HomeMy WebLinkAboutSoils Report 04.25.2018Hp�KUMAR
Geotechnical Engineering 1 Engineering Geology
Materials Testing 1 Environmental
5020 County Road 154
Glenwood Springs, CO 81601
Phone: (970) 945-7988
Fax: (970) 945-8454
Email: hpkglenwood@kumarusa.com
Office Locations: Denver (I -IQ), Parker, Colorado Springs, Fort Collins, Glenwood Springs, Summit County, Colorado
SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED STEEL BUILDING
LOT 5, RIFLE CREEK HIGHLANDS
COUNTY ROAD 317
GARFIELD COUNTY, COLORADO
PROJECT NO. 18-7-231
APRIL 25, 2018
PREPARED FOR:
MIKE RAINEY
3177 WEST 31st COURT
RIFLE, COLORADO 81650
444re]oad@gmail.com
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY - 1 -
PROPOSED CONSTRUCTION - 1 -
SITE CONDITIONS - 2 -
FIELD EXPLORATION - 2 -
SUBSURFACE CONDITIONS - 2 -
FOUNDATION BEARING CONDITIONS - 3 -
DESIGN RECOMMENDATIONS - 3 -
FOUNDATIONS - 3 -
FLOOR SLABS -5-
UNDERDRAIN SYSTEM - 5 -
SURFACE DRAINAGE ... - 6 -
LIMITATIONS - 6 -
FIGURE 1 - LOCATION OF EXPLORATORY BORINGS
FIGURE 2 - LOGS OF EXPLORATORY BORINGS
FIGURE 3 - LEGEND AND NOTES
FIGURES 4 - 5 - SWELL -CONSOLIDATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
H-P*KUMAR
Project No. 18-7-231
PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed steel building to be located on
Lot 5, Beaver Creek Highlands, County Road 317, southwest of Rifle, Garfield County,
Colorado. The project site is shown on Figure 1. The purpose of the study was to develop
recommendations for the foundation design. The study was conducted in accordance with our
agreement for geotechnical engineering services to Mike Rainey dated March 27, 2018.
Potential geologic hazards that may impact the site are beyond the scope of this report.
A field exploration program consisting of exploratory borings was conducted to obtain
information on the subsurface conditions. Samples of the subsoils obtained during the field
exploration were tested in the laboratory to determine their classification, compressibility or
swell and other engineering characteristics. The results of the field exploration and laboratory
testing were analyzed to develop recommendations for foundation types, depths and allowable
pressures for the proposed building foundation. This report summarizes the data obtained during
this study and presents our conclusions, design recommendations and other geotechnical
engineering considerations based on the proposed construction and the subsurface conditions
encountered.
PROPOSED CONSTRUCTION
The proposed building will be a 40 by 80 feet plan size steel frame and metal structure located in
the southern part of the lot approximately as shown on Figure 1. Ground floor will be slab -on -
grade. Grading for the structure is assumed to be relatively minor with cut depths between about
3 to 5 feet. We assume moderate foundation loadings, typical of the proposed type of
construction and carried primarily by footing pads and connecting grade beams.
If building loadings, location or grading plans change significantly from those described above,
we should be notified to re-evaluate the recommendations contained in this report.
H-P%KUMAR
Project No. 18-7-231
-2 -
SITE CONDITIONS
The lot was vacant and the ground surface in the area of the proposed building appeared mostly
natural. Trees and brush in the building area had been removed and the vegetation consisted of
grass and weeds. The terrain is relatively flat with a gentle slope down to the northeast. We did
not observe any other buildings in the immediate area of Lot 5.
FIELD EXPLORATION
The field exploration for the project was conducted on April 5, 2018. Two exploratory borings
were drilled at the locations shown on Figure 1 to evaluate the subsurface conditions. The
borings were advanced with 4 -inch diameter continuous flight augers powered by a truck-
mounted CME -45B drill rig. The borings were logged by a representative of H-P/Kumar.
Samples of the subsoils were taken with 1% inch and 2 inch I.D. spoon samplers. The samplers
were driven into the subsoils at various depths with blows from a 140 -pound hammer falling 30
inches. This test is similar to the standard penetration test described by ASTM Method D-1586.
The penetration resistance values are an indication of the relative density or consistency of the
subsoils. Depths at which the samples were taken and the penetration resistance values are
shown on the Logs of Exploratory Borings, Figure 2. The samples were returned to our
laboratory for review by the project engineer and testing.
SUBSURFACE CONDITIONS
Graphic logs of the subsurface conditions encountered at the site are shown on Figure 2. The
subsoils encountered, below about V2 to 1 foot of organic topsoil, consisted of sandy clay with
basalt gravel and scattered cobbles and possible boulders. The sandy clay was occasionally very
sandy, medium plastic and extended down to the maximum depth drilled of 26 feet.
Laboratory testing performed on samples obtained from the borings included natural moisture
content and density, and percent finer than sand size gradation analyses. Results of swell -
consolidation testing performed on relatively undisturbed drive samples, presented on Figures 4
H-P%KUMAR
Project No. 18-7-231
-3 -
and 5, indicate low to moderate compressibility under conditions of loading and wetting. One
sample (Boring 1 at 5') showed a moderate swell potential and two other samples (Boring 1 at
10' and Boring at 2.5') showed a nil to low swell potential when wetted under a constant 1,000
psf surcharge. The laboratory testing is summarized in Table 1.
Free water was encountered in Boring 1 at a depth of about 131/2 feet at the time of drilling. No
groundwater was encountered in Boring 2 at the time of drilling. The subsoils were generally
moist with the exception of the Boring 1 at 5' sample that was slightly moist.
FOUNDATION BEARING CONDITIONS
The soils possess generally low bearing capacity and a nil to low swell potential. The moderate
swell measured in the one sample that was slightly moist is believed to be an anomaly within the
generally moist subsoils. The groundwater encountered in Boring 1 is likely a perched condition
due to spring snow melt and run-off.
Spread footings appear feasible for foundation support of the building with some risk of
movement. The risk of movement is if potentially expansive bearing soils were to become
wetted. We should review the exposed bearing soils at the time of excavation. Potentially
expansive soils at footing (and floor slab) subgrade may need to be removed and replaced with
compacted road base such as CDOT Class 2, 5 or 6 material.
A lower risk of movement would be helical piers or screw piles. Provided below are
recommendations for shallow spread footings. If recommendations for a deep foundation system
are desired, we should be contacted.
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory borings and the nature of
the proposed construction, we believe the building be founded with spread footings bearing on
H-P%KUMAR
Project No. 18-7-231
-4 -
the natural soils with some risk of movement. Precautions, such as adequate compaction of
foundation backfill and positive surface drainage away from the building foundation walls,
should be taken to prevent wetting of the bearing soils.
The design and construction criteria presented below should be observed for a spread footing
foundation system.
1) Footings placed on the undisturbed natural granular soils should be designed for
an allowable bearing pressure of 2,000 psf. Based on experience, we expect
settlement of footings designed and constructed as discussed in this section will
be about 1 inch or less. There could be some additional movement if the bearing
soils were to become wetted. The magnitude of the additional movement would
depend on the bearing conditions and depth and extent of the wetting but may be
on the order of 1 to 11/ inches.
2) The footings should have a minimum width of 16 inches for continuous walls and
2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided with
adequate soil cover above their bearing elevation for frost protection. Placement
of foundations at least 36 inches below exterior grade is typically used in this
area.
4) Continuous foundation walls should be well reinforced top and bottom to span
local anomalies such as by assuming an unsupported length of at least 12 feet.
Foundation walls acting as retaining structures should also be designed to resist a
lateral earth pressure corresponding to an equivalent fluid unit weight of at least
55 pcf.
5) All existing fill, topsoil, potentially expansive clay soils and any loose or
disturbed soils should be removed and the footing bearing level extended down to
the firm natural soils. The exposed soits in footing area should then be moistened
and compacted.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to evaluate bearing conditions.
H-Ptv'KUMAR
Project No. 18-7-231
5
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, should be suitable to support lightly loaded slab -
on -grade construction. There is a risk of slab movement if the subgrade were to become wetted.
For long term performance of the slab, a depth (typically 11/2 to 2 feet) of imported road base
such as CDOT Class 2, 5 or 6 base course, could be placed below the slab. We should review
the slab subgrade conditions and need for a depth of compacted base course below the floor slab
at the time of construction.
To reduce the effects of some differential movement, floor slabs should be separated from all
bearing walls and columns with expansion joints which allow unrestrained vertical movement.
Floor slab control joints should be used to reduce damage due to shrinkage cracking. The
requirements for joint spacing and slab reinforcement should be established by the designer
based on experience and the intended slab use. A minimum 4 -inch layer of sand and gravel road
base should be placed immediately beneath the slab for support and to facilitate drainage. This
material should consist of minus 2 inch aggregate with at least 50% retained on the No. 4 sieve
and less than 12% passing the No. 200 sieve.
All fill materials for support of floor slabs should be compacted to at least 95% of maximum
standard Proctor density at a moisture content near to slightly above optimum. Required fill can
consist of the on-site soils devoid of topsoil and oversized (plus 6 inch) rocks, or a well graded
granular material such as road base can be imported.
UNDERDRAIN SYSTEM
It is our understanding the proposed finished floor elevation of the building at the lowest level is
at or above the surrounding grade. Therefore, a foundation drain system is not required. It has
been our experience in mountainous areas that local perched groundwater can develop during
times of heavy precipitation or seasonal runoff. Frozen ground during spring runoff can also
create a perched condition. We recommend below -grade construction, such as retaining walls,
crawlspace and basement areas, be protected from wetting and hydrostatic pressure buildup by
an underdrain and wall drain system.
H-P*KUMAR
Project No. 18-7-231
-6-
Tf the finished floor elevation of the building is revised to have a floor level below the
surrounding grade, we should be contacted to provide recommendations for an underdrain
system. All earth retaining structures should be properly drained.
SURFACE DRAINAGE
Positive surface drainage is a very important aspect of the project to prevent wetting of the soils
below the building. The following drainage precautions should be observed during construction
and maintained at all times after the building has been completed:
1) Inundation of the foundation excavations and underslab areas should be avoided
during construction.
2) Exterior backfill should be adjusted to near optimum moisture and compacted to
at least 95% of the maximum standard Proctor density in pavement and slab areas
and to at least 90% of the maximum standard Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be sloped to
drain away from the foundation in all directions. We recommend a minimum
slope of 12 inches in the first 10 feet in unpaved areas and a minimum slope of 3
inches in the first 10 feet in paved areas.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
5) Landscaping which requires regular heavy irrigation should be located at least 10
feet from foundation walls. Consideration should be given to use of xeriscape to
reduce the potential for wetting of soils below the building caused by irrigation.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical engineering
principles and practices in this area at this time. We make no warranty either express or implied.
The conclusions and recommendations submitted in this report are based upon the data obtained
from the exploratory borings drilled at the locations indicated on Figure 1, the proposed type of
construction and our experience in the area. Our services do not include determining the
presence, prevention or possibility of mold or other biological contaminants (MOBC) developing
H -P KIJMAJC
Project No, 18-7-231
-7 -
in the future. If the client is concerned about MOBC, then a professional in this special field of
practice should be consulted. Our findings include interpolation and extrapolation of the
subsurface conditions identified at the exploratory borings and variations in the subsurface
conditions may not become evident until excavation is performed. If conditions encountered
during construction appear different from those described in this report, we should be notified so
that re-evaluation of the recommendations may be made.
This report has been prepared for the exclusive use by our client for design purposes. We are not
responsible for technical interpretations by others of our information. As the project evolves, we
should provide continued consultation and field services during construction to review and
monitor the implementation of our recommendations, and to verify that the recommendations
have been appropriately interpreted. Significant design changes may require additional analysis
or modifications to the recommendations presented herein. We recommend on-site observation
of excavations and foundation bearing strata and testing of structural fill by a representative of
the geotechnical engineer.
Respectfully Submitted,
_f?
S•
i.J
David A. Young, P.L
DAY/kacs'�i3b'ka�pp ggqq
tt
cc: Precision Buildings - Branden Tuell (btuell C precisionbuildings.net)
c?'dif
a aok "•��Ac�err
6 se
0
H-PkKUMAR
Project No. 18-7-231
z
3
Y ROAD #317 L1'=
PRiSCRIPTIVE� �S
,,1T -�h Gti
4+,
rf�_,.-rl::�.. -.-c::^ ..;c;Sl3i•tt� ?5:_.__ .r�fuV.atC`affi.Y.TCNu .
KL•15AL. ANT-) ALUM.LAI'--•' ,�
L.S. NO. 10871 BEARS
N48°08'19"E 27.98'
cd
Oma
U
[Wi�°ro
M
a�zz
Lon
,Yccyy
4U
5 REBAR AND CAP
5 REBAR AND CAP L.S. NO. 37935 10.50' W.C.
L.S. NO. 37935 20.65' W.C.
iPOUNTY ROAD #317A
60' PRESCRIPTIVE EASEMENT
ER FIELD LOCATION
)UNTY ROAD #317A
;EMENT PER REC. NO.
773464
1AND CAP
35 35' W.C.
ory� N
syr
2634.10'
LOT 5
35.185 AC. ±
BEAVER CREEK
HIGHLANDS
PROPOSED
BUILDING 3� 40' ACCESS &
BORING 1 EASEMEISEE"
BORING 2,-
#5 REBAR CJD CAP \ 1
-20
'' L.S. NO. 37935 25' W.C.
aRINEHART
1\' SPRING #8
00
UU
min
zc
LOT 4 --
35.242 AC, ±
-
35.242AC.±
5 REBAR AND CAP
` L.S. NO. 37935 12' W.C.
ly
C24 C2 2 C
G L23 C74 4-22 G21 L
ti�
1
LOT 6
35.305 AC ±
r
s u9°5 6"
150 0 150 300
APPROXIMATE SCALE -FEET
LtS L
1r�4`
rn
zz
00
H H
W W
rn �
33
zc
5 REB
L.S. NO
1•,1
o
,�
v,
2-05.66 f r r
30' UTILITY EASEMENT
(TYP.) SEE NOTE #10
18-7-231 f H-P--14KUMAR
LOCATION OF EXPLORATORY BORINGS I Fig. 1
-- 0
— 5
— 10
15
— 20
— 25
— 30
18-7-231
BORING 1
18/12
WC=17.7
DD=109
-200=77
50/6
WC=10.0
DD=120
38/12
WC=15.3
DD=115
21/12
WC=14.6
DD=115
9/12
59/12
H-P-� KUMAR
BORING 2
f f 16
/ =21.6
DWC/12
D=100
11/12
/- WC=15.8
DD=108
f
/
/
/- 16/12
/- WC=17.2
// DD=114
f
/
/7 38/12
f WC=16.3
/ • DD=109
-200=60
/
/
/- 24/12
0
5
10
15
20
25-
5-
30-
30-
LOGS OF EXPLORATORY BORINGS
0
0
Fig. 2
ng'nrar n2 187231-02 lo 03 av0
LEGEND
-'G
/
/
/
/
li
TOPSOIL; ORGANIC SILTY CLAY, FIRM, VERY MOIST, DARK BROWN.
CLAY (CL); SANDY TO OCCASIONALLY VERY SANDY WITH BASALT GRAVEL AND SCATTERED
COBBLES, STIFF TO VERY STIFF, TYPICALLY MOIST, BROWN AND GRAY -BROWN, MEDIUM PLASTICITY.
RELATIVELY UNDISTURBED DRIVE SAMPLE; 2 -INCH I.D. CALIFORNIA LINER SAMPLE.
DRIVE SAMPLE; STANDARD PENETRATION TEST (SPT), 1 3/8 INCH I.D. SPLIT SPOON
SAMPLE, ASTM D-1586.
18/12 DRIVE SAMPLE BLOW COUNT. INDICATES THAT 18 BLOWS OF A 140 -POUND HAMMER
FALLING 30 INCHES WERE REQUIRED TO DRIVE THE CALIFORNIA OR SPT SAMPLER 12 INCHES.
Q DEPTH TO WATER LEVEL AT TIME OF DRILLING.
NOTES
1. THE EXPLORATORY BORINGS WERE DRILLED ON APRIL 5, 2018 WITH A 4 -INCH DIAMETER
CONTINUOUS FLIGHT POWER AUGER.
2. THE EXPLORATORY BORINGS WERE LOCATED BY THE CLIENT, APPROXIMATELY AS SHOWN ON
FIGURE 1.
3. THE ELEVATIONS OF THE EXPLORATORY BORINGS WERE NOT MEASURED AND THE LOGS OF THE
EXPLORATORY BORINGS ARE PLOTTED TO DEPTH.
4. THE EXPLORATORY BORING LOCATIONS SHOULD BE CONSIDERED ACCURATE ONLY TO THE
DEGREE IMPLIED BY THE METHOD USED.
5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY BORING LOGS REPRESENT THE
APPROXIMATE BOUNDARIES BETWEEN MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL.
6. GROUNDWATER LEVELS SHOWN ON THE LOGS WERE MEASURED AT THE TIME AND UNDER
CONDITIONS INDICATED. NO GROUNDWATER ENCOUNTERED IN BORING 2. FLUCTUATIONS IN THE
WATER LEVEL MAY OCCUR WITH TIME.
7. LABORATORY TEST RESULTS:
WC = WATER CONTENT (%) (ASTM D 2216);
DD = DRY DENSITY (pcf) (ASTM D 2216);
-200= PERCENTAGE PASSING NO. 200 SIEVE (ASTM D 1140).
18-7-231
H-PtiKUMAR
LEGEND AND NOTES
Fig. 3
CONSOLIDATION - SWELL
CONSOLIDATION - SWELL
2
1
0
—1
— 2
— 3
1
—1
— 2
3
10 APPLIED PRESSURE - KSF
10
1
100
SAMPLE OF: Sandy Clay with Gravel
FROM: Boring 1 ® 10'
WC = 15.3 %, DD = 115 pcf
EXPANSION UNDER CONSTANT
PRESSURE UPON WETTING
•
SAMPLE OF: Sandy Clay
FROM: Boring 1 @ 5'
WC = 10.0 %, DD = 120 pcf
1
_
I
EXPANSION UNDER CONSTANT
PRESSURE UPON WETTING
Thee* test rct&ite appy anly to the
ample* tatted T a testing apart
hall not be reproduced, asaept in
full, without the written approval of
(Kumar and Associ tea, Inc. wall
,Consalidstion testi g perform d in
.accordance with ASTM 0-45 6.
i
I
10 APPLIED PRESSURE - KSF
10
1
100
SAMPLE OF: Sandy Clay with Gravel
FROM: Boring 1 ® 10'
WC = 15.3 %, DD = 115 pcf
EXPANSION UNDER CONSTANT
PRESSURE UPON WETTING
•
18-7-231
10 APPLIED PRESSURE - KSF
H -P- KUMAR
10 100
SWELL -CONSOLIDATION TEST RESULTS
Fig. 4
1
Thee* test rct&ite appy anly to the
ample* tatted T a testing apart
hall not be reproduced, asaept in
full, without the written approval of
(Kumar and Associ tea, Inc. wall
,Consalidstion testi g perform d in
.accordance with ASTM 0-45 6.
i
I
18-7-231
10 APPLIED PRESSURE - KSF
H -P- KUMAR
10 100
SWELL -CONSOLIDATION TEST RESULTS
Fig. 4
CONSOLIDATION - SWELL
CONSOLIDATION - SWELL
1
0
—1
— 2
3
— 4
0
— 1
— 2
— 3
—4
5
10
100
SAMPLE OF: Sandy Clay with Gravel
FROM: Boring 2 @ 2.5'
WC = 21.6 %, DD = 100 pcf
N0
MOVEMENT
WETTING
UPON
•-..- -�____
_�
-----�.—..__.----•--
EXPANSION UNDERCONSTANT
PRESSURE UPONPON WETTING
i
r
These teat results apply only to the
samples leaked. Tha tailing report
shall not be repredvCea. eacepl in
full, without the whiten *pirate! of
Kumar and Associates, Inc Swell
Cain+ hdolion lasting arformed in
accordance wuI6 ASTM D-4546.
^--•�
10
100
APPLIED PRESSURE — KSF
10
100
18-7-231
H -P- KUMAR
SWELL -CONSOLIDATION TEST RESULTS
Fig. 5
SAMPLE OF: Sandy Clay with Gravel
l FROM: Boring 2 @ 10'
WC = 17.2 %, DD = 114 pcf
N0
MOVEMENT
WETTING
UPON
•-..- -�____
_�
-----�.—..__.----•--
i
r
These teat results apply only to the
samples leaked. Tha tailing report
shall not be repredvCea. eacepl in
full, without the whiten *pirate! of
Kumar and Associates, Inc Swell
Cain+ hdolion lasting arformed in
accordance wuI6 ASTM D-4546.
^--•�
APPLIED PRESSURE — KSF
10
100
18-7-231
H -P- KUMAR
SWELL -CONSOLIDATION TEST RESULTS
Fig. 5
1P)t-
VUAR
TABLE 1
SUMMARY OF LABORATORY TEST RESULTS
SAMPLE LOCATION
BORING
1
DEPTH
(ft)
NATURAL
MOISTURE
CONTENT
(%)
NATURAL
DRY
DENSITY
(pcf)
21 17.7 109
5 10.0 120
GRADATION
GRAVEL
(%)
SAND
(%)
PERCENT
PASSING
NO. 200
SIEVE
77
ATTERBERG LIMITS UNCONFINED
COMPRESSIVE
STRENGTH
LIQUID
LIMIT
(%)
PLASTIC
INDEX
(%)
(psf)
Project No. 18-7-231
SOIL TYPE
Sandy Clay with Gravel
Sandy Clay
10 15.3 115
15 14.6 115
Sandy Clay with Gravel
Sandy Clay with Gravel
2
Sandy Clay with Gravel
5 15.8 108
10 17.2 114
15 16.3 109
60
Sandy Clay with Gravel
Sandy Clay with Gravel
J
Very Sandy Clay