HomeMy WebLinkAboutMethod of ProceduresCRU¿ www.CRWcolorado.com April26,2017 Holy Cross Energy Administration Building 2At7 Re-Roof Method of Procedures Objective Execute roof replacement project per contract & Division 7 Design roof project with minimal to no negative impact on Holy Cross operations & in a safe, professional, and timely rn¿tnner. Project milestones of hig:h importance 1. Re-roof operations- May 15t;'- .Iune 16ft (with no rain days) 2. Microwave dish shutdown/ re-activation- May 15- June 9 3. SKM interior work- intermittent 4. Close out procedure- D7 Design & Building Department final inspection upon completion þunch list Items to be corrected at time of inspection) Junel2-16 5. Close out documents submitted within 10 days of final completion 6. Manufacturers inspection- 30-45 days following final completion Project schedule IN'{ay 8-t2 Set exterior stair access & fencing Forklift delivery Toilet delivery Material delivery Inventory materials Request microwave dish shutdown for May 15th Preconstruction meeting Commence Start of project May 15 May 15-19 Reioof from tidgelkle loyrard Westdf-ains SKM access doors interior install l|i/:ay 22 SKM Mechanical West drain reset/ relocate NIay 22-26 Complete Yfiest half of roof 1000/o May 29'-IweZ Re-ryqof frrys¡ $dgelir*e foward Eastdiains June 5 SKM Mechanical drainreset/ relocate East drains June S-June 9 Complete East half of roof 100% June 12-Jr,lae 1,6 Final inpþectïcRs & þ.unchl?st DY & 'Garfield County Close out document preparation July Carlisle Inspection Piojcct D.qscriirtion Roofing- Carlisle 90 Mil EPDM Fully adhered roof system ¡ Tear off existing roof membrane, leaving base insulation in place. r Perforate existing foil faced Polyiso 1" X 1" . Rurnove and dispose of existing Cîickets.r lo.stall Tz" Plywoc¡d af ìnside of paraþeÍ walls, tißd?'Plywood wi'tb 1"x2" shim sloped toward roof on top capo Install new crickets per taper drawing. Install new drain SS sumps.¡ Add 2" insulation mèchariically fastãned (32) per board at Corners (24) per baard at 12' Perimeter (16) per board in Eield? Adhere %" Seeutrshield HD FR e'cvsrbcæd with FAST Adheeive: (4" OC) at 12'){ 12' Corners (6" OC) at 12' perimeter and Field . Fully Adhere 90mil EPDM with 6" FAT tape directly to coverboard with standard bonding adhesive. Lay out sheets with no seams in the sump area. EPDM seams to be stripped in using 6" PS overlaymørt 'St¡iPo Install new Carlisle Securedge 2000 mansard brown 7" fascia system with factory fabricated radius comerso After complete installation, provide owner with a 2-Year'Workmanshio Guarantee and a 30- Year manufacturer's. NDlV/arranty with up to 70mph v¡ind ooveïage including edge metal FlumbirB- By Stornn King Mechanical r Relocate (2) Overflow drains¡ Remove and reset (2) main drains with deck plates as needed¡ Overflow drains will be installed outside of sump area, a 5" hole shall be drill'in roof deckÌng (on higþ web) and'useurr*derdeck ctamp and pþw.qod to'seotre drain at correct height. l InstaTl unistrut support system underneath roof draín locations as needed or required . Replace all plastic roof drain domes with cast iron domes r Remove sheet rock for access panels to drains at @) locations and replace'rñ/ith {4) 24*x2;4" fi¡e rated.,å}cÊêss.door (I|{IFAB MRFU2424) uninsulated, Fatch sheetrock if necessary, painting is no.t included-. r Insulate roof drain cast iron píping as needeci. Roof draïns wiil not be insulated as per plans. Please note insulation will be for new work only and will not include existing piping. o Remove (1) exhaust vent and cap at roof, verify with maintenance for e lectric al tenr,lination, . Cap ,dnain and,sonduct fLow,test 'd¡ains 'wifh roofing,contrøctor. Noted Items of hieh importance Þ Re-roof efforts in work area will be substantially completed daily Þ Overnight tie-inn will be,achier¡ed'daily Þ Materials will be covered and secr*red nrghtly whe$her o¡r growrd or roof. > All materials will be on site prior to start, and West half of roof.l00% comoletion will be siven oriòritv to ensure Microwave shutdown does'not exceed tim"e franäe alloited (We would request fulI 30 dav's shutdown in hopes of being as far away as possib,lei or substantialfy complefe before starhrp) Þ Chain link fence will be provided around stored materials on sround and around exterior stairãccess (Locked with key provided toÏoly Cross) Þ G,oqUnd cones & wa'rning lines will be usçd to restrict,au;to$obile and foot traffic in work area (Leaving employee entreinoe open) Þ Growid flagger will be used at all tirucs when fork lift is in use Þ Perimeter flagging and fall protection will be used at all times Project s-chedule'm4y changedu.p'to weaths'r"changes in material delivery dafes¡ unforeseen roof conditions, equipment failure, etc. 'We understand that communication is paramount, and will update Division 7 DesigR daily of prog¡ess, challenggsr and any items needing. addressed. Contacts ZanePinnt CRW, Inc. - Project Manager o.970-241.-101'8 c. wa-270-3071 Zane(ù.crwroofins.com Isaac Redding CRW,Inc. -Foreman c.970-644-r303 isaac@crwroofinq.com Sarah funk CR1ry, fuc. - Office/ Bookkeeping o.720-348-0438 sarah@crwroofltng.com Keith Forney Storm King Mechanical c.970-989-0086 skmkeith@aol.com Dale Storm King Mechanical c.970489-0090 skmdale@aol.com We look forward to being p,art of makíng this project a success" Thank you, ZanePinnt CRW, Inc. - Proj'ect Manager 2310 S. Raritan Street. Englewood . CO ¡ 80110 .T (7201 348-0438 , F {72A]. 348-0431