HomeMy WebLinkAbout0.4 Phasing4.08.05 (2) (i) PHASING (i) If more than one phase is proposed, a phasing plan shall be included in the application that delineates the proposed phasing of the development. (A. 97-109) Initiation Phase: Within one year of approval of the PUD amendment, a preliminary plan application for subdivision of the entire PUD shall be submitted to the County. The phasing as defined below is the currently anticipated sequence of development of the PUD. However, market conditions and construction implications may cause the Applicant to request modification of the sequence of the development of these phases. The configuration of the below described phases allows for utilities and roads in a manner such that if subsequent phases are not developed for some time, the completed areas of the development will function effectively. The applicant requests that with the approval of the Elk Meadows PUD, the sequence of phasing construction may be modified through the subdivision review process and not require an amendment of the originally approved PUD. See Section 4.08.05 (7) (b) of this Application for a Development Schedule for the below listed phases. Phase A Phase B Phase C Phase D The initial phase of development includes realignment of Four Mile Road, east and west entries into the property, road and utilities as needed to serve the lots within the Attached Residential Zone District; all residential lots within the Attached Residential Zone District (lots 54-63), relocation and stabilization of log barn, landscaping of both entries and the landscaping and installation of children's play equipment and public parking within the Community Facilitates Open Space Zone District. Additional improvements outside of the portrayed boundaries of Phase A will include core elements of the domestic water system (wells, storage tank and transmission lines), core elements of the raw water irrigation system (pond, pumping facilities and main deliver lines) and the commuminty pedestrian trail paralleling Four Mile Road extending from the north boundary to the south boundary of the PUD. Affordable Housing units will be constructed on lots within the Attached Housing Zone District as required by the platting of the remaining development phases. Access road and services to Lots 1 through 21 and 59 through 62 in the East Meadow neighborhood. Construction of the gravel pedestrian trail extending east along Four Mile Creek looping around lot 18 — 21 following the main access road and tying back into the "Four Mile Valley Public Trail". If Phase A is built without Phase B, a temporary looped access road will be provided. Access road and services to Lots 22 through 58 and 63 through 72 in the East Meadow neighborhood, the East Meadow open space park and trails and development of the Four Mile Creek Park landscape improvements. Access road and services to Lots 1 through 9in the South Meadow neighborhood. The public pedestrian trail from Four Mile Road to the west end of Phase D and the trail between Lots 5 & 6. This phase may also include gross earthwork on the access road to the Upper Meadow neighborhood. Phase E Phase F Phase G Access road and services to all remaining lots of the South Meadow neighborhood and the open space park in this neighborhood. Phase E assumes Phase D access is complete, but a looped access road following the emergency access and main road through Phase F will need to be provided as shown on the "Construction Phasing Plan." Access road and services to Lots 1 through 23 and Lots 37 through 41 in the Upper Meadow neighborhood including the emergency access drive/pedestrian trail connecting the main entry road to Upper Meadows loop road. A looped access road following the emergency access and main road through Phase G will need to be provided as shown on the "Construction Phasing Plan." Access and services to Lots 24 through 36 and Lots 42 through 55, public parking facility and the observation deck and shelter. The public pedestrian trail from Phase F to the west edge of the PUD. PHASING PLAN PHASE E PHASE A PHASE D PHASE B PROVIDE TEMPORARY LOOPED ACCESS FOR PHASE E. (SEE NOTE 2) W PHASE B IS CONSTRUCTED WITHOUT PHASE C PROVIDE TDAPORARY LOOPED ACCESS FOR PHASE S. (SEE NOTE 2) PROVIDE TEMPORARY LOOPED ACCESS FOR PHASE F. (SEE NOTE 2) north LEGEND NOTES PHASE A - 10 LOTS PHABE 8 - 25 LOTS PHASE C - 47 LOTS PHASE 0 - 0 LOTS PHASE E - 44 LOTS PHASE F - 28 LOTS PHASE 2 - 27 LOTS • TEMPORARY ROAD f 834000 ENT Or FOUR BCE ROAD AVD THE PRCPO5ED P 4STRJAR PA 714 ALOVO FOUR MILE ' MUSE BE COM8041108 IMMO RAF RBST PNAtt OF COHSERUC71PA: 2) ANY PHASE OF CONS RUCOON ON AA44OYEMi7RS THAT 8500555 LOPPED ACCESS 77 SE PROVIDED MUSE BE ADEQUATE FOR f71ER05442r Tp5OLES ANO PROPERLY MAWTA.WED. GRAPHIC SCALE (IN PSI') 1 face - DDD a F 6-85-07 ■RM' now 6 PHASES 70 7 CdB DPRI2NOINEERINI7 LLE ' VIL C' l/LYANTS} 802 mug SIHFIT. 55034 43 CABBOH5ALL CO 85671 f07tl7 304-8111 DATE REVISION GARFIELD COUNTY RESERVE AT ELK MEADOWS CONSTRUCTION PHASING PLAN DES. YTN Elf. YTN DR. 11112 _ DITA' FILE N0. 'SHEET JTBO/B.Of . nw (b) A development schedule indicating the approximate dates when construction of the various stages of the PUD can be expected to begin and be completed; Initiation Phase: Within one year of approval of the PUD amendment, a preliminary plan application for subdivision of the entire PUD shall be submitted to the County. The phasing schedule as defined below is the currently anticipated sequence of development of the Elk Meadows PUD. However, market conditions and construction implications may cause the Applicant to modify the sequence of the development of these phases. The configuration of the below described phases allows for utilities and roads in a manner such that if subsequent phases are not developed for some time, the completed areas of the development will function effectively. The following scheduled date for each phase are based on the assumption that the PUD receives approval by the Board of County Commissioners in June of 2007. Phase A The initial phase of development includes realignment of Four Mile Road, east and west entries into the property, road and utilities as needed to serve the lots within the Attached Residential Zone District; all residential lots within the Attached Residential Zone District (lots 54-63), relocation and stabilization of log barn, landscaping of both entries and the landscaping and installation of children's play equipment and public parking within the Community Facilities Open Space Zone District. Additional improvements outside of the portrayed boundaries of Phase A will include core elements of the domestic water system (wells, storage tank and transmission lines), core elements of the raw water irrigation system (pond, pumping facilities and main deliver lines) and the community pedestrian trail paralleling Four Mile Road extending from the north boundary to the south boundary of the PUD. Affordable Housing units will be constructed on lots within the Attached Housing Zone District as required by the platting of the remaining development phases. Schedule: Completion of infrastructure by the end of June 2010. Phase B Access road and services to Lots I through 21 and 59 through 62 in the East Meadow neighborhood. Construction of the gravel pedestrian trail extending east along Four Mile Creek looping around lot 18 — 21 following the main access road and tying back into the "Four Mile Valley Public Trail". If Phase A is built without Phase B, a temporary looped access road will be provided. Schedule: Completion of infrastructure by the end of June 2012 Phase C Access road and services to Lots 22 through 58 and 63 through 72 in the East Meadow neighborhood, the East Meadow open space park and trails and development of the Four Mile Creek Park landscape improvements. Schedule: Completion of infrastructure by the end of June 2014 Phase D Access road and services to Lots 1 through 9in the South Meadow neighborhood. The public pedestrian trail from Four Mile Road to Phase E Phase F Phase G the west end of Phase D and the trail between Lots 5 & 6. This Ubase may also include gross earthwork on the access road to the pper Meadow neighborhood. Schedule: Completion of infrastructure by the end of June 2016 Access road and services to all remaining lots of the South Meadow neighborhood and the open space park in this neighborhood. Phase E assumes Phase D access is complete, but a looped access road following the emergency access and main road through Phase F will need to be provided as shown on the "Construction Phasing Plan." Schedule: Completion of infrastructure by the end of June 2018 Access road and services to Lots 1 through 23 and Lots 37 through 41 in the Upper Meadow neighborhood including the emergency access drive/pedestrian trail connecting the main entry road to Upper Meadows loop road. A looped access road following the emergency access and main road through Phase G will need to be provided as shown on the "Construction Phasing Plan." Schedule: Completion of infrastructure by the end of June 2020 Access and services to Lots 24 through 36 and Lots 42 through 55, public parking facility and the observation deck and shelter. The public pedestrian trail from Phase F to the west edge of the PUD. Schedule: Completion of infrastructure by the end of June 2022