a manner as to minimize heat, dust, smoke, vibration, glare and odor and all other undesirable environmental effects beyond 0 11 • the boundaries of the property in which such uses are located, in accord with the following standards: (1) Volume of the sound generated: every use shall be so operated that the volume of sound inherently and recurrently generated does not exceed ninety (90) decibles, with a maximum increase of five (5) decibles permitted for a maximum of fifteen (15) minutes in any one hour, at any point of any boundary line of the property on which the use is located. (2) Vibration generated. every use shall be so operated that the ground vibration inherently and recurrently generated is not perceptible, without instruments, at any point of any boundary line of the property on which the use is located; (3) Emissions of smoke and particulate matter: every use shall be so operated so as to comply with all Federal, State and County air quality laws, regulations and standards; (4) Emission of heat, glare, radiation and fumes: every use shall be so operated that it does not emit heat, glare, radiation or fumes which substantially interfere with the existing use of adjoining property or which constitutes a public nuisance or hazard. Flaring of gases, aircraft warning signals, reflective painting of storage tanks, or other such operations which may be required by law as safety or air pollution control measures shall be exempted from this provision; (5) Storage area, salvage yard, sanitary land fill, and mineral waste disposal areas: (a) Storage of flammable, or explosive solids, or gases, shall be in accordance with accepted standards and laws and shall comply with the National Fire Code; (b) At the discretion of the County Commissioners all outdoor storage facilities for fuel, raw materials and products shall be enclosed by a fence or wall adequate to conceal such facilities from adjacent property; (c) No materials or wastes shall be deposited upon a property in such form or manner that they may be transferred off the property by any reasonably foreseeable natural causes or forces; (d) All materials or wastes which might constitute afire hazard or which may be edible by or otherwise be attractive to rodents or insects shall be stored outdoors in accordance with applicable State Board of Health Regulations: (6) Water pollution: in a case in which potential hazards exist, it shall be necessary to install • safeguards designed to comply with the Regulations of the Environmental Protection Agency 12 before operation of the facilities may begin. All percolation tests or ground water resource tests as may be required by local or State Health Officers must be met before operation of the facilities may begin. Response: These regulations listed above are performance regulations which means they will apply as conditions as long as the use is operating. Note, volume of sound is regulated by COGCC 800 Series which differs from Section 5.03.08(1) above. V. COMPREHENSIVE PLAN 2030 Response: The Garfield County Comprehensive Plan 2030, as amended, identifies the Battlement Mesa PUD as an "unincorporated community' which is further defined as self- contained subdivisions that contain town and neighborhood centers primarily to serve their own populations. Their infrastructure and certain governmental functions are provided by one or more special districts. Compatible zoning is identifies as residential urban, commercial limited, commercial general, and planned unit development. Battlement Mesa PUD was a fundamental example when this designation was crafted. The elements of the Plan that are the most germane to this application include 1) economy, employment and tourism, 2) natural resources, and 3) mineral extraction. Staff finds that the development of the pipeline is in general conformance with the County's Comprehensive Plan demonstrated by the following policies, goals and vision contained within the plan so long as adequate mitigations can be properly implemented to minimize adverse impacts: Economy, Employment and Tourism: Goal: Maintain a strong and diverse economic base (for both employment and income generation). Policy: Garfield County will encourage the development of a diversified industrial base recognizing physical location -to market capabilities of the community, and the social and environmental impacts of industrial uses. Strategy & Action: Ensure that commercial/industrial developments are compatible with adjacent land uses and preserve the visual quality of the county. Natural Resources Goal: Ensure that natural, scenic, ecological, and critical wildlife habitat resources are protected and/or impacts mitigated. Ensure the appropriate reclamation of land after extraction processes. Mineral Extraction i 13 Vision: Resource extraction, including oil and gas development, has been encouraged to remain in the • county due to their contribution they make to the county's overall goal of having a diverse and stable economy. While resource industries are welcomed in the county, they have been expected to fairly mitigate negative impacts that might have resulted due to their operations. Goals: Ensure that mineral extraction is regulated appropriately to promote responsible development and provide benefit to the general public. Ensure that mineral extraction activities mitigate their effects on the natural environment, including air quality, water quality, wildlife habitat or important visual resources. In working with mineral extraction projects, the county will protect the public health, safety and welfare of its citizens. Policies: Garfield County recognizes that surface and mineral owners have certain legal rights and privileges, including the right to extract and develop these interests. Private property owners also have certain legal rights and privileges, including the right to have the mineral estate developed in a reasonable manner and to have adverse impacts mitigated. The property rights of mineral lessees must be balanced with the rights of private property owners and the general public. Mineral resource extraction activities will protect critical wildlife habitat as identified by state and federal agencies. Development within these designations that cannot be designed, constructed and conducted so as to have a minimum adverse impact upon such habitat or these wildlife species, shall be discouraged. VI. BATTLEMENT MESA HEALTH IMPACT ANALYSIS In 2009, the Garfield County Board of County Commissioners commissioned the Colorado School of Public Health (CSPH) to conduct a Health Impact Assessment (HIA) in order to address citizen concerns about health impacts of natural gas development and production in the Battlement Mesa Planned Unit Development (PUD). The HIA scope of work was informed by citizen concerns and was limited to Battlement Mesa. The HIA process included stakeholder participation and review. The two primary functions of the HIA are to: 1) Identify ways in which Antero's proposed natural gas development project can affect the health of the Battlement Mesa residents; and 2) Develop a priority list of recommendations to minimize the potential health impacts of Antero's proposed project. A 2nd draft was completed in 2011; however, the Board of County Commissioners voted not to extend a contract with the University of Colorado School of Public Health to produce a final report for the Battlement Mesa Health Impact Assessment. At the time the contract was ended, 0 14 the BOCC did acknowledge their intent to use the document at the time an application to drill in Battement Mesa was submitted to the County. Staff has requested the Applicant to respond directly to the some 70+ recommendations suggested in the HIA for the benefit of the decision makers; however, the required land use review in this memorandum is focused solely on the rules and regulations adopted and required by the BOCC. Although not legally required, the Applicant has addressed portions of the HIA in depth at their numerous community outreach meetings as well as produced a complete spreadsheet (Exhibit TT) that specifically addresses each of the HIA recommendations as a courtesy to this discussion and the Board of County Commissioners. Again, while the HIA is not a legally binding document and does not contain any rules or regulations adopted by the BOCC, Staff has identified the suggested COAs here for consideration. 1. Install a fully functional water storage facility and pipeline network before any development of well pads in the Battlement Mesa. 2. Conduct monthly inspection of water and gas pipeline for leaks to prevent water and soil pollution and that the results of the inspections be posted on the Garfield County Website. 3. Notify the sheriff and fire department one week prior to well drilling, hydraulic fracturing, flow back, and pipeline pigging activities. 4. Adhere to its best management practices for pipelines and all COGCC rules throughout the life of the project as a condition of the special use permit. 5. Require all gas pipelines to follow established truck haul routes and allow no gas pipelines through the center of the PUD. 6. Assign a County inspector to oversee and inspect all pipeline construction and maintenance in the PUD. VII. SUGGESTED FINDINGS 1. That proper public notice was provided as required for the hearing before the Planning Commission and Board of County Commissioners. 2. The hearing was extensive and complete, that all pertinent facts, matters and issues were submitted and that all interested parties were heard at the meeting. 3. For the above stated and other reasons, the proposed Special Use Permit and Pipeline Land Use Change Permit is in the best interest of the health, safety, convenience, order, prosperity and welfare of the citizens of Garfield County. • 15 4. That with the adoption of conditions, the application is in general conformance with the 2030 Comprehensive Plan, as amended. 5. That with the adoptions of conditions and the application has adequately met the Pipeline Review Criteria contained in Section 9-104 of the Land Use and Development Code, as amended and the Special Use Permit Criteria contained in the Garfield County Land Use Resolution of 1978 as amended. VIII. PLANNING COMMISSION RECOMMENDATION On October 28, 2015, the Planning Commission forwarded a recommendation of approval to the Board of County Commissions (by a vote of 6 to 1) for the proposed Special Use Permit for a Pipeline with the following suggested findings and conditions. 1. That all representations of the Applicant, either in testimony or the submitted application materials, shall be considered conditions of approval unless specifically altered by the Board of County Commissioners. 2. That the Pipeline shall be operated in accordance with all applicable Federal, State and local regulations governing the operation of this type of facility. 3. Prior to issuance of the Special Use Permit, the Applicant shall provide additional operational procedures for monitoring protocol for the pipeline for leak or spill detection. Said procedures will be included in the Emergency Response Plan or as an addendum to said plan. The Applicant shall comply with all provisions of the SPCC Plan including spill response and clean-up. 4. Prior to construction, the Applicant shall provide copies of any permits required by the Army Corps of Engineers. 5. Prior to issuance of the Special Use Permit, the Applicant shall provide security in a form acceptable to the County Attorney's Office in the amount of $32,500 for re -vegetation. The Applicant shall comply with the representations in their Weed Management Plan and shall comply with the Reclamation Standards contained in the Garfield County Weed Management Plan as noted in the referral comments from the County Vegetation Manager dated September 11, 2015. 6. Prior to initiating construction the Applicant shall obtain all required permits from the Road and Bridge Department including but not limited to permits for boring, road cuts, overweight or oversize vehicles, temporary access, and grading within the right-of-way. Compliance with all conditions of the Road and Bridge permits shall be required. The Applicant shall be responsible for repair of any damage to roadways or curbs. 7. Prior to initiating construction the Applicant shall submit for approval by the Road and Bridge 0 16 Supervisor traffic control plans including areas adjacent to the County Road Right of Way, construction access points, proposed bore locations and potential road cuts or the Applicant can demonstrate that traffic control plans are addressed in the applicable Road and Bridge Permits. 8. The Applicant shall coordinate with the County Road and Bridge Department during construction including field inspections as needed to ensure that minimum pipeline depths are maintained and to ensure construction is done in a manner that maintains current drainage along County Roads and avoids conflicts with future drainage. The Applicant shall install posts/markers along key sections of the pipeline indicating depth to the pipeline. Maintaining drainage shall be the responsibility of the pipeline operator subject to approval by the Road and Bridge Supervisor. 9. The pipeline shall maintain compliance with CDPHE Storm Water Management Permits, Drainage and Soil Erosion Protection, BMP's, Reclamation and Re -vegetation Plans, and Weed Management Plans. 10. The Applicant shall comply with all COGCC rules and regulations regarding the pipeline facility including but not limited to reclamation and decommissioning. 11. The Applicant shall maintain compliance with COGCC Rules and Regulations in regards to noise abatement and C.R.S. Article 12 of Title 25, noise standards as appropriate. Any pumping stations required for operation of the pipeline shall utilize electric pumps or muffled internal combustion motors. 12. The Applicant shall maintain all required CDPHE permits for the facility including any applicable air quality APEN permits. 13. The Applicant shall comply with the Battlement Mesa Wildlife Mitigation Plan - Agreement between Ursa Operating Company and CPW including any wildlife protection or mitigation requirements. The Applicant shall comply with recommendations of the Sensitive Areas Survey completed by WestWater Engineering Inc. dated June 2015, including but not limited to weed management, re -vegetation, avoiding construction during nesting seasons, and temporary safety fencing for open trenches as needed. 14. In accordance with Section 9-103 (J), upon completion of the pipeline the Applicant shall submit an engineer's statement certifying compliance with the conditions of the Land Use Change Permit and a digital copy of the surveyed pipeline as built. 15. Potable water and sanitation shall be addressed during construction by provision of portable facilities in compliance with OSHA requirements. 016. The Operator shall commit to ensuring truckloads of dirt, sand, aggregate materials, drilling 17 cuttings, and similar materials are covered to reduce dust and PM emissions during transport. 17. The construction of the Pipeline shall be limited to the hours of 7:OOAM to 7:OOPM, Monday through Saturday. If inclement weather conditions or field conditions require schedule changes, construction may occur on Sundays to meet construction schedule. Ursa will notify Garfield County and affected residents if Sunday work is necessary. 18. All extraction and processing activities shall be required to comply with the following performance standards: (1) Volume of the sound generated: The noise shall be required to meet the standards in COGCC Rule 800 Series. (2) Vibration generated: every use shall be so operated that the ground vibration inherently and recurrently generated is not perceptible, without instruments, at any point of any boundary line of the property on which the use is located; (3) Emissions of smoke and particulate matter: every use shall be so operated so as to comply with all Federal, State and County air quality laws, regulations and standards; (4) Emission of heat, glare, radiation and fumes: every use shall be so operated that it does not emit heat, glare, radiation or fumes which substantially interfere with the existing use of the adjoining property or which constitutes a public nuisance or hazard. Flaring of gases, aircraft warning signals, reflective painting of storage tanks, or other such operations which may be required by law as safety or air pollution control measures shall be exempted from this provision; (5) Storage area, salvage yard, sanitary land -fill, and mineral waste disposal areas: (a) Storage of flammable, or explosive solids, or gases, shall be in accordance with accepted standards and laws and shall comply with the National Fire Code; (b) At the discretion of the County Commissioners all outdoor storage facilities for fuel, raw materials and products shall be enclosed by a fence or wall adequate to conceal such facilities from adjacent property; 0 18 e (c) No materials or wastes shall be deposited upon a property in such form or manner that they may be transferred off the property by any reasonable foreseeable natural causes or forces; (d) All materials or wastes which might constitute a fire hazard or which may be edible by or otherwise be attractive to rodents or insects shall be stored outdoors in accordance with applicable State Board of Health Regulation; (6) Water pollution: in a case in which potential hazards exist, it shall be necessary to install safeguards designed to comply with the Regulations of the Environmental Protection Agency before operation of the facilities may begin. 19. The Operator shall provide information to the residents of Valley View Village prior and during construction to inform them of their plans, timing, and what to expect during the construction portion adjacent to their homes. More specifically, the Operator shall meet with HOA Presidents or appropriate neighborhood representatives. 20. Prior to the issuance of a Special Use Permit, the Applicant shall address the comments prepared by Garfield County Consulting Engineer, Chris Hale, Mountain Cross Engineering: a) The Applicant should include fittings or transition necessary to transition from a 12" pipe to a 16" pipe at station 47+00. b) There are two horizontal bends proposed in an area of pipeline that is proposed to be bored beneath Stone Quarry Road, station 59+37 to station 61+87. The Applicant should discuss the feasibility of constructing 452 and 872 bends in borings. c) The Applicant should provide a detail for the proposed valve sets. d) The typical trench section should be revised to match the Garfield County conditions for pipeline installations. The note on the cover should be revised to reference these conditions also. 21. The "Integrated Vegetation and Noxious Weed Management Plan" prepared by West Water Engineering identified locations along the pipeline that had riparian areas and wetlands. The Applicant should identify if any permitting was obtained and/or necessary and the mitigation that was implemented. Specific construction mitigation necessary should be included on the plan sheets. 22. Applicant agrees and commits to a three year time frame for Phase I activities which includes placing up to 53 wells into full production. This time frame will commence at the start of construction of either Phase I well pads or pipeline. 0 19 • IX. RECOMMENDED MOTION "I will make a motion to approve the Special Use Permit Application forthe Ursa natural gas and water pipeline with the specific findings and conditions as contained herein." n • 20