HomeMy WebLinkAboutOWTS Installation Observations 03.19.17
March 19, 2017 Project No. C1185
David Dodson
ddodson@rof.net
Onsite Wastewater Treatment System (OWTS) Installation Observations
Van Rand Park Owner’s Association
Garfield County, Colorado
Permit Number SEPT-05-16-4209
David,
ALL SERVICE septic, LLC observed the installation of the onsite wastewater treatment system (OW TS)
on February 8, 9, 13, 16, 22, and March 1, 2017 for the subject property. Excavation Services installed
the system.
The existing septic tanks were pumped and removed. The existing soil treatment area (STA) was over-
excavated in the area of the new seepage pit. Any additional STA outside of the new seepage pit was
abandoned in place.
The new OWTS was placed in the designated easement on Lot 10 of the Van Rand Park Subdivision.
The easement measures 57-feet (east and west) and 75-feet (north and south). The new OWTS
consists of a 48-inch diameter vault with a man-way for access. Duplexing 1 horsepower, 230 volt
Meyers grinder pumps were installed in the vault. A control panel with an audible and visual alarm was
installed within line of sight of the pump vault. The alarm system also has an auto-dialer in the case of an
alarm to call Dodson Engineered Products. We also tested the alarm at the time of the inspection. The
pumping system has a counter system in order to track pump cycles. This system will assist in tracking
the amount of wastewater entering the OWTS.
Wastewater is pumped up to a 2000-gallon, single-compartment septic tank. Effluent gravity flows to an
additional 2000-gallon, two-compartment septic tank with an effluent filter on the outlet tee. From the
septic tanks, effluent gravity flows to a distribution box, which is accessible from grade. Speed Levelers
were installed on the sewer pipes exiting the distribution box to assure equal distribution.
The OWTS is subject to heavy machine traffic. All OWTS components are traffic rated. All
connecting piping is Schedule 80.
Excavation for the seepage pit was 35-feet long (east and west), 18-feet wide (north and south), and 12-
feet deep below the inlet pipes. The bottom of the excavation was filled with 6-inches of ¾-inch
diameter cleaned screened rock. Three 4-foot diameter perforated manhole rings were equally
distributed within the seepage pit excavation. Manhole rings were surrounded by ¾-inch diameter
cleaned screened rock, compacted in 2-foot lifts with a vibratory plate compactor.
Cast iron extensions and cast iron lids were utilized to bring the manhole rings of the seepage pit to
grade for access. HP-Kumar tested the compaction over the seepage pit. Their report is enclosed.
Below is a recap of each inspection and the scope of work completed at each stage of construction:
• February 8, 2017 8:15am – Observed excavation to final depth through contaminated soils. Total
hole was 30-inches greater in length than specified due to the thickness of manhole rings (5-
inches each side of ring). Contaminated soils were hauled to South Canyon Landfill.
• February 8, 2017 1:30pm – 6-inches of gravel had been placed on the bottom of the excavation.
• February 9, 2017 – Two manhole rings had been placed in the seepage pit. Removal of
contaminated material was still in progress.
• February 13, 2017 – Cover was placed over seepage pit. The distribution had been installed.
Septic tanks were set. HP-Kumar had tested compaction over seepage pit.
• February 16, 2017 – The old septic tanks were being pumped and removed.
• February 22, 2017 – Plumbing was installed in the septic tanks.
• March 1, 2017 – Controls for the solids handling pump were installed. Observed flow equalizers
in distribution box. The audible and visual alarm was tested and found to be functional.
We have estimated an average of wastewater flow of 1000 gallons/day. Continued water meter
readings are required to assure the OWTS does not exceed the maximum design flow of 1000
gallons/day. If 1000 gallons/day is reached, the OWTS is not designed to handle excess flow and
Garfield County must be notified.
The OWTS was generally installed according to specifications. This observation is not a guarantee of
workmanship and/or parts and materials. ALL SERVICE septic, LLC should be notified if changes are
made to the OWTS in the future. Any additional OWTS construction must be according to the county
regulations.
LIMITS: Observations are limited to components that are visible at the time of the inspection. The installer must
have documented and demonstrated knowledge of the requirements and regulations of the county in
which they are working. The quality of the installation is dependent of the expertise of the installer, soil
type, and weather conditions.
Please call with questions.
Sincerely,
ALL SERVICE septic, LLC Reviewed By:
Carla Ostberg, MPH, REHS Richard H. Petz, P.E.
Beginning of excavation
Encountering contaminated material
Manhole rings
Gravel for seepage pit
Removing contaminated material
Placement of manhole rings
Gravel surrounding manhole rings
Cast iron manhole lids access to manholes
Distribution box with traffic rated riser
D-box plumbed
Tanks being set
Cover over the seepage pit
Old septic tanks removed Old pump chamber
Tanks and distribution box Access to grinder pumping system
Access to pump chamber
Alarm system for grinder pump
Distribution box with flow equalizers
Note Schedule 80 pipes
N
~
I
O' 10' 20'
Scale: 1" = 20'-0"
LOT 9
s oo·oo·oo" E
15.89'
INCOMING
[
SEWER
LINES FROM
I BUSINESSES
2000-LLON,
SINGLE-OMPARTMENT,
CONCRET SEPTIC TANK
WITH H20 RA ED LID
EASEMENT STAKE ON
FENCE
33 Four Wheel Drive Road
Carbondale, Colorado 81623
Phone 970.309.5259
carla@allserviceseptic.com
---
·, 4. ·. <1 •• 4 ..
"\.i:I . <I
<!.
"' .. 4 ... :
.<I:
-.;: . .
" <I •• <! 4 ~·· .. ., .. 44
<I .
'\· •• <I·.
~··
4.
LOT 10
.---35' x 18' x 12' DEEP SEEPAGE
PIT WITH 4' DIA PERFORATED
CONCRETE RINGS
_,__..--r-----4" DIASCH-80 PVC PIPE
(MIN 1% SLOPE TO PIT)
DISTRIB ION BOX TO
GRA WITH TRAFFIC
ED RISER AND CAST
.....__-----Al"('ON MANHOLE LID
____ ...,,.....__4" DIA SCH-80 PVC PIPE
(MIN 1% SLOPE TOD-BOX)
4" DIA SCH-80 PVC PIPE
(MIN 1% SLOPE TO TANK)
~
CD RECORD DRAWIN,G_ ~~JH COMPONENTS
Date: 03/19/17
~·.·
Van Rand Park Owner's Association
Lots 1-11, Van Rand Park
Garfield County, Colorado Designed By: CBO ecord 1
Reviewed By: RHP
Project Number: C1185 Drawn By: ANG Sheet 1 of 1
N
~
I I
O' 10' 20'
Scale: 1" = 20'-0"
\
LOT 9
s oo·oo·oo" E
15.89'
EASEMENT STAKE ON
FENCE
33 Four Wheel Drive Road
Carbondale, Colorado 81623
Phone 970.309.5259
carla@allserviceseptic.com
---
p
/":. ', ~ <"' .~ ..... ;.>
d. ·.ll .,, : ~·· .. 4 ...... ···~
LOT 10
~--
'\. <!". 4 '\. .4· .. ;. :4~
·~·.· .· 4 .. ·. "'.4". .;,
"\ • _45 • • • 4. :"'
·"' ~ .· ·.· ~· ~ '\·~."'·. i(J.. 4. . """ . .d. ~ . ·4 .. -"
'\" ·.".. .<! ·. 4.l:
. " 4 .. ·. . 4. . . _..q 4.
'4l . .,
. . 4.
"\ "': .. ·.4 .· .. 4
'· 'Z_··.,
4 4 .
"'-". ··:., '4
'\.
CD RECORD DRAWIN,G_ ~IJH MEASUREMENTS
Van Rand Park Owner's Association
Lots 1-11, Van Rand Park
Garfield County, Colorado
Project Number: C1185
Date: 03/19/17
Designed By: CBO ecord
Reviewed By: RHP
Drawn By: ANG Sheet 1 of 2
H-P~KUMAR 5020 County Road 154
Glenwood Springs, CO 81601
Geoteclmical Eng1neenng I Engineering Geology Phone : (970) 945-7988
Materials Testing I Environmental Fax: (970) 945-8454
Email: bQkglenwood@kumarusa .com
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado --------
Earthwork Compaction Testing Report
Client: Excavation Services Project No.: 17-7-165 Day: Monday
Attn: Justin Nunn Date: 2/13/17
P.O. Box 1159 Report No.: 1 Page: 1 of 1
Carbondale, Colorado 81623
Project: Van Rand Industrial Park Leach Field Compaction Testing, 7150 Highway 82, Glenwood
Springs, Colorado
Weather: Partly cloudy, calm, rain overnight Temperature: 40° at 9 :30 am
Earthwork Contractor: Excavation Services
Equipment Used: Dual smooth drum roller
Description of Earthwork Compaction tests were performed on 3/4" base course used as drywell backfill.
Tested : Tests 1and3 indicated unacceptable compaction and about 2% above
optimum moisture content. Test 2 indicated acceptable compaction and about
1 % above optimum moisture content. Proctor on file from material source was
referenced.
Verbal Communication: Mike Buster with Excavation Services was informed of our test results. As
discussed, we will re-test areas of Tests 1 and 3 after they have been dried and
reworked.
Placement and Compaction Procedure: Not observed by H-P/Kumar
Lift Thickness: Max. Rock Size: Moisture
Conditioning :
Comoactor(s) Used: Number of Passes:
Nuclear Gauge Moisture/Density Test Results
Location Field Dry Field Field Min.
Test Depth or Density Moisture Comp. Comp. Proctor
No . Elev. (pcf) Content (%) Req. Lab No.
% (%)
1 7' E. of S. drywell subgrade 126.0 10.6 94 98 074-16
2 4' W. of middle drywell subgrade 130.8 9.2 98 98 074-16
3 5' E. of N. drywell subgrade 126.9 9.9 95 98 074-16
Proctor Sample Reference:
Lab No. Method Description Max. Dry Opt.
Dens .(%) Moist.(%)
074-16 (Job #115181A) ASTM D 698 %" Aaar egate Base Course WSM Pit 134.1 8.2
THIS REPORT PRESENTS OPINIONS AS A RESIA. T OF OUR 08SERVATIONSOF FILL PLACEMENT. WE HAVE RELIED ON THE CONTRACTOR TO CONT INUE APPL YING THE RECOMMENDED
COMPACTIVE EFFORT ANO MOISTURE TO FILL DURING THE TI MES WHEN OUR OBSERVER IS NOT OBSERVING OPERATIONS.
THE NUCLEAR DENSOMETER METHOD OF TESTING WAS USED IN SUBSTANTIAL ACCORDANCE WITH ASTM D 6938
Distribution :
Excavation Services -Justin Nunn (justin@excavationservices.biz)
/ljf
Chris Newberry Thomas J. Westhoff, CET
Field Technician Reviewed By
H-P~KUMAR 5020 County Road 154
Glenwood Springs, CO 81601
Geotechnical Engineering Engineering Geology Phone: (970) 945-7988
Materials Tes1111g I Environmental Fax: (970) 945-8454
Email: hQkglenwood@kumarusa.com
---
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado -
Earthwork Compaction Testing Report
Client: Excavation Services Project No.: 17-7-165 Day: Thursday
Attn: Justin Nunn Date : 2/16/17
P.O . Box 1159 Report No.: 2 Page : 1 of 1
Carbondale, Colorado 81623
Project: Van Rand Industrial Park Leach Field Compaction Testing, 7150 Highway 82, Glenwood
Springs, Colorado
Weather: Clear, calm, dry Temperature : 50° at 10:30 am
Earthwork Contractor: Excavation Services
Equipment Used : Dual smooth drum roller
Description of Earthwork Compaction re-tests were performed on drywell backfill. All re-tests indicated
Tested : acceptable compaction and near optimum moisture content.
Verbal Communication: Mike Buster with Excavation Services was informed of our test results.
Placement and Compaction Procedure: Not observed by H-P/Kumar
Lift Thickness: Max. Rock S ize: Moisture
Conditioning:
Compactor(s ) Used: Number of Passes :
Nuclear Gau g e Moisture/Density Test Results
Location Field Dry Field Field Min.
Test Depth or Density Moisture Comp. Comp. Proctor
No. Elev. (pcf) Content (%) Req . Lab No.
% (%)
1A Re-test of 1 from 02-13-17, subgrade 134.3 6.4 100 98 074-16 7' E. of S. d rvwell
3A Re-test of 3 from 2-13-17, subgrade 130.9 6.9 98 98 074-16 5' E. of N. drvwell
Proctor Samp le Reference:
Lab No. Method Description Max. Dry Opt.
Dens .(%) Moist.(%)
074-16 (Job #115181A) ASTM D 698 %" Aaaregate Base Course, WSM Pit 134.1 8.2
THIS REPORT PRESENTS OPI NIONS AS A RESULT OF OUR OBSERVATIONSOF FIU PLACEMENT, WE HAVE RELI ED ON THE CONTRACTOR TO CONT INUE APPi. YING THE RECOMMENDED
CO MPACTIVE EFFORT ANO MOISTURE TO FILL DURING THE TI MES WHEN OUR OBSERVER IS NOT OBSERVING OPERATIONS,
THE NUCLEAR DENSOMETER METHOD OF TESTING WAS USED IN SUBSTANTIAL ACCORDANCE WITH ASTM 0 6938.
Distribution:
Excavation Services -Justin Nunn (justin@excavationservices.biz)
/ljf
Chris Newber!l Thomas J. Westhoff, CET
Field Technician Reviewed By
832‐R‐13‐002
Do Your Part, Be SepticSmart:
The Do's and Don'ts of Your Septic System
Learn these simple steps to protect your home, health, envi r onment and property value:
u*'*"#Mbe1Wt+t+
sept1csmart"
U.S. Environmental Protect ion Ag ency
P.r.otect It and Inspect It:
Do:
• Have your system inspected (in general) every three years by a licensed contractor
and have the tank pumped, when necessary, generally every three to five years.
Don't:
• Pour cooking grease or oil down the
sink or toilet.
• Rinse coffee grounds into the sink.
• Pour household chemicals down the
Do:
• Eliminate or limit the use of a garbage
disposal.
• Properly dispose of coffee grounds &
food.
sink or flush them . • Put grease in a container to harden
before discarding in the trash.
• Flush non -degradable products or • Dispose of these items in the trash can!
chemicals, such as feminine hygiene
products, condoms, dental floss,
diapers, cigarette butts, cat litter, paper
towels, pharmaceuticals.
Don't:
• Park or drive on your drainfield. The
weight can damage the drain lines.
• Plant trees or shrubs too close to your
drainfield, roots can grow into your
system and clog it.
Don't
• Concentrate your water use by using
your dishwasher, shower, washing
machine, and toilet at the same time.
All that extra water can really strain
your septic system .
Do:
• Consult a septic service professional to
advise you of the proper distance for
planting trees and shrubs, depending on
your septic tank location.
Do:
• Stagger the use of water-generating
appliances. This can be helpful
especially if your system has not been
pumped in a long time.
• Become more water efficient by fixing
plumbing leaks and consider installing
bathroom and kitchen faucet aerators
and water-efficient products.