HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLRE-01-21-6643
BH Holdings, LLC
231 Blue Heron Vista — Glenwood Springs, Colorado
Ironbridge PUD, Phase II — Lot 276
1) ALL WORK SHALL COMPLY WITH THE 2015 INTERNATIONAL RESIDENTIAL CODE (IRC)
AND 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC).
2) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY BUILDING REQUIREMENTS.
REDLINED NUMERICAL NOTATIONS ON PLANS REFER TO ANNOTATED ITEMS ON THE
ATTACHED "RESIDENTIAL PLAN REVIEW LIST".
3) PRIOR TO INSTALLATION OF CONCRETE FOUNDATION GEOTECHNICAL ENGINEER TO
PERFORM OPEN -HOLE SOILS REPORT TO VERIFY MINIMUM SOILS BEARING PRESSURE
OF 1,500 P.S.F. AND PLACEMENT OF 10-FEET OF COMPACTED STRUCTURAL FILL BELOW
FOUNDATION AS PER SOILS REPORT. CONTRACTOR SHALL PROVIDE COPY OF GEOTECH
ENGINEER'S WET -SEALED REPORT FOR INSPECTOR REVIEW AT TIME OF UNDERGROUND
PLUMBING INSPECTION.
4) EXTERIOR WALLS, OPENINGS, AND PROJECTIONS WITHIN 5 FEET OF PROPERTY LINE
SHALL COMPLY WITH 2015 I.R.C., TABLE R302.1 FOR FIRE -RATED CONSTRUCTION.
5) A LOT IMPROVEMENT CERTIFICATE SEALED BY A COLORADO LICENSED SURVEYOR
IS REQUIRED AT FRAME INSPECTION TO VERIFY STRUCTURE (INCLUDING ROOF
OVERHANGS) WILL BE IN COMPLIANCE WITH BUILDING SETBACK REQUIREMENTS -
INCLUDING EASEMENTS AS SHOWN ON THE FINAL PLAT -AND I.R.C. REQUIREMENTS
AS DESCRIBED IN ITEM #4 ABOVE.
6) STRUCTURAL ENGINEER SHALL BE RESPONSIBLE FOR REVIEW AND INSPECTION OF
CONCRETE MAT FOUNDATION, INCLUDING PLACEMENT OF STEEL REINFORCEMENT
BARS & ANCHOR BOLTS. PROVIDE ENGINEER'S SEALED APPROVAL REPORT AT FRAME
INSPECTION.
7) ELECTRICAL PERMITTING AND INSPECTIONS BY COLORADO STATE ELECTRICAL BOARD.
ELECTRICAL ROUGH -IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL
FINAL APPROVAL IS REQUIRED FOR FINAL INSPECTION & CERTIFICATE OF OCCUPANCY.