HomeMy WebLinkAboutConditions of PermitCONDITIONS o F PERMIT
BLM F-08-22-7775
4C Ranch Investment LLC
NEW IRC/ IBC MODULAR DWELLING ON FOUNDATION CRAWL SPACE WITH
ATTACHED CARPORTAND UNFINISHED BONUS ROOM ABOVE, SERVED BY NEW
O NSITE WASTEWATER TREATM ENT SYSTEM
9023 CR 3,1 2, NEW CASTLE
sEC. 34,T.06, R.90 - 218334300058
1) MANUFACTURED HOUSES ARE REGULATED & TNSPECTED BY COLORADO DEPT. OF
HOUSTNG (C.D.O.H.)AND ALL FACTORY-BUtLT RESIDENTIAL STRUCTURES INSTALLED lN
GARFIELD COUNTY MUST MEET C.D.O.H. GUIDELINES FOR MANUFACTURE AND
INSTALLATION ATTHE JOB SITE.
2l FOUNDATTON CRAWL SPACE & ANY S|TE CONSTRUCTED DECKS i PORCHES AND
CARPORTS SHALL COMPLY WITH 2015 I.R.C., 2OO9 I.E.C.C. AND MANUFACTURER'S
I NSTALLATION REOUI REMENTS.
3) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REOUIREMENÏS AND
MAN U FACTU RER'S I NSTALLATION REOU I REMENTS.
4\ ALL pLUMBtNc AND cAS ptptNc CONNECTTONS MUST BE PERFORMED BY A COLORADO
LICENSED PLUMBER, AND ALL ELECTRICAL CONNECTIONS MUST BE PERFORMED BY A
COLORADO LICENSED ELECTRICIAN.
5) ELECTRTCAL pERMtTTtNc AND TNSPECTTONS BYCOLORADO STATE ELECTRIC BOARD.
ELECTRICAL ROUGH.IN APPROVAL IS REOUIRED AT BASEMENT FRAME INSPECTION.
ELECTRICAL FINAL APPROVAL REOUIRED FOR FINAL INSPECTION & CERT. OF
OCCUPANCY.
ó) pRtoRTo FTNAL BUtLDtNG TNSPECTION & CERTIFICATE OF OCCUPANCY, PROVIDE
BUILDING INSPECTOR WITH FINAL APPROVAL / SIGN-OFF FROM GARFIELD COUNTY'S
PUBLIC HEALTH DEPARTMENT FOR INSTALLATION OF THE ON.SITE WASTEWATER
TREATMENT SYSTEM.
7) GARF|ELD COUNTY BUTLDtNG DEPT. INSPECTTONS TO INCLUDE THE FOLLOWING:
A. FOOTINGS DESIGNED AT 1,500 psf OPEN HOLE SOILS REPORT lS REOUIRED AT FIRST
FOOTING INSPECTION
B. FOUNDATION
C. SEPTIC SYSTEM CONNECTION
D. PLUMBING/GAS
E. SITE / CRAWL SPACE FRAMING CONNECTIONS, STICK.BUILT CARPORT / BONUS ROOM
FRAMING & PRE-ENGINEERED ROOF TRUSSES, AND ANY EXTERIOR DECKS BALCONIES,
STAIRS, DOOR LANDINGS TO BE COMPLETED AT FRAMING INSPECTION.
F. FINAL INSPECTION & CERTIFICATE OF OCCUPANCY*
*NOTE: GARFIELD COUNTY REOUIRES C.D.O.H. INSTALLATION INSIGNIATO BE
AFFTXED pRtOR TO FTNAL BUTLDtNG TNSPECTION & CERTTFTCATE OF QCCUPANCY
B) ANy CONSTRUCTTON ACT|VTTY THAT CHANGES THE BASIC CHARACTER OR TOPOGRAPHY
OF THE NATURAL LAND LOCATED IN THE 1OO-YEAR FLOODPLAIN MUST FIRST OBTAIN A
,FLOOD PLAI N DEVELOPM ENT PERM IT' TH ROUG H GARFIELD COU NTY'S PLAN N I NG DEPT.