June 20, 2022 Project No. C1729
Kurt Carruth
kurt@hinge-architects.com
Subsurface Investigation and Onsite Wastewater Treatment System Design
4-Bedroom Residence + 1-Bedroom ADU
5011 CR 154
Garfield County, Colorado
Kurt,
CBO Inc. performed a subsurface investigation and completed an onsite wastewater treatment system
(OWTS) design for the subject residence. The 1.35-acre property is located outside of Glenwood
Springs, in an area where OWTSs and wells are necessary.
Legal Description: Section: 1 Township: 7 Range: 89 Subdivision: ICE MINOR SUBDIVISION-AMENDED
Lot: 3 1.35 ACRES
Parcel ID: 2395-012-01-003
SITE CONDITIONS A 3-bedroom residence presently exists on the property. The residence is served by an existing OWTS.
The existing OWTS consists of one 1250-gallon concrete septic tank followed by a soil treatment area
(STA) comprised of a pipe and gravel seepage bed measuring 18’ x 45’ with 3’ of gravel under the
perforated pipe. Individual Sewage Disposal System (ISDS) Permit 1348 documents this system. The
permit received final approval on November 23, 1983. This system will be abandoned.
A remodel to the residence is proposed which will result in 4-bedrooms in the residence and an attached
1-bedroom additional dwelling unit (ADU).
The residence is served by a private well on the property. The well is greater than 50-feet from the
proposed septic tank and greater than 100-feet from the proposed soil treatment area (STA). There is
also a well on the neighboring property to the northwest. This well has been verified to be greater than
100-feet to the proposed OWTS components.
The Roaring Fork River runs to the southwest of the residence. The OWTS components will be located
greater than 50-feet from the edge of the river.
The proposed STA location has an approximate five percent slope to the southwest toward the river. The
area is vegetated with native grasses.
There should be no traffic or staging of material over the future STA site to avoid compaction of soils
prior to construction of the STA.
Page 2
SUBSURFACE
The subsurface was investigated on April 29, 2022 by digging one soil profile test pit excavation (Test Pit). A
visual and tactile soil analysis was completed by Carla Ostberg at the time of excavation.1 Only one test pit
was excavated in an effort not to disturb the existing STA.
The materials encountered in Test Pit #1 consisted of reddish brown topsoil sandy loam to a maximum
depth explored of 6.5-feet. No bedrock or groundwater was encountered.
A sample of the soil was taken from Test Pit #1 at 3-feet below grade. Soil structure grade was
moderate. The soil formed a ball and a ribbon less than 1-inch in length before breaking. Soil structure
shape was blocky and consistence was friable. Soil texture was gritty.
STA sizing is based on Soil Type 2, Sandy Loam with moderate structure grade. Pressure-dosed, over-
excavated, unlined sand filters with a minimum of 2-feet of sand filter material (Secondary Sand) are
proposed. A long term acceptance rate (LTAR) of 0.8 gallons per square foot will be used to
design the OWTS.
DESIGN SPECIFICATIONS The existing septic tank will be abandoned by pumping the contents and crushing the top, bottom, and
sides and filling the void with onsite material. If the existing STA is encountered during excavation for the
new STA, any saturated soils will be over-excavated and staged for drying prior to disposal.
Design Calculations:
Average Design Flow = 75 GPD x 2 people/bedroom x 3 Bedrooms + 75 GPD (4th bedroom) + 150 GPD (1-
Bedroom ADU) = 675 GPD
LTAR = 0.8 GPD/SF (Base Soil Type 2, over-excavated sand filter)
675 GPD / 0.8 GPD/SF = 843.75 SF
The new OWTS design is based on 4-bedrooms in the Main House and a 1-bedroom ADU. An average
daily wastewater flow of 675 GPD will be used.
For the purposes of this OWTS design, Benchmark Elevation has been established as 100’ as the
existing sewer line that enters the existing septic tank. CBO Inc. should be notified of any discrepancies
or problems with grade elevations of proposed components during installation of the OWTS.
OWTS Component Minimum Elevation
Primary Tank Inlet Invert Approximate horizontal distance 6’ / min. 2% fall to
septic tank / min. 1.5” fall
Automatic Distributing Valve Approximate horizontal distance 40’ / min. 1% rise
for drain back / min. 5” rise
Infiltrative Surface Approximate horizontal distance 20’ / min. 1% fall
to furthest bed / min. 2.5” fall
*Elevations are based upon standard OWTS installation practices. Component elevations may change during
installation due to site conditions. Minimum grade refers to piping between components.
The existing sewer line from the house to the existing septic tank will remain in use. We explored the
sewer line with a camera, and it was found to be in good condition.
1 Carla Ostberg holds a Certificate of Attendance and Examination from the CPOW Visual and Tactile
Evaluation of Soils Training.
Page 3
A clean out should be installed in the existing sewer line and a new section of 4-inch diameter SDR-35
sewer line run to the new septic tank.
The system installation will include a 1500-gallon, two-compartment Infiltrator® poly septic tank with an
effluent filter on the outlet tee followed by a 500-gallon, single compartment Infiltrator® poly pump
chamber with an Orenco® Biotube Pump Vault and an Orenco® PF3005 pump. Risers must bring the
manhole lids to grade for access. If more than one riser is added to the septic tank, an extension handle
must be installed on the effluent filter. The floats should be set to dose approximately 80 gallons each
pump cycle, allowing approximately 4 gallons of drain back after each pump cycle. A pump curve is
enclosed. The control panel for the pump must be located within line of sight of the septic tank. We
recommend Valley Precast out of Buena Vista be contracted for start-up of the pumping system.
Pump Table
Dose Range Max = 172.75 gal. (675 GPD x
25% + 4 gal drain back)
Min. 64 gal. (15 gal x 4) + 4 gal
drain back
Dose Setting 80 gallons/dose 4 gallons drain back (40’ / 1.5”
diameter pump line)
Float Separation 500 gallon single-compartment
Infiltrator® poly pump chamber
6” on/off float separation
Pump Criteria 28.5 gallons per minute (GPM) 25.2 feet total dynamic head
(TDH)
Effluent will be pumped through a 1.5-inch diameter pump line to an Orenco® automatic distributing valve
(ADV), model 6402. This pump line must have a minimum 1% grade for proper drain back into the tank after
each pump cycle. The ADV must be placed at a high point in the system in an insulated riser with access
from grade. Screened rock must be placed below the ADV to support the ADV and to assure the clear pipes
exiting the ADV remain visible for future inspection and maintenance.
Effluent will be pressure dosed through 1.5-inch diameter distribution lines to two 10’ x 42.5’ beds. A
minimum of 2-feet of sand filter material will be installed in the over-excavated footprints. Sand filter material
must be clean, coarse sand, all passing a screen having four meshes to the inch. The sand must have an
effective size between 0.15 and 0.60 mm. The uniformity coefficient must be 7.0 or less. Material meeting
ASTM 33, for concrete sand, with three percent or less fines passing 200 mesh sieve may be used. A
gradation of the sand media must be submitted to this office prior to obtaining the sand.
Laterals must be 1.5-inches in diameter with 5/32-inch diameter orifices facing down, spaced 3-feet on
center, installed on the center of each GeoMat™ with the filter fabric over the laterals. Three 39” wide
GeoMat™ sheets must be placed on each 10-foot wide bed. All material associated with the GeoMat™
installation must be proprietary products associated with the GeoMat™, including orifice shields and
geotextile fabric. Manufacturer instructions must be followed regarding installation of the GeoMat™.
Each 1.5-inch diameter lateral must end in a sweeping ell facing up with a ball valve for flushing. Valves
should be placed in a 10-inch sprinkler box for access. Laterals must be covered by a soil separation
fabric and at least 1-foot of topsoil or other suitable soil able to support vegetative growth. There shall be no
cobble-sized (<2.5”) or greater rock in final cover over the GeoMat™. Inspection ports must be placed at
each corner of each bed. Ports may be cut to grade and covered with a valve box for access.
Construction must be according to Garfield County On-Site Wastewater Treatment System Regulations, the
OWTS Permit provided by Garfield County Building Department, and this design.
Page 4
COMPONENT SPECIFICATIONS
The component manufacturers are typical of applications used by contractors and engineers in this area.
CBO Inc. must approve alternative components prior to installation of the OWTS. Requests must
be submitted, in writing, to our office for approval prior to installation. Component technical data
sheets are available upon request.
COMPONENT MANUFACTURER MODEL NO. COMMENTS
Septic Tanks Infiltrator® 1530T-2CP 1500-gallon, two-
compartment poly septic
Effluent Filter Orenco® 4-inch full size filter
Risers and Lids Orenco® Risers and Lids
Pump Orenco® PF300511 ½ HP
120 Volt
pump
Biotube ProPak Pump Package Orenco® BPP30DD Vault, Filter, Panel (demand dose)
Tank Risers and Lids Orenco® Double-walled PVC Risers and Lids (24” diameter)
ADV Orenco® V6402A 1.5” Inlet and Outlets
ADV Riser and Lid Orenco® Double-walled PVC Risers
and Lids (30” diameter) GeoMat™ GeoMatrix Systems, LLC 243’ GeoMat™ (39” sheets)
78 orifice shields
Flushing Assembly Orenco® 1.5” diameter (2) 45° or 90° long sweep only (6 total)
INSTALLATION CONTRACTOR
CBO Inc. expects that the installer be experienced and qualified to perform the scope of work outlined in this
design. The installer must review this design thoroughly and coordinate with our office in advance of
installation. Any additional conditions in this design or county permit must be completed and documented
prior to final approval of the OWTS installation. Communication between the installer and this office is
expected throughout the installation.
INSTALLATION OBSERVATIONS CBO Inc. must view the OWTS during construction. The OWTS observation should be performed before
backfill, after placement of OWTS components. Septic tanks, distribution devices, pumps, dosing
siphons, and other plumbing, as applicable, must also be observed. CBO Inc. should be notified 48 hours
in advance to observe the installation.
In an effort to improve the accuracy of the record drawing, we request that the installer provide a
sketch of the installation, including path of the sewer lines, water line installation (if applicable),
septic tank location, STA location, and measurements from building corners or another fixed
objects on the property. This sketch is most easily provided on Sheet W2.0 of the OWTS Design
Packet. Photographs of the installation and final cover are also requested to supplement our installation
documentation.
Page 5
REVEGETATION REQUIREMENTS
An adequate layer of good quality topsoil capable of supporting revegetation shall be placed over the entire
disturbed area of the OWTS installation. A mixture of native grass seed that has good soil stabilizing
characteristics (but without taproots), provides a maximum transpiration rate, and competes well with
successional species. No trees or shrubs, or any vegetation requiring regular irrigation shall be placed over
the STA. Until vegetation is reestablished, erosion and sediment control measures shall be implemented
and maintained on site. The owner of the OWTS shall be responsible for maintaining proper vegetation
cover.
OPERATION INFORMATION AND MAINTENANCE
The property owner shall be responsible for the operation and maintenance of each OWTS servicing the
property. The property owner is responsible for maintaining service contracts for manufactured units,
alternating STAs, and any other components needing maintenance.
Geo-fabrics or plastics should not be used over the STA. No heavy equipment, machinery, or materials
should be placed on the backfilled STA. Machines with tracks (not wheels) should be used during
construction of the STA for better weight distribution. Livestock should not graze on the STA. Plumbing
fixtures should be checked to ensure that no additional water is being discharged to OWTS. For example, a
running toilet or leaky faucet can discharge hundreds of gallons of water a day and harm a STA.
If an effluent filter or screen has been installed in the OWTS, we recommend this filter or screen be cleaned
annually, or as needed. If the OWTS consists of a pressurized pump system, we recommend the laterals be
flushed annually, or as needed.
The homeowner should pump the septic tank every two years, or as needed gauged by measurement of
solids in the tank. Garbage disposal use should be minimized, and non-biodegradable materials should not
be placed into the OWTS. Grease should not be placed in household drains. Loading from a water softener
should not be discharged into the OWTS. No hazardous wastes should be directed into the OWTS.
Mechanical room drains should not discharge into the OWTS. The OWTS is engineered for domestic waste
only.
ADDITIONAL CONSTRUCTION NOTES If design includes a pump, weep holes must be installed to allow pump lines to drain to minimize risk of
freezing. The pump shall have an audible and visual alarm notification in the event of excessively high-
water conditions and shall be connected to a control breaker separate from the high-water alarm breaker
and from any other control system circuits. The pump system shall have a switch so the pump can be
manually operated.
Excavation equipment must not drive in the excavation of the STA due to the potential to compact soil.
Extensions should be placed on all septic tank components to allow access to them from existing grade.
Backfill over the STA must be uniform and granular with no material greater than minus 3-inch.
LIMITS: The design is based on information submitted. If soil conditions encountered are different from conditions
described in report, CBO Inc. should be notified. All OWTS construction must be according to the county
regulations. Requirements not specified in this report must follow applicable county regulations. The
contractor should have documented and demonstrated knowledge of the requirements and regulations of
the county in which they are working. Licensing of Systems Contractors may be required by county
regulation.
Page 6
7-18-2022
Please call with questions.
Sincerely,
CBO Inc. Reviewed By:
Carla Ostberg, MPH, REHS Romeo A. Baylosis, PE
Pump Selection for a Pressurized System - Single Family Residence Project
Parameters
Discharge Assembly Size
Transport Length Before Valve
Transport Pipe Class
Transport Line Size
Distributing Valve Model
Transport Length After Valve
Transport Pipe Class
Transport Pipe Size
Max Elevation Lift
Manifold Length
Manifold Pipe Class
Manifold Pipe Size
Number of Laterals per Cell
Lateral Length
Lateral Pipe Class
Lateral Pipe Size
Orifice Size
Orifice Spacing
Residual Head
Flow Meter
'Add-on' Friction Losses
1.25
40
40
1.50
6402
20
40
1.50
5
6
40
1.50
6
40.5
40
1.50
5/32
3
5
None
0
inches
feet
inches
feet
inches
feet
feet
inches
feet
inches
inches
feet
feet
inches
feet
Calculations
Minimum Flow Rate per Orifice
Number of Orifices per Zone
Total Flow Rate per Zone
Number of Laterals per Zone
% Flow Differential 1st/Last Orifice
Transport Velocity Before Valve
Transport Velocity After Valve
0.68
42
28.5
3
0.8
4.5
4.5
gpm
gpm
%
fps
fps
Frictional Head Losses
Loss through Discharge
Loss in Transport Before Valve
Loss through Valve
Loss in Transport after Valve
Loss in Manifold
Loss in Laterals
Loss through Flowmeter
'Add-on' Friction Losses
5.7
1.9
6.5
0.9
0.1
0.1
0.0
0.0
feet
feet
feet
feet
feet
feet
feet
feet
Pipe Volumes
Vol of Transport Line Before Valve
Vol of Transport Line After Valve
Vol of Manifold
Vol of Laterals per Zone
Total Vol Before Valve
Total Vol After Valve
4.2
2.1
0.6
12.8
4.2
15.6
gals
gals
gals
gals
gals
gals
28.5
25.2
gpm
feet
0 5 10 15 20 25 30 35 400
50
100
150
200
250
300
Net Discharge (gpm)
PumpData
PF3005 High Head Effluent Pump
30 GPM, 1/2HP
115/230V 1Ø 60Hz, 200V 3Ø 60Hz
PF3007 High Head Effluent Pump
30 GPM, 3/4HP
230V 1Ø 60Hz, 200/460V 3Ø 60Hz
PF3010 High Head Effluent Pump
30 GPM, 1HP
230V 1Ø 60Hz, 200/460V 3Ø 60Hz
PF3015 High Head Effluent Pump
30 GPM, 1-1/2HP
230V 1Ø 60Hz, 200/230/460V 3Ø 60Hz
Legend
System Curve:
Pump Curve:
Pump Optimal Range:
Operating Point:
Design Point:
5011 CR 154 Legend
5011 Co Rd 154
100 ft
N
➤➤
N
Garfield County, CO
Developed by
Account
Number
R011607
Par cel Number 239501201003
Acr es 1
Land SqFt 0
T ax Ar ea 011
2019 Mill Levy 79.7760
Physical
Addr ess
5011 154 C OUNTY RD
GLENWO O D SP RINGS 81601
Ow ner Address NIC KOL AY, C L IVE &
NAO ISE
15818 RO SEVIEW LANE
C YPRESS TX 774296703
2019 T otal A ctual
Va lue
$1,083,320 L ast 2 Sales
Date Pr ice
1/2/2020 $1,074,000
6/4/1993 $0
Date created: 6/2/2022
Last Data Uploa ded: 6/2/2022 2:18:50 AM
230 ft
Overvi ew
Legend
Parcels
Roa ds
Parcel/Account
Number s
Highw ays
Limited Access
Highwa y
Major Road
Loca l Roa d
Minor Road
Other Road
Ra mp
Ferry
Pedestria n Way
Owner Na me
Lakes & River s
County Boundar y
Line