Re: Heyl Residence, Foundation Stepped Footing Review & Approval — TGE19-11949
Mr. Argo,
The purpose of our letter is to address the perimeter foundation stepped footing construction for the
above-mentioned project. After reviewing the photos provided by Dave Heyl (Heyl Construction, Inc.) on
May 15th 2019, Tamarack Grove Engineering has analyzed to the best of our knowledge, and with verbal
verification provided by Dave Heyl that the perimeter foundation stepped footing locations, rebar
placement, and spacing has been adequately constructed per the design noted on the approved
construction documents stamped on April 29th, 2019. All perimeter foundation stepped footing locations
have been reviewed through provided photos and back checked with the most current construction
drawings set stamped on April 29th, 2019. The list of items noted below are changes made in the field.
Current construction drawing set stamped on April 29th, 2019 shows one stepped footing location for
garage perimeter footings. For the garage perimeter foundation stepped footing locations, multiple
stepped footing segments are permitted due to the subgrade slope.
If there are any other questions related to this project, please feel free to contact our office.
Kind Regards,
rpt
Tyler C. Maier
Tamarack Grove Engineering
812 La Cassia Dr.
Boise, ID. 83705
Ph. (208) 629-0879
Email: Tyier.Maier@tamarackgrove.com
05/15/19
SpeatiVill u Sbu VIAL 6Utu
812 L. Cassis Or. • Boise. ldsho 83705 • Phonic 208.348.8841 • Fax; 208.345.8848