HomeMy WebLinkAbout1.22 Article 78) Sections addressing Article 7, Divisions 1, 2 and 3 as applicable
ARTICLE 7
Pro -Gas is requesting a Limited Impact Review for Bulk Sales of LPG for a 0.69 acre
parcel located in Travelers Highlands Subdivision an industrial subdivision, located south
and west of the town of Parachute along Interstate 70.
Pro -Gas desires to install a propane (Liquid Petroleum Gas) storage and distribution
facility, known in the industry as a "Bulk Plant" at the tax parcel 2409-284-01-009. The
location is shown on the air photo below.
PROPOSED SITE CONDITIONS:
Pro Gas LLC is a company that provides propane to commercial and residential
customers. Their main operations are located in Loma, Colorado and with a growing
demand for propane delivery services in Garfield County, purchased the 0.69 -acre
property in the Travelers Highland Subdivision to install a 30,000 -gallon propane and
tank storage area for their residential and commercial propane customers. The facility
would not be open to the public and there are no sales of propane that would occur at
this location. Pro -Gas employees will access the site to fill their local service delivery
trucks and are routed out to FII propane tanks for their customers. The site will not be
manned and will not have any type of office. A copy of the proposed site plan for the
facility has been included as Attachment C to this report.
Pro Gas LLC indicates propane sales run seasonally with peak operations taking place
from December thru March. During this peak period, Pro Gas anticipated bulk tank will
be filled on a biweekly basis using a semi -truck and trailer (WB -50). Local deliveries by
Pro Gas to residential and commercial customers will occur on a daily basis using one
(1) bobtail type delivery truck accessing the site in morning hours to fill their service
truck.
TRAFFIC IMPACT ANALYSIS
Pro Gas LLC, estimates they would have a total of one (1) vehicle trips per day to the
facility. The trip will generally occur in the morning hours between 7:00 — 8:00 AM as
delivery trucks enter the facility to fill their delivery service truck then head out for
deliveries.
The hourly traffic volumes on Highway 6 & 24, according to the CDOT data, indicates
the peak hour traffic volume during the 7:00 — 8:00 period at 29 vehicles. Adding 1
additional trip to this state highway will have no impact on traffic operations.
A two-lane roadway with left turn lanes has a capacity of approximately 16,000 vehicles
per day. The CDOT 2016 ADT for State Highway 6 & 24 is 580 vehicles per day with
19% of the volume being heavy trucks. The 2037, the ADT increases to 1,366 vehicles.
Therefore, adding and additional one trip on this roadway will have an insignificant
increase in traffic volume and capacity.
The intersection of State Highway 6 & 24 and 4th Street/Stone Quarry Road was
upgraded in 2011 to include auxiliary lane and access radius improvements, all of which
meet current CDOT design standards, including provisions for heavy truck traffic trips.
A WB -50 vehicle turning template for the site has been modelled using AutoTURN v 7.0
software for the project site access locations on 4th Street and Scarrow Avenue. The
existing roadways can adequately accommodate the anticipated vehicles.
Pro Gas, LLC anticipates adding 2 ADT to Highway 6 & 24, which will have negligible
impact to the overall traffic operations and capacity. The existing access at Highway 6
& 24 meets current CDOT requirements for turning and axillary lane needs and no
modifications or changes are needed as a result of the proposed project.
Pro -Gas has received a letter of approval and support from the Parachute Rural Fire
District for this use at the site.
The site has been previously been utilized as a storage yard with a mixture of gravel
and asphalt millings for a driving and parking surface as shown in the air photo below.
The addition of the Pro Gas Bulk Propane facility will have little effect on the property or
the existing drainage of the property.
DIVISION 1
7-101 Zone District Use Regulations. The proposed use shall comply with Article 3, Zoning.
7-102 Comprehensive Plan and Intergovernmental Agreements. The proposed use is in general
conformance with the Garfield County Comprehensive Plan and there are no applicable
intergovernmental agreements. The subject property is located in an Industrial zone as
defined by the Comprehensive Plan. The proposed use is compatible with the industrial
and storage uses anticipated within this area.
7-103 Compatibility. The nature, scale, and intensity of the proposed use is compatible with the
adjacent industrial uses of this area.
7-104 Source of Water. The proposed use does not require water. Drivers shall have access to
bottled water. There is no current access to water at the site and there is no need for any water at
the site for the proposed use. Personnel will be spending minimal time at the site filling the
transports and drivers will have access to bottled water. Any water required for fire safety is
covered in the Fire Safety Analysis.
7-105 Central Water Distribution and Wastewater Systems. A central water distribution and a
wastewater system are not required for the proposed use. Personnel will
be spending minimal time at the site filling the transports.
7-106 Public Utilities. The subject property has adequate existing public utilities to serve the
proposed use. The Owner of the subject property will install a utility pole near the bulk tank for
electrical service. A transformer is located at the site.
7-107 Access and Roadways. The subject property has legal, physical and safe access to the
subdivisions interior roads. No additional road shall be required as there will be minimal daily
traffic to the subject site. Please see Traffic Study submitted.
7-108 Use of Land Subject to Natural Hazards. Applicant knows of no natural or geologic
hazards on the subject property that would hinder the proposed use.
7-109 Fire Protection. Adequate fire protection shall be provided pursuant to the Fire Safety
Analysis Manual for LP -Gas Storage Facilities and all State and Federal laws and regulations
applicable to the proposed use. State and Federal regulations require that there be no
combustible materials within 50 feet of the tank so there will be nothing within that area that
could be a fire hazard. The Parachute & Rural Fire Protection District has approved this site for
propane storage.
The First Safety Analysis Manual for LP -Gas Storage Facilities is included herein.
DIVISION 2
7-201 Agricultural Lands. Not applicable.
7-202 Wildlife Habitat Areas. The subject property is within a developed industrial subdivision .
There will be no further wildlife disturbance.
7-203 Protection of Waterbodies. There are no water bodies near the subject property.
7-204 Drainage and Erosion. The subject will be graded to provide a site for the propane tank
and a driveway. All weeds and debris will be removed. Erosion protection will be in place.
Please see Grading and Drainage Plan submitted with the Impact Analysis.
7-205 Environmental Quality. Air and water quality will be maintained pursuant to the
Operations and Maintenance Handbook for LP -Gas Bulk Storage Facilities, Pamphlet 58 and all
State and Federal laws and regulations applicable to the proposed use. If propane was to leak, it
disseminates and evaporates quickly in to the air. There would be no impact on air or water
quality. The Operations and Maintenance Handbook for LP -Gas Bulk Storage Facilities is
attached. One hard copy of Pamphlet 58 is included in this application.
7-206 Wildfire Hazards. The subject property is located in an area designated as "NR" on the
Wildland Fire Susceptibility Index Map and therefore these is no wildfire risk.
7-207 Natural and Geologic Hazards. Applicant knows of no natural or geologic hazards on the
subject property that would hinder the proposed use. Please see Soils analysis submitted with the
Impact Analysis
7-208 Reclamation. Not applicable. Any removal of the propane tank will be in accordance
with the Operations and Maintenance Handbook for LP -Gas Bulk Storage Facilities and
Pamphlet 58 and the property shall be returned to its original state.
DIVISION 3
7-301 Compatible Design. The design of the proposed use is compatible with the adjacent
industrial uses. See description above for 7-102 and 7-103.
7-302 Off -Street Parking and Loading Standards. The proposed use is not listed in Table 7-
302.A. The site design includes off load and access areas within the property for receiving and
distributing propane by truck. The site does not have any buildings or full time employees on the
site and the site is not open to the public.
7-303 Landscaping Standards. Not applicable. The proposed use is industrial.
7-304 Lighting Standards. Pamphlet 58 requires lighting to be available when necessary for
operations to occur. Applicant agrees that any lighting will be in compliance with the lighting
standards and will be low impact.
7-305 Snow Storage Standards. The subject has adequate room for snow storage on the property
should it be necessary.
7-306 Trail and Walkway Standards. Not applicable.
ARTICLE 7-1001
INDUSTRIAL USE
A. Residential Subdivisions. The subject property is not within a platted residential
subdivision or near any residential subdivision.
B. Setbacks. The subject property will follow the Operations and Maintenance Handbook
for LP -Gas Bulk Storage Facilities, which is 50 feet for a Bulk plant and 20 feet for the empty
smaller tanks.
C. Concealing and Screening. Applicant shall comply with any required concealing or
screening. Not proposing any as the property is zoned industrial and surrounded by industrial
uses.
D. Storing. The proposed use shall comply with the Operations and Maintenance Handbook
for LP -Gas Bulk Storage Facilities, Pamphlet 58 and all State and Federal laws and regulations
applicable to the proposed use.
E. Industrial Wastes. The proposed use shall comply with the Operations and Maintenance
Handbook for LP -Gas Bulk Storage Facilities and all State and Federal laws and regulations
applicable to the proposed use. If propane was to leak, it disseminates and evaporates quickly in
to the air and there is no requirement for containment.
F. Noise. The proposed use shall not create noise that will exceed the State noise standards.
G. Ground Vibration. The proposed use shall not create any ground vibration other than that
normally caused by buck traffic.
H. Hours of Operation. The proposed use will be utilized seven days a week generally
during normal business hours as described in the traffic estimates in the Request for Waiver from
Submittal of Traffic Study. It is possible that a tuck may be required to enter the site after hours
based on their CDL required rest times. It is also possible that Applicant's staff may be required
to access the site after hours to handle occasional delivery traffic or handle any complaints.
1. Interference, Nuisance, or Hazard. The proposed use shall not emit heat, glare, radiation,
or fumes that substantially interfere with the existing use of adjoining property or that constitutes
a public nuisance or hazard. The proposed use shall comply with the Operations and
Maintenance Handbook for LP -Gas Bulk Storage Facilities, Pamphlet 58 and all State and
Federal laws and regulations applicable to the proposed use.
FIRE SAFETY ANALYSIS MANUAL FOR LP — GAS STORAGE FACILITIES
http://www.nfpa.org/public-educationiby-topic/safety-in-the-home/gasoline-andpropane/
propane-safety/fire-safety-analysis-manual-for-lp-gas-storage-facilities
Link is to 2011 version. Hard copy of the 2014 version is available upon request.
OPERATIONS AND MAINTENANCE HANDBOOK FOR LP -GAS BULK STORAGE
FACILITIES
http://www.ncpcm.org/pdf/O&M%20HANDBOOK.pdf
Hard copy available upon request.
IMPACT ANALYSIS
Pro -Gas is requesting a Limited Impact Review for Bulk Sales of LPG for a 0.69 acre
parcel located in Travelers Highlands Subdivision an industrial subdivision, located south
and west of the town of Parachute along Interstate 70.
Pro -Gas desires to install a propane (Liquid Petroleum Gas) storage and distribution
facility, known in the industry as a "Bulk Plant" at the tax parcel 2409-284-01-009. The
location is shown on the air photo below.
PROPOSED SITE CONDITIONS:
Pro Gas LLC is a company that provides propane to commercial and residential
customers. Their main operations are located in Loma, Colorado and with a growing
demand for propane delivery services in Garfield County, purchased the 0.69 -acre
property in the Travelers Highland Subdivision to install a 30,000 -gallon propane and
tank storage area for their residential and commercial propane customers. The facility
would not be open to the public and there are no sales of propane that would occur at
this location. Pro -Gas employees will access the site to fill their local service delivery
trucks and are routed out to fill propane tanks for their customers. The site will not be
manned and will not have any type of office. A copy of the proposed site plan for the
facility has been included as Attachment C to this report.
Pro Gas LLC indicates propane sales run seasonally with peak operations taking place
from December thru March. During this peak period, Pro Gas anticipated bulk tank will
be filled on a biweekly basis using a semi -truck and trailer (WB -50). Local deliveries by
Pro Gas to residential and commercial customers will occur on a daily basis using one
(1) bobtail type delivery truck accessing the site in morning hours to fill their service
truck.
TRAFFIC IMPACT ANALYSIS
Pro Gas LLC, estimates they would have a total of one (1) vehicle trips per day to the
facility. The trip will generally occur in the morning hours between 7:00 — 8:00 AM as
delivery trucks enter the facility to fill their delivery service truck then head out for
deliveries.
The hourly traffic volumes on Highway 6 & 24, according to the CDOT data, indicates
the peak hour traffic volume during the 7:00 — 8:00 period at 29 vehicles. Adding 1
additional trip to this state highway will have no impact on traffic operations.
A two-lane roadway with left turn lanes has a capacity of approximately 16,000 vehicles
per day. The CDOT 2016 ADT for State Highway 6 & 24 is 580 vehicles per day with
19% of the volume being heavy trucks. The 2037, the ADT increases to 1,366 vehicles.
Therefore, adding and additional one trip on this roadway will have an insignificant
increase in traffic volume and capacity.
The intersection of State Highway 6 & 24 and 4th Street/Stone Quarry Road was
upgraded in 2011 to include auxiliary lane and access radius improvements, all of which
meet current CDOT design standards, including provisions for heavy truck traffic trips.
A WB -50 vehicle turning template for the site has been modelled using AutoTURN v 7.0
software for the project site access locations on 4th Street and Scarrow Avenue. The
existing roadways can adequately accommodate the anticipated vehicles.
Pro Gas, LLC anticipates adding 2 ADT to Highway 6 & 24, which will have negligible
impact to the overall traffic operations and capacity. The existing access at Highway 6
& 24 meets current CDOT requirements for turning and axillary lane needs and no
modifications or changes are needed as a result of the proposed project.
Pro -Gas has received a letter of approval and support from the Parachute Rural Fire
District for this use at the site.
The site has been previously been utilized as a storage yard with a mixture of gravel
and asphalt millings for a driving and parking surface as shown in the air photo below.
v
The addition of the Pro Gas Bulk Propane facility will have little effect on the property or
the existing drainage of the property.
The facility installation application is pending by the State of Colorado Department of Oil and Public
Safety, the state agency that regulates propane in Colorado. Pro -Gas developed the required Fire
Safety Analysis for the site. Pro -Gas has also received a letter of approval and support from the
Parachute Rural Fire District which provides fire protection to this industrial subdivision for this use
at the site.
Adjacent Land Use. Adjacent land use is commercial and industrial with the immediately
adjacent to the property to the northeast is vacant. The land to the northwest is Interstate
70. The land to the southeast is industrial welding services LLC. The land to the southwest is
vacant.
2. Site Features. The property is currently vacant industrial land with a slight (2%) gradient to the
southwest and is above the 100 -year floodplain. Access to the property is from Highway 6 toe
Street the entrance to the Travelers Highlands Subdivision and then on Scarrow Avenue, the
property is on the northwest corner of 4°i Street and Scarrow Avenue.
Soil Characteristics. The land is currently vacant and according to the Hazard Identification
and Risk Assessment the property is in zone 3. The property is in an area with low risk.
4. Geology and Hazard. The land is currently developed industrial. Pursuant to the Slope
Hazard Map for Study Area 3 in Garfield County, Colorado the subject property has no slope
hazard. See Geotechnical Report.
5. Groundwater and Aquifer Recharge Areas. Not applicable to this proposed use.
6. Environmental Impacts. The land is currently industrial land that has been used for
industrial use since 1462 and is overgrown with weeds and some debris. The removal of
the weeds, debris, minor site grading and the installation of the of the propane tank with a
driveway and fencing will not harm the environment.
7. Nuisance. The proposed use will not cause any generation of smoke, glare or other
emanations. There may be minimal dust, noise or vibration due to truck traffic. Small
amounts of propane are released in normal operations according to standard procedures
and compliance with Pamphlet 58 when it is required to bleed the line. The amount
released is negligible and will not pass further than the property line. See additional
description attached regarding the handling of complaints.
8. Hours of Operation. The proposed use will be utilized seven days a week generally
during normal business hours as described in the traffic estimates in the Request for
Waiver from Submittal of Traffic Study. It is possible that a truck may be required to
enter the site after hours based on their CDL required rest times. It is also possible that
Applicant's staff may be required to access the site after hours to handle occasional
delivery traffic or handle any complaints.
HANDLING OF COMPLAINTS
Receive a complaint of noise, smoke, dust, vibration, smell, etc:
1. Obtain the name, address and contact information of the complainant.
2. Verify the date, time and place, and a description of the event with the complainant.
3. Investigate the facts of the complaint:
time
a. Was the company proximate to the complaint?
b. Were the personnel and/or equipment of the company or assigns present at the date,
and place that the event took place?
c. If so, was the activity within the scope of normal business?
Were all company policies and procedures followed?
Was all equipment in proper operating condition?
4. If all these conditions are met. The complaint is valid and the responsibility of the company.
a. What actions or corrections can be implemented to prevent the same from occurring
again?
b. Different procedures, different scheduling, equipment repair/replacement, etc.
c. Institute the corrections and communicate with the complainant of the action taken.
5. If the company or its assigns were NOT responsible for the event, communicate such to the
complainant.
6. Retain documentation.