HomeMy WebLinkAbout2.0 Final Signed AgreementMID-CONTINENT QUARRY AND TRANSFER TRAIL OPERATIONS AGREEMENT
This MID-CONTINENT QUARRY AND TRANSFER TRAIL OPERATIONS AGREEMENT
("Agreement') is effective as of April 1, 2010 by and between CaIX Minerals LLC (hereinafter
"CaX ), a Colorado limited liability company, the address of which is 2040 W. Hamilton Place,
Sheridan, CO 80110, and Glenwood Tramway LLC (hereinafter "Gr), a Colorado limited
liability company, the address of which is 51000 Two Rivers Plaza, Glenwood Springs, CO 81601.
WHEREAS, CaIX owns and operates the Mid -Continent limestone quarry, which is located just
north of Glenwood Springs, Colorado, and which may be accessed via Transfer Trail;
WHEREAS, GT owns and operates the Glenwood Caverns Adventure Park, which is also located
just north of Glenwood Springs, Colorado, and which may also be accessed via Transfer Trail; and
WHEREAS, CaIX and GT wish to memorialize certain agreements that they have made regarding
Ca1X's Mid -Continent quarry operations, contemplated improvements to Transfer Trail, the
extension of new utility infrastructure along Transfer Trail, and maintenance of Transfer Trail.
NOW, THEREFORE, in consideration of the mutual covenants and commitments herein contained,
and other good and valuable consideration, the receipt and sufficiency of which are hereby
acknowledged, CatX and GT agree as follows:
1. Term. This Agreement shall be in effect for an Initial Term of five years. The
Agreement will automatically renew for three successive five year Terms unless the parties agree to
terminate it at the end of a five year Term. Thereafter, the parties may agree in writing to extend
the Agreement for additional terms.
2. Ouany Operations. Ca1X shall minimize its blasting activity at the Mid -Continent quarry
during the period Memorial Day through Labor Day (which is the principal `season' for GT). CaIX
shall provide reasonable advance notice to GT of any blasting activity. CaIX will not extend the pit
of the Mid -Continent quarry any closer to GT's property boundary than 1320 feet (one-quarter of a
mile). CaIX will minimize noise levels at the Mid -Continent quarry by enclosing the milling
operations and by employing `discriminating' alarms on its rolling stock.
3. Radio Usage on Transfer Trail. GT will provide CaIX certain radio frequencies for use by all
drivers working for each of CaIX and GT; all drivers working for either of CalX and GT will
disclose their locations on Transfer Trail, pursuant to a separate "Radio Usage Agreement" which
the parties will execute at a later date. Ca1X and GT will provide radios for their own drivers.
4. UtilitEasement and Installation. GT will grant to the City of Glenwood Springs an
electrical easement across GT's property for a 15kV electric line in order to extend electrical access
along Transfer Trail up to Mid -Continent quarry. CaIX will allow GT to connect to all such
extended utilities, such connection point to be at the scale house of the Mid -Continent quarry.
CaIX and GT shall have separate meters for measuring usage.
5. Road Maintenance. Ca1X will maintain Transfer Trail from the uppermost quarry entrance
down to Traver Tail for the entire Term of this Agreement. Required maintenance activities
?oM
include, but are not limited to, dust control, road grading, ditch clearing, and snow removal. CaIX
shall provide all gravel as may be required for all maintenance activities on Transfer Trail including
the portion maintained by GT.
6. Road Upgrade GT will eventually elect to upgrade Transfer Trail to handle increased traffic.
These upgrades will include, but not be limited to, engineering, surveying, widening road, reducing
grades, guard rails, and paving. CaIX and GT agree to split equally all upgrade costs incurred from
Traver Trail along Transfer Trail to the uppermost quarry entrance.
7. County of Garfield Resolutions. CatX will comply with the provisions of Garfield County
resolution Nos. 2009-97 and 82-222 and any amendments thereto or permits issued thereunder.
Those resolutions are attached to this Agreement as Exhibit A.
8. Termination. This Agreement will terminate if CaIX ceases its quarry operations. CaIX
agrees to provide GT written notice that its operations have ceased.
9. Mediation. If any claim, controversy or dispute ("Dispute") arises between the parties that
cannot be settled by negotiation, the parties agree to submit the Dispute to non-binding mediation
for resolution before seeking redress through litigation. The parties will choose a mediator from a
list provided by the Garfield County Court. If the Dispute cannot be resolved through mediation,
the parties will submit the Dispute to binding arbitration in accordance with the rules of the
American Arbitration Association. The laws of Colorado will govern the interpretation of this
Agreement and the venue for resolving a Dispute will be Garfield County, Colorado.
10. Modification. This Agreement maybe modified or amended by written document signed by
both parties.
11. Successors and Assigns. The provisions of this Agreement shall inure to the benefit of and
be binding upon the parties hereto, their successors and assigns.
12. Entire Agreement. This Agreement constitutes the entire agreement between the
parties with respect to the subject matter of this Agreement. This Agreement supersedes all prior
oral and written communications, agreements and understandings of the parties not made a part
of this Agreement.
13. Notices. Any notice to be given under this Agreement will be in writing sent by first
class mail or overnight delivery to the following addresses or to such other address as a party
may direct in writing:
To Ca1X: CaIX Minerals LLC
2040 W. Hamilton Place,
Sheridan, CO 80110
$A b4ft
To GT: Glenwood Tramway, LLC
Attention: Steve Beckley
51000 Two Rivers Plaza
Glenwood Springs, CO 81601
IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the date first
above written.
CaIX Minerals LLC
By:
6jamin H. Miller, Managing Member
Glenwood Tramway, LLC
By:
Steve Beckley, Manag ber