HomeMy WebLinkAboutLetter from Engineer 07.19.2014KURTZ & ASSOCIATES. INC.
5012 County Road 154
Glenwood Springs, CO 81601
STRUCTURAL CONSULTANTS
Phone (970) 945 6305
Fax (970) 945 1093
MEMORANDUM
To: Garfield County Building and Planning Department
108 Eight Street
Glenwood Springs, Co.
Re: ECOS Commercial Building: Summary of Field Inspections
6690 Highway 82, Garfield County, CO.
July 19, 2014
Kurtz & Assoc., Inc. is the structural engineer of record for the noted commercial
building. The building footprint is 40'-0" north -to -south by 103'-8" east -to -west. The
large, walk -out basement type structure building is a two story structure which occupies a
relatively steep site. Consequently, the floor -to -floor height from the lower level to the
main level is 14'-6". The lower level floor is a concrete slab -on -grade.
Brian Kurtz, P.E. of Kurtz & Assoc., Inc. performed the following structural
inspections during the course of the construction:
A. Feb. 22, 2013: Inspected the foundation during construction. At that time the
footings had been poured and forming for the perimeter foundation walls was in progress.
Footing sizes, and dowel size and spacing was verified to be in conformance with the
structural documents.
B. July 08, 2013: Inspected the upper floor framing. The upper floor system
consists of a 3" thick concrete slab placed on corrugated steel form deck over 12" deep
light gage steel 'C' joists spaced at 12" on center. The 'C' joists span approximately
20'-0" and are supported on 18" deep (W18's) wide flange, structural steel beams. The
south edge of the upper floor, and subsequently the south exterior wood stud bearing wall,
are supported by 12" deep (W12's) wide flange, structural steel beams. The W12's span
approximately 20'-0" in concert with the floor joists and are supported by structural steel
columns. The framing system was designed so that the lower level walls along the south
side of the building were not load bearing walls. The beams and columns along the south
wall from grid '4' to '6' were designed as a rigid frame to resist lateral loads given the
absence of any structural walls on this side of the building. At this time the specified
beam -to -column welding necessary to create the rigid frame was not fully complete: the
beam to column welding at grid line '6' was yet to be implemented, and the beam -to -
column welding at grid line '4' was incomplete. This welding was completed and re-
inspected by our office on Sept. 06, 2013.
(2)
C. Sept. 06, 2013: Inspected the upper level, exterior, wood stud bearing walls,
the upper level, interior, wood stud shear walls and the roof framing. The roof framing
system utilizes pre -manufactured roof trusses spaced at 24" on center spanning 40'-0"
north -to -south. Two significant structural changes were addressed at this time:
1. The roof overhangs overhang on the south, east and west sides of the building were
increased to 4'-0".
2. The conventional wood stud bearing walls with structural headers at window openings
was revised, in part, to incorporate continuous polycarbonate wall panels.
These two revisions were addressed by our office at that time, and were incorporated into
the structural documents on July 31, 2014.
D. June 24, 2014: Inspected the repair of a concrete corbel on grid line '6'. The
corbel supports the north end of the W18 steel floor beam. The concrete had cracked
during construction at this location. A triangular steel bracket had been epoxy bolted to
the end of the concrete wall and a 3" high steel strap had been extended from the bracket
across the corbel and crack and bolted into the sound concrete wall. The strap is located
near the bottom of the 12" high bracket. I recommended that a second horizontal strap be
installed near the top of the bracket, and in a manner similar to the initial strap, extended
across the crack, and bolted to the sound concrete and welded to the vertical steel plate.
At this time I also noted that a wind load resisting hold-down anchor had not been
installed. The anchor attaches the south end of the upper level, interior, wood stud wall
on grid line '5' to the W18 steel floor beam. I recommended that the hold-down be
installed in accordance with the structural documents.
E. July 25, 2014: Re -inspected the grid line '6' concrete corbel repair, and
verified that the hold-down anchor on grid line '5' was installed. The'completed corbel
repair is structurally acceptable. The hold-down was installed as specified.
CONCLUSION:
At this time the structural elements of the building have been substantially
completed in a professional manner, and are in accordance with the structural documents.