Bill Gavette < gavette@carbondalefire.org >
Monday, April26, 20212:47 PM
Matt Provost; Andy Schwaller
brandy@affordablefireinc.com
lExternall 32 Fenwick - Fire Sprinkler Rough-in
Matt & Andy,
The fire sprinkler rough-in and hydro test for 32 Fenwick has been completed and approved
Thanks,
BillGavette
Deputy Chief
Carbondale & Rural Fire Protection District
www.ca rbonda lefi re.org
970-963-249L
Frax, [Ms, nËscuÊ
From : Bra ndy Remy Ima ilto : bra ndy@affordablefireinc.com]
Sent: Tuesday, April 20, 2021 9:04 AM
To: Bill Gavette
Subject: 32 Fenwick
Good Morning,
Last week a hydro inspection was done at 32 Fenwick via email and pictures with Rodney Moyer.
yesterday a drywall inspection was completed but they will not sign off until there is confirmation from you
that the hydro passed.
Please respond with confirmation or sign the permit card on site.
Thank you!