Geotechnical, Environmental and Materials Testing Consultants
Grand Junction - Montrose - Moab - Crested Butte - Rifle
(970) 245-4078 h fax (970) 245-7115 h geotechnicalgroup.com
2308 Interstate Avenue, Grand Junction, Colorado 81505
June 29, 2009
Chevron North America Exploration & Production Company
744 Horizon Court, Suite 140
Grand Junction, CO 81506
Attention: David K. Howard
Subject: Chevron Central Processing Facility-Stage 2
Garfield County Foundation Permit Nos:
11192, 11194, 11204, 11224, 11244, 11245, 11246, 11247, 11248,
11250, 11251 and 11284
GEG Job No. 3,241
Document Number: PBSR-59836AVF-CIV-RPT-GEG-03241-00001
Dear Mr. Howard,
As requested, a Geotechnical Engineering Group (GEG) representative
performed observation and testing services on a full time basis during
construction of the structure foundations listed above by Garfield County Building
Permit No. The GEG representative tested structural fill compaction beneath
foundations, tested concrete properties, observed reinforcing steel placement
and documented structure to foundation anchorage for each of the structures.
The purpose of this letter is to present our review of observation and testing data
and our conclusions regarding final foundation construction of the subject
structures. In summary, each of the structures identified was constructed in
conformance with the referenced engineering design documents.
Following is a summary of the GarCo Permit No., Design Identification and
the structure common name for each structure reviewed:
11192 ZZZ-0115 PUMP CONTROL BUILDING
11194 ZZZ-0114 CONDENSATE LOADING SKID BUILDING
11204 ZZZ-4001 CONTROL BUILDING
11224 ZZZ-0104 TELECOMUNICATIONS BUILDING
11244 ZZZ-0117 VAPOR RECOVERY UNIT BUILDING
11245 MAK-11245 GAS FILTER SEPERATOR SKID BUILDING
11246 ZZZ-103 INSTRUMENT AIR SKID BUILDING
11247 MBF-1070 FUEL GAS SCRUBBER BUILDING
11248 MBF-1090 FLARE SCRUBBER BUILDING
11250 BBC-0210 GLYCOL REBOILER/SURGE SKID BLDG, (1 of 2)
Chevron Central Processing Facility-Stage 2 Page 2 of 3
Garfield County Foundation Permit Letter
Shallow, 7-1-09
GEG Job No. 3241
11251 BBC-0212 GLYCOL REBOILER/SURGE SKID BLDG, (2 of 2)
11284 ZZZ-102 RESTROOM BLDG
Reference Documents:
Foundation design sheets by Projects Associates, Incorporated
2033-201-CL-1101-01 dated 12/27/07 and revised 11/13/08 (all permits)
2033-201-20-AP-0002-02 dated 5/14/08 and revised 5/18/09 (all permits)
2033-240-30-SP-0004-01, Rev D dated June 21, 2008 (all permits)
2033-201-30-CI-1135-01, Rev O dated 11/15/08 (#11192)
2033-201-30-CI-1120-01, Rev O dated 9/19/08 (#11194)
2033-201-30-CI-1104-04, Rev O dated 10/15/08 (#11204)
2033-201-30-CI-1141-01, Rev O dated 10/24/08 (#11224)
2033-201-30-CI-1117-01, Rev O dated 10/16/08 (#11224)
2033-201-30-CI-1111-01, Rev O dated 9/19/08 (#11245)
2033-201-30-CI-1122-01, Rev 2 dated 2/10/09 (#11246)
2033-201-30-CI-1114-01, Rev 1 dated 11/3/08 (#11247)
2033-201-30-CI-1130-01, Rev O dated 10/16/08 (#11248)
2033-201-30-CI-1116-01, Rev O dated 11/20/08 (#11250/11251)
2033-201-30-CI-1130-01, Rev O dated 10/16/08 (#11284)
2033-201-30-CI-1134-01, Rev 1 dated 2/19/09 (#11284)
Conclusions
Review of our records indicates proper structural fill compaction beneath
foundations, proper concrete strength, proper reinforcing steel placement and
proper structure to foundation anchorage for each of the structures. Based on
this review, we conclude each of the structures identified was constructed in
conformance with the referenced engineering design documents.
We appreciate the opportunity to perform engineering services. If we can be of
further service or answer any questions regarding this letter, please call.
Sincerely,
GEOTECHNICAL ENGINEERING GROUP, INC.
Scott Godfrey, EIT
Project Engineer
Chevron Central Processing Facility-Stage 2 Page 3 of 3
Garfield County Foundation Permit Letter
Shallow, 7-1-09
GEG Job No. 3241
Reviewed By:
John P. Withers, P.E.
Engineer
SEG:JPW:sg
1 cc: Chevron Eroom
1 cc: emailed to Mr. David K. Howard,
1cc: emailed to Tony Chiono, Elkhorn Construction