Onsite Wastewater System Certification
To: Andy Schwaller— Garfield County, Chief Building Official
From: Adam Racette, PE
Re: AVPC South Septic System — Certification
Date: June 6, 2019
The South Onsite Wastewater Treatment System (OWTS) for the Aspen Valley Polo Club was
constructed and installed in May and June of 2019. Roaring Fork Engineering observed the system
during installation and at the completion on June 5, 2019. The system appears to be constructed in
accordance with the engineered design that was submitted to and approved by the Garfield County
Building Department. The pumps, alarms, ADV, and flushing assemblies were all testing and operational.
The equipment was provided by Valley Precast and installed by Avalanche Excavation. Pictures of the
system are included for reference.
Figure 1— Septic Tanks
ROARING FORK
ENGINEERING
Figure 2 — Pump Chamber
Figure 3 — ADV
ROARING FORK
ENGINEERING
Figure 4 — STA
Please call with any questions: 970-3408-4130