My office has been contacted by DZ Remodeling to provide professional engineering services
for the above referenced project. If the scope of remodel work extends beyond that discussed
herein, we will submit our standard letter of agreement to provide the following services:
1. Observation of existing conditions prior to demolition.
2. Follow-up with Field Reports to help define critical elements if applicable.
3. Design and Construction Documents for any additional structural work.
4. Observations during new structural construction with Field Reports.
I have reviewed a Schematic Design set of plans dated 11-11-2019, prepared by DZ Remodeling
for this remodel work. No construction documents for existing structure have been recovered for
review. The work involved includes removal of an interior wall between the entry hallway and
kitchen.
Conclusion:
Wall to be revised is not anticipated as a support wall. I recommend that drywall be removed
without altering framing, and my office be notified to observe and verify the framing conditions
at the wall to be removed. A Field Report will follow that site visit.
19032 2019-12-04 Letter