HomeMy WebLinkAboutApplication- PermitNo. 6615
GA FI FI D COUNTY
BUILDING, SANITATION and PLANNING DEPARTMENT
109 8th Street Suite 303
Glenwood Springs, Colorado 81601
(303) 945-8212
Lot 22, Block 6, Aspen Crystal River Estates, Carbondale
Job Address
Nature of Work
.Jse of Building
Owner
Building Permit
Manu. Horne on Foundation
Buffalo Ranch LBC
Contractor
Bell country Hciii
Amount of Permit S 405.84
Permit: 124.75
Plan : 81.09
Set Up Fee : 200.00
Paid $81.09 1-23-98
Date February 13, 1998
S. Archuleta
Clerk
BUILDING PERMIT APF CATION
s3ARFIELD COUNTY, COLORAL'
Applicant to cram late numbered spaces only. PERMIT NO. 44 r.- PARCEDSCHED NO.
Joe ADDRESS
1
LEGAL
DESCR.
LOT F.10. Z
BLOCK
SUBOIVP;ION
2
OWNER3 0 fir-kx
ADDRESS -
3
4
5
CONTRACTOR- �U1�t6
ARCHITECT OR DESIGNER atv4
ENGINEER
aoK
ADDRESS C60
LI2.6 r L r2t U t 12 1-6 TeS
ADDRESS
ADDRESS
S,F OF BUILDING / if go
S.FofIOT 7o-1
7
USE OF BUILDING F 1 SCIfJCNT,AL-
8
CLASS oFV„+oRx: XNEW ❑ADDITION ❑ALTERATION ❑REPAIR .0 MOVE ❑REMOVE
LICENSE NO.
NO. OF FLOOR
DESCRreE',VORIC 54- tit)1 } Cc t /IA r`�v U f`/'1G roe-cooe. t. 6 Ncow-1��0..//`` ���t/
10
GARAGE SINGLE DOUBLE
CARPORT SINGLE
DOUBLE
DRIVEWAY PERMIT ON SITE SEWAGE DISPOSAL PERMIT
SITE PLAN
11
VALUATION OF WORK: $ ADJUSTED VAL.$
SPECIAL CONDITIONS:/ y 6 , a' ��
NOTICE
SEPARATE PERMITS ARE REQUIRED FOR ELECTRICAL PLUMBING, HEATING,
VENTILATING OR AIR CONDITIONING.
THIS PERMIT BECOMES NULL AND VOID IF WORK OR CONSTRUCTION AUTHORIZED IS
NOT COMMENCED W1THIN 180 DAYS, OR IF CONSTRUCTION OR WORK IS SUSPENDED
OR ABANDONED FOR A PERIOD OF 180 DAYS AT ANY ME AFTER WORK IS
COMMENCED.
I HEREBY CERTIFY THAT 1 HAVE'READ AND EXAMINED THIS APPLICATION AND KNOW
THE SAME TO BE TRUE AND CORRECT. ALL PROVISIONS OF LAWS AND ORDINANCES
GOVERNING THIS TYPE OF WORK WILL BE COMPLIED WITH WHETHER SPECIFIED
HEREIN OR NOT. THE GRANTING OF A PERMIT DOES NOT PRESUME TO GIVE
AUTHORITY TO VIOLATE OR CANCEL THE PROVISIONS OF ANY OTHER STATE OR
LOCAL LAW RE ULA N • T TION OR THE PERFORMANCE OF
CONSTRUCTIQN t f 'v 1: / .�
lr.� Date
Signature or
r, Contractor or authoriz
uilding artmentApprovalda
*gent havine rea.. •'understood roti - Above.
Planning Department Approval/dat
PLAN CHEC'.; FEE
SCHOOL IMF ACT FEE
US'. OF BUILDINGS NOW ON
PAr::'TEL
TOTAL
CCs ST. TYPE
WATER SUF- LY
SPECIAL AP! 'iOVALs
ZONING
HEALTH DEI
FIRE DEPT.
SOIL REPOR
SETBACKS
FLOOD HAL' D
MANUF. HOF -r
OTHER t'P
DATE PERMIT 15SUED
REQUIRED
-001 0 b
RECE,VEo
AGREEMENT '�-113
PERMISSION IS HEREBY GRANTED TO THE APPLICANT AS OWNER, CONTRACTOR AND/OR THE AGENT OF THE CONTR..CTOR OR OWNER TO
CONSTRUCT THE STRUCTURE AS DETAILED ON PLANS AND SPECIFICATIONS SU81•ATTED TO AND REVIEWED BY THE BUILDING DEPARTMENT
IN CONSIDERATION OF THE ISSUANCE OF THIS PERMIT THE SIGNER HEREBY AG'ZEES TO COMPLY WITH ALL BUILDING
REGULATIONS ADOPTED BY GARFIELD COUNTY PURSUANT TO AUTHORITY GIV N IN 30.28.201 CRS AS AMENDED. i
AGREES THAT IF THE ABOVE SATO ORDINANCES ARE NOT FULLY COMPLIED WIT! IN THE LOCATION, ERECTION, CONS]
THE ABOVE DESCRIBED STRUCTURE. THE PERMIT MAY THEN BE REVOKED BY !OTICE FROM THE COUNTY AND THA'
SHALL BECOME NULL AND VOID.
THE ISSUANCE OF A PERMIT BASED UPON PLANS, SPECIFICATIONS AND OTHE''. DATA SHALL NOT PREVENT THE BIN
THEREAFTER REQUIRING THE CORRECTION OF ERRORS IN SAID PLANS, SPECIFIs :ATIONS AND OTHER DATA OR FROM
OPERATION BEING CARRIED ON THEREUNDER WHEN IN VIOLATION OF THIS G ,DE OR ANY OTHER ORDINANCE OR
JURISDICTION.
:ODES AND LAND USE
AE SIGNER FURTHER
UCTION AND USE OF
THEN AND THERE IT
DING OFFICIAL FROM
''EVENTING BUILDING
'EGULATION OF THIS
THE REVIEW OF THE SUBMITTED PLANS AND SPECIFICATIONS AND INSPECTI(.NS CONDUCTED THEREAFTER DOES rJOT CONSTITUTE AN
ACCEPTANCE OF ANY RESPONSIBILITIES OR LIABILITIES BY GARFIELD CODE TY FOR ERRORS, OMISSIONS OR L''"CREPANCIES, THE
RESPONSIBILITY FOR THESE ITEMS AND IMPLEMENTATION DURING CONSTRUCT,' UN RESTS SPECIFICALLY WITH THE A''ICHITECT, DESIGNER,
BUILDER AND OWNER. COMMENTS ARE INTENDED TO BE CONSERVATIVE AND INE '.]PPORT OF THE OWNERS INTEREST. ff
Gatform.003 I HEREBY ACKNOWLEDG\THAT I I LAVE READ AND UNDER;TAND THE AGREEMENT ABOVE IINITIA .`]Lti� f
The following items are required by Garfield County for a final inspection:
1. A final Electrical Inspection from the Colorado State Electrical Inspector,
2. Permanent address assigned by Garfield County Building Department posted where readily
visible from access road;
3. A finished roof, a lockable house, complete exterior siding, exterior doors and windows
installed, a complete kitchen with cabinets, a sink with hot & cold running water, non-absorbent
kitchen floor coverings, counter tops and finished walls, ready for stove and refrigerator, all
necessary plumbing;
4. A complete bathroom, with wash bowl, tub or shower, toilet stool, hot and cold running
water, non-absorbent floors and walls finished and a privacy door;
5. All steps outside or inside over three (3) steps must have hand; ails, guard rails on balconies or
decks over 30" high constructed to all 1994 UBC requirements;
6. Outside grading done to where water will detour away from the building;
7. Exceptions to the outside steps, decks and grading may be made upon the demonstration of
extenuating circumstances, i.e. weather, but a Certificate of Occupancy will not be issued until all
the required items are completed and a final inspection made.
A CERTIFICATE OF OCCUPANCY WILL NOT BE ISSUlk 0 UNTIL ALL THE ABOVE
ITEMS HAVE BEEN COMPLETED.
**4*Cannot occupy or use dwelling until a Certificate of Occupa, icy (C.O.) is issued.
Occupancy or use of dwelling without a C.O. will be considered a,t illegal occupancy and may be
grounds for vacating premises until above conditions are met.
I understand and agree to abide by the above conditions for occupancy, use and the issuance of a
Certificate of Occupancy for the dwelling under building permit #f 6 6 (-3-
66,a4,10
,a/L f_1- ZL-
Date
. 8'o aC-7,414,1•0 d 0
Je<1/ 7
_. � a Y
1 -. 200 , a 0
GARFIELD COUNTY
Building and Planning Department
February 11, 1998
Buffalo Ranch L.L.C.
c/o Jeff Parker
P.O. Box 221
Carbondale, CO 81623
RE: Building Permit applications
Dear Mr. Parker:
Please consider this letter to be a written summary of our phone conversation on February 10,
1998, regarding three (3) building permit applications requested by the Buffalo Ranch L.L.C..
As I noted, the applications have been reviewed and approved by the Building and Planning
Department, and are ready for you to pick up and pay the remaining fees.
As I noted in the conversation, I would encourage you not to pay the remaining fees and pick up
the permits, until you are convinced that there is no other alternative available. At a minimum, I
would suggest waiting until after the March 18`" meeting in Carbondale to discuss the issues
revolving around the Te -Ke -Ki and Aspen Crystal River Estates subdivisions. Your permits
will need to be paid for and issued within 90 days of this letter, which should give everyone
ample opportunity to try and come to an agreement that will satisfy all of the interested parties.
If you chose to pick up the permits before there is any resolution of these issues, you will be
required to sign the statement that I faxed down to you yesterday. A copy of the statement is
enclosed for your review. Basically, the statement is acknowledging that the County Building
Department is not responsible for gaining legal access to the property for inspection purposes. If
access is not available, it may result in the invalidation of the building permits.
If there is any difference in your understanding of our conversation, please let me know.
Sincerely,
Mark L. Bean, Director
Building & Planning Department
109 8th Street, Suite 303
945-8212/285-7972 Glenwood Springs, Colorado 81601
if?AJ
NOTICE
This notice is provided to the applicant(s) for building permits for
structures located in subdivisions with uncertain legal access. Garfield
County will issue a building permit for any legally created lot and the
structure can be located on the lot in conformance with the Garfield
County Zoning Resolution and Individual Sewage Disposal Regulations.
At the time of submission of a building permit application, a fee for the
review of the plans will be charged and at the time of issuance of the
building permit, a fee will be charged. All fees are not refundable, if the
applicable work has been done by the County.
To do inspections of work, the Garfield County Building Department
must be able to access the property where the structure is being built. If
Garfield County is not allowed to access the property, the County will
not complete the final inspection and the building cannot be lawfully
occupied. It is your responsibility to insure that all work is accessible
pursuant to Section 108.01 of the 1994 Uniform Building Code.
Further, work pursuant to this permit must commence within 180 days
of issuance or the permit will become void. A new building permit will
have to be obtained to start or continue any work.
The above statements are acknowledged by:
D e�
This signed statement will be attached to the building permit(s) subject
to the above statements
EQUIRED BUILDING SST BACKS
VERY GE] ITLE DOWN5L PE
TOWARDS Tl-iE. Sal IrH
C\ EXISTWIS SVED
PROPOSED SEPTIC 5
}'i-:UPUSE.L3 WELL
0
2. WIDE GRAVEL DIVE
NOTE:
BUILDER WILL MAINTAIN A MINIMUM SEPARATIC1 J
OF 1Zm. BETWEEN THE SEPTIC SYSTEM AND THE
WEI_I _.
FELL_ COUNTRY HOMES
P.O. BOX 229
NEW CASTLE. CO 81647
(970) 984-3500
JANUARY 21, 1998
PROJECT SITE PLAN
L0T22, BLOCK 6
ASPEN CRYSTAL RIVER ESTATES
GARFIELD COUNTY. COLORADO
PREPARED FOR: BUFF ALO RANCH. LLC
Z EU
m•r
X' e
eG/�
7 w o
*/%/
mea
�o f
G o
¢
P1
w g
�TFUGTUKAL- PANEL -5
rn
rn
� o
-{ 0
ni 7
1/4.S
- .ri - rn rn
___) z C
c:., _n "--I i -TI
(iKA`<'ING AWAY FROM 5TI LJGTORE
CP
_a
i
n+
7
n+
rs
0
0
010
0
1
00
0
(4
0
0
m
-1.
z
0
0
0
0
1 - 6
GARFIELD COUNTY BUILDING AND PLANNING
MINIMUM APPLICATION REQUIREMENTS
for
SINGLE FAMILY DWELLING CONSTRUCTION
including
NEW CONSTRUCTION
MANUFACTURED HOMES
ADDITIONS
ALTERATIONS
and
MOVED BUILDINGS
In order to understand the scope of the work intended under a permit application and
expedite the issuance of a permit it is important that complete information be provided.
Adequate and complete information will prevent delays in the plan review process.
Reviewing a plan and the discovery that required information has not been provided by the
applicant may result in the delay of the permit issuance and in proceeding with building
construction. The owner or contractor may be required to provide this information before
the plan review may proceed. This causes delays because other plans that are in line for
review may be given attention before the new information may be reviewed after it has
been provided to the Building Department.
Please review this document to determine if you have enough information to design
your project and provide adequate information to facilitate a plan review. If you do
not, it may be helpful to obtain a book titled "Dwelling construction under the
Uniform Building Code. This book is available to you through this department at our
cost. Also, please consider using a design professional for assistance in your
design and a construction professional for construction of your project.
To provide for a more understandable plan in order to determine compliance with the
building, plumbing and mechanical codes, applicants are requested to review the following
check list prior to and during design. Applicants are required to indicate appropriately and
to submit completed check list at time of application for a permit:
For the placement of a manufactured home, questions numbers 1-4 and 19-28 are
the only questions that need to be addressed:
1
1 Is a site plan included that indicates the distance of the proposed building or
addition to property lines, other buildings, set back easements and utility
easements?
Yes ?C No ,q Not necessary for this project (2)
2. Does the site plan include the location of the I.S.D.S. (Individual Sewage
Disposal System) and the distances to property lines, wells (on subject
property and adjacent properties) , streams or watercourses?
Yes No oi Not necessary for this project (2)
3. Does the site plan indicate the location and direction of the County or private road
accessing the property?
Yes X No 0) Not necessary for this project (2)
4. Do the plans include a foundation plan indicating the size, location and spacing of
all reinforcing steel in accordance with the uniform building code or per stamped
engineered design?
Yes ?( No (1) Not necessary for this project (2)
5. Do the plans indicate the location and size of ventilation openings for under floor
crawl spaces and the clearances required between wood and earth?
Yes No (1) Not necessary for this project (2)
6. Do the plans indicate the size an location of ventilation openings for the attic, roof
joist spaces and soffits?
Yes No (1) Not necessary for this project (2)
7. Do the plans include design loads as required under the Uniform Building code for
roof snow Toads, (a minimum of 40 pounds .per square foot in Garfield County) floor
loads and wind Toads?
Yes No (1) Not necessary for this project (2)
8. Does the plan include a building section drawing indicating foundation, wall, floor
and roof construction?
Yes No (1) Not necessary for this project (2)
9. Does the building section drawing include size and spacing of floor joists, wall
studs, ceiling joists, roof rafters or joists or trusses?
Yes No (1) Not necessary for this project (2)
10. Does the building section drawing or other detail include the method of positive
connection of all columns and beams?
Yes No (1) Not necessary for this project c2�
2
1 1. Does the plan indicate the height of the building or proposed addition from the
highest point of the building or addition measured at mid span between the ridge
and the eave down to existing grade contours?
Yes No _ (+) Not necessary for this project (2)
1?. Does the plan include any stove or zero clearance fireplace planned for installation
including make and model and Colorado Phase II certifications or phase 11 EPA
certification ?
Yes No (1) Not necessary for this project (2)
13. Does the plan include a masonry fireplace including a fireplace section indicating
design to comply with the Uniform Building Code Chapter 37?
Yes No _ (1) Not necessary for this project (2)
' 4. Does the plan include a window schedule or other verification that egress/rescue
windows from sleeping rooms and/or basements comply with the requirements of
the Uniform Building Code?
Yes No _ (1) Not necessary for this project (2)
15. Does the plan include a window schedule or other verification that windows provide
natural light and ventilation for all habitable rooms?
Yes No (n Not necessary for this project (2)
16. Do the plans indicate the location of glazing subject to human impact such as glass
doors, glazing immediately adjacent to such doors; glazing adjacent to any surface
normally used as a walking sF irface; sliding glass doors; fixed glass panels; shower
doors and tub enclosures and specify safety glazing for these areas?
Yes No (1) Not necessary for this project (2)
17. is the location of all natural and liquid petroleum gas furnaces, boilers and water
heaters indicated on the plan?
Yes No (1) Not necessary for this project (2)
18 Do you understand that if you belong to a homeowners association, it is your
responsibility to obtain written permission from that association, if required by that
association, prior to submitting an application for a building permit?
Yes No (I) Not necessary for this project (2)
19. Will this be the only residential structure on the parcel?
Yes DC No If No -Explain
3
20. Have two (2) complete sets of constructions drawings been submitted with the
appli!;ation?
Yes No (1) No necw nary for this project (2)
21. Is this an application for the placement c a manufactured home?
Yes ic. No
If yes, have you specified the size of i'ie unit (min. 20ft x 20ft); live roof Toad
(min.40#); wind design (min. wind speed f 80 mph & 15 Ib. wind load); foundation
design; method of anchoring?
Yes X No (1) Hot nece, sary for this project (2)
?. Have you designed or had this plan desk tied while considering building and other
construction code requirements?
Yes ,C No (3)
3. Does the plan accurately indicate what ye i intend to construct and what will receive
a final inspection by the Garfield l3uildin !Department?
Yes )C No (3)
4. Do you understand that approval for lesign and/or construction changes are
required prior to the application of thesF changes?
Yes \C No (3)
25. Do you understand that the Building D( oartment will collect a "Plan Review" fee
from you at the time of applicatioii and tl at you will be required to pay the "Permit
Fee" as well as any "School impact" or "peptic system " fees required, at the time
you pick up your building permit?
Yes A No (3)
26. Are you aware that twenty four (24) hoR'r notice is required for all inspections?
Inspections will be made from Battlement Mesa to West Glenwood in the
mornings and from Glenwoo<t Springs to Carbondale in the afternoon.
Morning inspections must be ci fled in by 12:00 p.m. the day before; afternoon
inspections must be called in t,y 5:00 p.m. the day before . Failure to give 24
hour notice for inspections will delay your inspection one (1) day.
Yes )c No
27. Are you aware that you are required to call for all inspections required under the
Uniform Building Code including approval on a final inspection prior to receiving a
Certificate of Occupancy and oct upancy of the building?
Yes X No (3)
4
28. Are yn, i aware that the person signiTilg the Permit Application whether the "Owner",
"Agent of the Owner", "General Contractor", "Contractor" or otherwise, signing the
application is the party responsil ale for the project complying with the Uniform
Codes"
Yes / No (3)
I hereby acknowledge that I have react, understand and answered these questions
accurately to the best of my ability.
4;1
sign ore 1-4-16,) jr
d
ateV
13
,1
Phone: q "`'`ill (days); (3'9 3 - (ifil! 1q (evenings)
Project Name: 6, 1 -%��"
Project Address:
Notes:
4�1 ie1 £5h5
(1) If you have a'.,wered "No" on any of these questions } )u may be required to provide this information at the request of the Building
Official prior t beginning the plan review process Del ' ys in Issuing the permit ail to be expected. Work may not proceed without
the issuance ^f the permit.
(2) If yoI have answered "Nat necessary for this project" on any of the questions and it is determined by the Building Official that the
information is necessary to review the application ar,d plans to determine minimum compliance with the adopted codes, please
expect the following:
A. The application may be placed behind n ore recent applications for building permits in the review process and not
reviewed until required information has b' en provided and the application rotates again to first position for review.
B Delay in issuance of the permit.
C. Delay in proceeding with construction.
(3) If you answei ed "No" to this question the circumstance : described in the question could result in a "Stop Work Order" being issued
or a "Certificate of Occupancy not being issued.
PerApp02.95 Effective August 15, 1995
5
E;ecorded,,:, ' o'clock M ,
Reception No Recorder
WARRANTY DEED
THIS DEED, made this , �d day of Jan Jett- 3
Je Jf PARkEP\ A k A iii' r. i, PEAe4.4---
of the t County of 0 cs c• l 4. ill
Ccy (t)rfiAO , grantor(s) and
Aav U 1,.. LL—
between
,1953,
and State of
whose legal address is / CD f S Z
Po 60;.; z 21, C A g 60P0 [�/
of the County of 6„1/e.-0
WITNESS, that the grantor(s), for and in consideration of the sum of
Gtth d Val u mac. (?pit S 1 ctereth air
the receipt and sufficiency of which is hereby acknowledged, hal
docs grant, bargain, sell, convey and confirm, unto the grantee(s),
together with improvements, if any, situate, lying and being in the
State of Colorado, described as follows:
L04 2 eiotk Asee., Cr s44 Klv6rz_
DA PT
and State of CO iG
Teu dot( arc, 0-44-ct Of/j«-5 0°4
, grantee(s):
DOLLARS,
granted, bargained, sold and conveyed, and by these presents
res heirs and assigns forever, all the real property,
County of 6c, rc.. %P
also known by street and number as: ,v/A
assessor's schedule or parcel number: AL/6. 3 - 02 1 ' D Z -02,Z
TOGETHER with all and singular the hereditaments and appurtenances thereto belonging, or in anywise appertaining, the reversion
and reversions, remainder and remainders, rents, issues and profits thereof, and all the estate, right, title, interest, claim and demand
whatsoever of the grantor(s), either in law or equity, of, in and to the above bargained premises, with the hereditaments and appurtenances;
TO HAVE AND TO L-IOLD the said premises above bargained and described, with the appurtenances, unto the grantee(s),
heirs and assigns forever. The grantor(s), for /1i.4 /11An. sel /-1 s heirs and personal representatives. do
covenant, grant. bargain and agree to and with the grantee(s), heirs and assigns, that at the time of the ensealing and
delivery of these presents, 7i ee k rc- well seized of the premises above conveyed, have.- good, sure, perfect, absolute and
indefeasible estate of inheritance. in law. in fec simple. and ha v. good right, full power and authority to grant, bargain, sell and convey
the same in mariner and form as aforesaid, and that the same are free and clear from all former and other grants, bargains, sales, liens, taxes,
assessments. encumbrances and restrictions of whatever kind or nature soever, except N :u- -
The grantor(s) shall and will WARRANT AND FOREVER DEFEND the above bargained premises in the quiet and peaceable posses-
sion of the grantee(s), 1Ts heirs and assigns, against all and every person or persons lawfully claiming the whole or any part
thereof.
IN WIT ES I', the grantor(s) ha 5' executed this deed on the date set forth above.
.44K PAQtc5R,
BILA JEFFEE W1+IPPI.P ppie ffg
STATE OF COLORADO
County of GCS et 01
ss.
The foregoing instrument was acknowledged before me this V KA day of J ,
LI& R2A, bye RkR Je cr 'res Wk.pr,k, Phirvv/
Witness my hand and official seal.
by
`If in Denver, insert "City and".
My commission expires: OE,1 I- j 91
Name and Address or Person Creating Newly Created Legal Description (§ 38-35-106.5,
No. 932. Rev. 4-94.
ee+(,uvir, to: tBucca(a ea e t LLC
WARRANTY DEED (For Photographic Record) PC$ �1 Z7
Bradford Publishing, 1743 Wazec St., Denver, CO 80202 — (303) 292- 500 — l0-96
ecZr bOnr G.(z., Co Puo23
N
ILDIN
k
Job Addres
Owner
Assessor's Parcel No
&rf-02 Date *3/9?
PERMIT CARD
Contractor
Setbacks: Frons
CVL
Soils 1L s1
Footing
Foundation
Grout
Underground Plumbing
Rough Plumbing
Framing
Insulation
Roofing
Drywall
Gas Piping
AtraZ( 40467A,
a P44.3
Addressrt /(b 816 `5 Phone #94/7_ 5i? y
Addres/0 41:1-9 d1one #qW5
Rear
RH
INSPECTIONS
LH
Zoning
Weatherproofing
Mechanical
Electrical Rough (State)
Electrical Final (State)
Final /Checklist Completed?
Certificate Occupancy #
Date
Septic System # c
Date 02/13/U
Final
Other
CO" cd-ot 44.4414.
(continue on back)
August 20, 2001
Jeffrey W. Parker
Buffalo Ranch LLC
P O Box 3463
Boulder, Co 80307
Mr. Parker,
Garfield County
BUILDING & PLANNING DEPARTMENT
Code Compliance Office
shackett@garfield-cou nty.com
Please refer to your previous correspondence with this office concerning expiration of your
building and septic system permits as listed on the accompanying letter.
The provisions of Uniform Building Code, section 106.4.4, do not allow us to renew these
permits. They are hereby all canceled. Should you wish to proceed with the work in the future,
new permits will be required.
Yours truly,
edekf_
tve aett '
Compliance Officer
109 8th Street, Suite 303, Glenwood Springs, Colorado 81601
(970) 945-8212 (970) 285-7972 Fax: (970) 384-3470
Andrew Schwaller
Garfield County Building & Planning Dept.
109 8th street, Suite 303
Glenwood Springs, CO 81601
June 22, 2001
Re: Building permit #'s 6614, 6615, 6616; Septic permit #'s 2912, 2913, 2914
Dear Mr. Schwaller:
RECEIVED JUN 2 ? 2001
PO Box 3463
Boulder, Co 80307
(303) 265-9191
1 appreciate your letter of 5/25/01 about the above referenced building and septic permits. 1 can
assure you that while there have been some difficulties in regards to completion of the project,
we do intend to complete the job as outlined.
The work has been ongoing but limited due to legal problems related to accessing the sites of the
permitted work. However, we do expect the work to be completed, barring further problems,
within the next 180 days.
Please be so kind as to extend the above permits for 180 days so that we can have the work
inspected and finished while access issues are formalized. Please feel free to call the attorney for
Buffalo Ranch LLC, Mr. Seibert, at (970) 259-8366 if you need any further information.
Thank you very much for your attention to this matter.
Sincerely,
W. Parker
Buffalo Ranch LLC