HomeMy WebLinkAbout6.00 Cost Opinion for WorkPROJECT: Elk Creek Fish Bypass Channel - New Castle, CO Ver 1 -Date:November 10, 2017 Final Design - Cost Opinion Description Quantity Unit Unit Cost Total Cost Totals Notes / Assumptions Site Preparation Staging Area 1 LS $1,000 $1,000 Erosion and Sediment Control Management 1 LS $1,750 $1,750 Silt fence 160 LF $5 $800 Access Road Reinforcement 131 CY $20 $2,620 Temporary Construction Fencing 500 LF $5 $2,500 New bid item added after 50% Construction Access Ramp 2 EA $750 $1,500 Care of Water Implementation and Management 1 LS $3,500 $3,500 Turbidity Curtain 145 LF $15 $2,175 Oil Boom 145 LF $20 $2,900 Concrete Materials and Rubble Haul-Off and Disposal 80 CY $20 $1,600 Large Woody Debris Removal 5 EA $100 $500 Clearing of Riparian Vegetation 400 SY $5 $2,000 PIP Mature Trees 1 EA $500 $500 Tree Removal 3 EA $400 $1,200 Sub Total:$24,545 Fish Passage Channel Excavation 430 CY $10 $4,304 Material Haul-off and Disposal 381 CY $25 $9,528 Furnish and Install Fish Boulders (3' - 4' Dia)60 TON $120 $7,200 Furnish and Install Channel Side Boulders (1.5' - 2' Dia)187 TON $75 $14,013 Increased based on 50% design comments Furnish and Install Inlet Protection Boulders (4' -Dia)61 TON $120 $7,275 Increased based on annual cleaning concerns. Furnish and Install Vane Boulders (5' - 6' Dia)74 TON $120 $8,917 Increased based on gravel sedimentation concerns. Alluvial Backfill 126 CY $10 $1,255 Harvest and Install Cobble Bed 50 CY $25 $1,250 Concrete Wall Pass Through with Stop Logs 1 LS $4,000 $4,000 Performance Adjustments 16 HR $150 $2,400 Sub Total:$60,143 Stabilization, Planting, and Maintenance Erosion Control Blanket 190 SY $25 $4,750 Seeding 230 SY $5 $1,150 Harvest and Replant Willows 25 EA $50 $1,250 2 Year Vegetation Warranty 1 LS $1,500 $1,500 Sub Total:$8,650 ITEMIZED CONSTRUCTION SUBTOTAL $93,338 Contingency (3%)$2,800 CONSTRUCTION WITH CONTIGENCY $96,138 Land Survey (LS)$0 Geotechnical Engineering $0 Structural Engineering $0 Utility Relocations $0 Traffic Control LS $500 Hydrographic Survey $0 Included in Current Contract Cultural Resource Survey and Report $0 Full Wetland Delineation $0 Lands and Easements (Permanent)$0 Lands and Easements (Construction)$0 Lands and Easements Processing $0 Construction Bonding/Ins (5%)$4,667 5% construction after design Mob and Demob (5%)$4,667 5% construction Environmental Assessment Recovery Prgm $0 Engineering Design $0 Included in Current Contract Hydraulic Modeling $0 Included in Current Contract Permitting 404, 401 $0 Included in Current Contract CDOT ROW License $0 Not required for this project. Permitting Floodplain $0 Included in Current Contract Plans and Specifications for bid $0 Included in Current Contract Construction Stakeout $2,000 Construction Review Observations $0 Included in Current Contract Vegetation Replacement YR 2 $2,000 TOTAL PROJECT COST OPINION $109,972 Elk Creek Fish Bypass Channel Final Design - Engineers Opinion of Cost Page 1