HomeMy WebLinkAbout2.01 Compliance with Article 7COMPLIANCE WITH ARTICLE 7, DIVISIONS 1 – 3
The following section of this application addresses compliance with the criteria
and standards of Article 7, Divisions 1-3 of the Garfield County Land Use and
Development Code. Responses to each criterion are in “italics”. Where
standards don’t apply, NA or reason for non-applicability will be stated.
DIVISION 1 GENERAL APPROVAL STANDARDS FOR LAND USE
CHANGE PERMITS
Section 7-101 Compliance with Zone District Use Restrictions.
Response: The site is located in the County’s Rural "R” Zone
District. The development is in compliance with the Zone
District, lot and building requirements, Intent Statement, use
and general restrictions and measurements contained in
Article 3 (Zoning) of the LUDC. A chart comparing the site
plan for the single-family house and the ADU using
dimensional standards per Table 3-201 is included in the
application narrative.
Section 7-102 Compliance with Comprehensive Plan and
Intergovernmental Agreements
Response: The Garfield County Comprehensive Plan 2030
designates the site as Residential Medium (RM).
Comprehensive plan issues were discussed in the
application narrative. It is our opinion that for all intents and
purposes, the proposal is in compliance with the
Comprehensive Plan 2030. The subject property is within the
Town of Carbondale Area of Influence. The Wooden Deer
subdivision was not submitted to the Town of Carbondale for
review in 1992. It is our understanding that Wooden Deer
predates any Intergovernmental Agreements with the Town
of Carbondale. In addition, ADU’s are not usually referred to
neighboring jurisdictions.
Section 7-103 Compatibility
Response: The nature, scale and intensity of the ADU and
use of this lot is consistent with surrounding lots within the
subdivision, adjoining subdivisions and any nearby
Agricultural properties
Section 7-104 Sufficient Legal and Physical Source of Water
Response: a sufficient legal and physical source of water
has been obtained in the past. See water supply documents
section for well permit, pump tests, Statement of Beneficial
Use and transfer of ownership
Section 7-105 Central Water Distribution and Wastewater Systems
Response: The central water system for Wooden Deer was
discussed in the Application Narrative. The HOA has
approved the ADU for the subject property. An OWTS
application per County standards has been submitted as part
of the original building permit for Lot 2 and is included with
the application documents.
Section 7-106 Public Utilities
Response: Adequate public utilities are available. Utilities
already serve the subdivision in general and Lot 2 in
particular. The single-family home and ADU are being
connected to the Wooden Deer water system and the
OWTS will be operational prior to Certificate of Occupancy.
Electricity also exists for the subject property.
Section 7-107 Access and Roadways
Response: A waiver request has been made for submitting
roadway standards related to Wooden Deer Drive, as we are
assuming that the original application that all County Road
standards in place at that time. Access to the lot off of the
Wooden Deer Dr. cul-de-sac is by a primitive driveway.
Width of the access point is approximately 16 feet. Driveway
will have either gravel or native material as a driving surface.
No improvements or modifications to County roads are
needed or proposed. No interior public roads are proposed
for the Property.
Section 7-108 Use of Land Subject to Natural Hazards
Response: No significant hazards exist where development
may occur, including areas subject to falling rock, mud flows,
snow slides, high water table, flooding etc. There are steep
slopes on the lot but steep slopes are not present where the
structure is being located and/or it is been subject to a
Grading and Drainage plan by a professional engineer.
Section 7-109 Fire Protection
Response: The Wooden Deer original subdivision plans
were reviewed by the Carbondale and Rural Fire Protection
District. The water system was designed to all standards in
effect at that time (mid-1990s). The water storage tank is
located on or adjacent to the subject lot. A fire hydrant is
located on the cul-de-sac used for access to the subject
property.
DIVISION 2 GENERAL RESOURCE PROTECTION STANDARDS FOR
LAND USE CHANGE PERMITS
Section 7-201 Protection of Agricultural Lands
Response:
No adverse affect on Ag Lands: The subject parcel is not
directly adjacent to any Agricultural lands or operations.
Because of the vegetation and topography, this lot was
never actively ranched to or used directly for agriculture.
Section 7-202 Protection of Wildlife Habitat Areas
Response:
A waiver from wildlife habitat analysis has been requested.
The subject property should have been reviewed for critical
wildlife habitat areas during the subdivision planning and any
necessary conditions or requirements put in place at that
time.
Section 7-203 Protection of Water bodies
Response: There are no water bodies on the property
subject to the ADU application or directly adjacent to Lot 2 of
the Wooden Deer Subdivision.
Section 7-204 Drainage and Erosion
Response: there should be no drainage or erosion problems
associated with the construction or use of the ADU. A
Grading and Drainage Plan analyzed and drawn by a
professional engineer was submitted with the Building Permit
application.
Section 7-205 Environmental Quality
Response: No impacts are foreseen related to air quality -
as impacts of an ADU minimal. No impacts to water quality
are foreseen. Any residential hazardous materials will be
stored per Federal, state or county regulations as applicable.
Section 7-206 Wildfire Hazards
Response: The subject property is listed as high wildfire
hazard area according to the County Risk Assessment
Maps. Vegetation has been removed in the vicinity of the
home (and ADU space) in order to create defensible space.
In addition, the Carbondale and Rural Fire Protection District
recently worked with the Wooden Deer HOA on a fire
mitigation program. Please see the Firewise Community
Assessment for Wooden Deer. This of course is a long-term
issue and we hope that the HOA and the Fire District
continue to work together in the future. Finally, a fire hydrant
is easily accessible at the lot boundary in the cul-de-sac of
Wooden Deed Drive.
Section 7-207 Natural and Geologic Hazards
Response: While we have requested a waiver from
analysis of the Natural and Geologic hazards (as these
should have been analyzed as part of the Subdivision
Review Process), hazards are relatively minimal for the site.
The lot does have some steep slopes, but the building area
is on a portion of the site that is relatively flat. Otherwise, it is
our understanding with the area that issues with the
following do not exist at the subject site:
• avalanche hazards
• landslide hazards
• rock fall possibilities
• alluvial fan issues
• corrosive/expansive soils (soils test and suitability for
construction submitted with building permit)
• mud flows
• development on faults
Section 7-208 Reclamation
Response: The development will comply with the standards
outlined in Section 7-208 of the Land Use Code.
Reclamation standards in Section 7-208 B will be followed
for the OWTS and utility extensions. These include:
• Contouring and Revegetation.
• Weed management.
• Application of Top Soil Where Necessary.
• Retaining Walls (if applicable).
• Removal of significant Debris (if applicable).
Disturbed areas will also be treated so that noxious weeds
are controlled.
DIVISION 3 SITE PLANNING AND DEVELOPMENT STANDARDS
The standards in this section apply to any land use change including division of
land. While single-family dwellings, and we also assume ADU’s, are largely
exempt, we will respond to these conditions where appropriate.
Section 7-301 Compatible Design
Response: The ADU, and the subdivision itself, complies
with these sections.
A. Site Organization. The structure, including ADU is being
built in an appropriate location. The subdivision itself
appears to be logically laid out in relationship to
topography, access and neighboring properties.
B. Operational Characteristics. NA. No objectionable
emissions expected from this type of land-use.
C. Buffering. No required buffering is anticipated. Lighting is
the only operational characteristic which could create
problems with this type of land-use and its location. The
project will comply with County lighting standards.
D. Materials. Complies
Section 7-302 Off- Street Parking and Loading Standards
Response: NA. ADU has minimal parking requirements.
There are plenty of appropriate parking areas as per the site
plan. The single-family dwelling has a three-car garage.
Clear vision areas will be maintained as necessary in the
vicinity of the Access Driveway.
Section 7-303 Landscaping Standards
Response: NA. ADU’s are exempt
Section 7-304 Lighting Standards
Response. Any outdoor lighting will comply with the
standards of this section of the Garfield County LUDC, and
be downcast and shielded as necessary.
Section 7-305 Snow Storage Standards
Response: NA. This type of residential unit is exempt.
Section 7-306 Trail and Walkway Standards
Response: NA. No trails or walkways were associated with
the subdivision or this lot.