HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-05-17-4725
Wayne Rudd
Commercial Tenant Improvements: Installation of Spray Paint Booth
Midland Exemption, Parcel B — Units G3 & G4
62 County Road 113 (Cattle Creek Road)
Glenwood Springs, Colorado
1) NEW WORK RELATED TO PROPOSED TENANT IMPROVEMENTS SHALL COMPLY WITH THE
FOLLOWING BUILDING CODES: 2015 IBC, IMC, IPC, IFGC AND 2009 IFC, IECC.
2) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS AND
INSPECTIONS POLICY.
3) ALL WORK TO COMPLY WITH "COMMERCIAL LIMITED" ZONE DISTRICT REGULATIONS PER
GARFIELD COUNTY'S LAND USE & DEVELOPMENT CODE.
4) EXISTING TENANT SPACE AND SURROUNDING BUILDING WERE PREVIOUSLY APPROVED AS
TYPE II -B CONSTRUCTION WITH FIRE SPRINKLERS, OCCUPANCY GROUP F-1 (MODERATE -
HAZARD FACTORY INDUSTRIAL). MAXIMUM ALLOWABLE QUANTITIES OF HAZARDOUS
MATERIALS ARE LISTED IN TABLE 307.1(1).
5) NEW PRE -FABRICATED SPRAY BOOTH & ADJACENT AREAS WITHIN THE TENANT SPACE
SHALL COMPLY WITH I.B.C., SECTION 416, I.F.C., SECTIONS 1504.3.2.1 THROUGH 1504.3.2.6,
SECTIONS 1504.4 THROUGH 1504.8, AND NFPA 33.
6) INSTALLATION OF SPRAY BOOTH SHALL COMPLY WITH MANUFACTURER'S SPECIFICATIONS
& REQUIREMENTS.
7) AN AUTOMATIC FIRE SPRINKLER SYSTEM OR FIRE EXTINGUISHER SYSTEM SHALL BE
PROVIDED AND SHALL BE INSTALLED IN ACCORDANCE WITH I.B.C., CHAPTER 9.
8) APPLICANT RESPONSIBLE TO CONTACT LOCAL FIRE DISTRICT FOR PERTINENT I.F.C. AND FIRE
SPRINKLER REQUIREMENTS FOR SPRAY BOOTH INSTALLATION INCLUDING ALTERATIONS TO
EXISTING FIRE ALARM AND/OR FIRE SPRINKLER SYSTEMS. FIRE DISTRICT SHALL CONDUCT
ROUGH -IN AND FINAL INSPECTIONS, AND FINAL APPROVAL REPORT IS REQUIRED PRIOR TO
FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.
9) MECHANICAL VENTILATION AND INTERLOCKS WITH THE SPRAYING OPERATION SHALL BE IN
ACCORDANCE WITH 2015 I.M.C. AND 2009 I.E.C.C., SECTION 503. MECHANICAL ROUGH -IN
INSPECTION REQUIRED PRIOR TO FRAME INSPECTION.
10) ELECTRICAL PERMITTING AND INSPECTIONS BY COLORADO STATE ELECTRICAL BOARD.
ELECTRICAL ROUGH -IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL FINAL
APPROVAL IS REQUIRED FOR FINAL INSPECTION & CERTIFICATE OF OCCUPANCY.