HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-03-19-5659
HES 51 Road 223, LLC
Tension Fabric Structure for Commercial Vehicle Storage
51 County Road 223 — Rifle, Colorado
1) ALL WORK SHALL COMPLY WITH THE 2015 INTERNATIONAL BUILDING CODE (I.B.C.)
2015 INTERNATIONAL FIRE CODE (I.F.C.) AND MANUFACTURER'S INSTALLATION
SPECIFICATIONS.
2) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS &
INSPECTIONS POLICIES.
3) WORK SHALL COMPLY WITH ALL REQUIREMENTS OF "COMMERCIAL GENERAL" ZONE
DISTRICT AS DEFINED IN GARFIELD COUNTY'S LAND USE & DEVELOPMENT CODE.
4) TENSION FABRIC STRUCTURE IS APPROVED AS CONSTRUCTION TYPE II -B (NON-
SPRINKLERED) WITH OCCUPANCY/USE GROUP S-1: "MODERATE -HAZARD STORAGE".
MAXIMUM ALLOWABLE QUANTITY OF FLAMMABLE AND COMBUSTIBLE MATERIALS
SHALL BE AS PER I.B.C., SECTIONS 413 & 414, AND I.F.C., CHAPTER 27.
5) CONTACT LOCAL FIRE DISTRICT FOR REVIEW AND APPLICABLE I.F.C. REQUIREMENTS.
FIRE DISTRICT'S FINAL APPROVAL REPORT IS REQUIRED PRIOR TO FINAL BUILDING
INSPECTION & CERTIFICATE OF OCCUPANCY.
6) OPEN -HOLE SOILS REPORT IS REQUIRED AT FOOTING INSPECTION, 2000 P.S.F.
7) ALL HIGH-STRENGTH BOLTING AND FIELD WELDING REQUIRES SPECIAL INSPECTOR PER
SPECIAL INSPECTIONS PROVISIONS OF I.B.C., CHAPTER 17. PROVIDE APPROVAL REPORT
AT FRAME INSPECTION.
8) TENSION FABRIC STRUCTURE HAS BEEN APPROVED AS AN UNHEATED BUILDING. IF
HEATED - EITHER AT PRESENT OR IN THE FUTURE - THERMAL ENVELOPE SHALL BE
INSULATED PER 2009 I.E.C.C. REQUIREMENTS.
9) INTERIOR PARTITIONS AND/OR TENANT IMPROVEMENTS INCLUDING RESTROOMS ARE
NOT INCLUDED UNDER THIS PERMIT. IF INCLUDED AT A LATER DATE, RESTROOMS WILL
REQUIRE INSULATION AT THERMAL ENVELOPE (INCLUDING SLAB) AND A HEAT SOURCE
TO PROTECT PLUMBING FROM FREEZE -UPS.
10) EGRESS REQUIREMENTS PER 2015 I.B.C., CHAPTER 10. PROVIDE A MINIMUM OF (2)
WALK DOORS FOR EGRESS WITH 36" X 80" MINIMUM SIZE PER SECTION 1010.1. LOCKS,
LATCHES AND LANDINGS PER SECTION 1008. LANDINGS AT DOORS PER SECTION 1010.
VERIFY EXIT DIRECTIONAL SIGNAGE PRIOR TO ELECTRICAL ROUGH -IN INSPECTION.
11) LIGHT, VENTILATION & TEMPERATURE CONTROLS PER 2015 I.B.C., CHAPTER 12.
12) ELECTRICAL REQUIREMENTS, PERMITTING AND INSPECTIONS BY COLORADO STATE
ELECTRICAL BOARD. ELECTRICAL FINAL APPROVAL IS REQUIRED PRIOR TO FINAL
BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.