1) ALL WORK MUST COMPLY WITH THE 2015 IBC, IMC, IPC, IFGC, IFC, AND THE 2009 IECC.
2) COMPLY WITH ALL MANUFACTURER'S INSTALLATION INSTRUCTIONS & SPECIFICATIONS.
3) ALL WORK SHALL COMPLY WITH "COMMERCIAL GENERAL" ZONE DISTRICT
REGULATIONS PER GARFIELD COUNTY'S LAND USE & DEVELOPMENT CODE.
4) BUILDINGS ARE APPROVED AS TYPE II-B CONSTRUCTION, S-1 OCCUPANCY GROUP AND
FOR "COLD STORAGE" ONLY. IF STRUCTURES ARE TO BE HEATED (NOW OR IN THE
FUTURE) BELOW -GRADE INSULATION TO BE INSTALLED PER 2009 IECC REQUIREMENTS.
5) FENCES HIGHER THAN 7'-0" ABOVE GRADE REQUIRE A BUILDING PERMIT & AMENDED
PLANS SHALL BE SUBMITTED ILLUSTRATING FENCE LOCATIONS FOR APPROVAL.
6) ANY ADDITIONAL ACCESSORY -USE BUILDINGS (SHEDS, OFFICES, ETC.) SHALL BE SUBJECT
TO FURTHER BUILDING DEPT. REVIEW & PERMITTING. AMENDED PLANS ILLUSTRATING
SUCH WORK SHALL BE SUBMITTED FOR SUBSEQUENT REVIEW & APPROVAL.
7) VERIFY DRIVEWAY ACCESS REQUIREMENTS AND STANDARDS WITH CITY OF GLENWOOD
SPRINGS AND PROVIDE SIGN -OFF FOR ALL RELATED ISSUES.
8) CONTACT LOCAL FIRE DISTRICT FOR PERTINENT I.F.C. AND FIRE SPRINKLER REQUIRE-
MENTS. FIRE DISTRICT'S FINAL APPROVAL REPORT IS REQUIRED FOR FINAL INSPECTION
AND CERTIFICATE OF OCCUPANCY.
9) IF SECURITY GATE IS USED AT ACCESS DRIVE, IT SHALL BE LOCATED FAR ENOUGH OFF
ROADWAY SO AS TO NOT INTERFERE WITH PROPER FLOW OF TRAFFIC ON COUNTY
ROAD 116 (RECOMMENDED DISTANCE OF 50' MINIMUM).
10) SITE RETAINING WALLS ALONG COUNTY ROAD 116 SHALL BE CONSTRUCTED FULLY
WITHIN PROPERTY LINES AND ARE NOT ALLOWED TO ENCROACH INTO THE ROAD
RIGHT-OF-WAY. A LOT IMPROVEMENT CERTIFICATE, SEALED BY A COLORADO LICENSED
SURVEYOR, IS REQUIRED AT THE TIME OF FOOTING/FOUNDATION INSPECTION TO
VERIFY ADHERENCE TO SETBACKS & CONSTRUCTION LIMITS WITHIN PROPERTY LINES.
11) ALL HIGH STRENGTH BOLTING AND FIELD WELDING REQUIRES SPECIAL INSPECTOR.
PROVIDE APPROVAL REPORT AT FRAME INSPECTION.
12) IF EXTERIOR LIGHTING IS INSTALLED, IT SHALL CONFORM TO GARFIELD COUNTY'S
LIGHTING STANDARDS (SECTION 7-304).
13) ELECTRICAL PERMITTING AND INSPECTIONS BY COLORADO STATE ELECTRICAL BOARD.
ELECTRICAL ROUGH -IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL
FINAL APPROVAL IS REQUIRED FOR CO/FINAL INSPECTION.