HomeMy WebLinkAbout1.00 General Application Materials_Part24SC-10 Chemical Treatment (CT)
CT-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Maintenance and Removal
Chemical feed systems for sedimentation ponds or tanks should be maintained in accordance with
manufacturer's recommendations and removed when the systems are no longer being used. Accumulated
sediment should be dried and disposed of either at a landfill or in accordance with applicable regulations.
Barriers and devices containing chemicals should be removed and replaced when tears or other damage to
the devices are observed. These barriers should be removed and properly disposed of when the site has
been stabilized.
Sediment Retention Device (SRD)SC-11
March 2023 SC-11
Photographs SRD-1 and SRD-2. WattleFence installed in a
channelized area with the goal of removing sediment and channel
dissipation 1); and, 2) the same device operating under heavy rain
events.
Description
A sediment retention device
(trademarked product WattleFence) is
constructed using a fleece of coconut
fiber wrapped in a biodegradable jute
woven fabric. The installed device has
a vertical height of 9" with a 6" splash
apron and is attached to wooden
stakes. Wattlefence provides the
combined features of wattles and silt
fence including sediment reduction
and turbidity reduction.
Appropriate Uses
Sediment retention devices can be
used in the following applications:
As perimeter control for stockpiles
and the site.
As check dams in small drainage
ditches.
For channel dissipation in areas of
concentrated flow
On disturbed slopes to shorten flow
lengths (as an erosion control).
As inlet and outlet protection.
As part of multi-layered perimeter
controls.
Sediment retention devices work well in combination with other layers of erosion and sediment controls.
Design and Installation
When installed on slopes, sediment retention devices should be installed along the contour (i.e.,
perpendicular to the flow) to avoid concentrating flows into channels. When installed for other uses, such
as perimeter control, the device should be installed in a way that will not produce concentrated flows. For
example, a "J-hook" installation may be appropriate to force runoff to pond and evaporate or infiltrate the
fencing in multiple areas rather than concentrate in one and cause erosive conditions parallel to the
control measure. An example of this kind of installation is
shown in section SC-2 (Sediment Control Logs) of this manual.
WattleFence is designed to be installed without trenching, an
advantage over sediment control logs. The device is trenched
at intervals depending on the desired application.Yes
N
Western Green WattleFence Product Literature
SC-11 Sediment Retention Device (SRD)
SC-11 March 2023
Design details and notes for sediment retention devices are presented below. The device must be
properly trenched and staked into the ground to prevent undercutting, bypassing and displacement.
Improper installation can lead to poor performance. Be sure that sediment retention devices are properly
trenched, anchored and tightly jointed.
Maintenance and Removal
Sediment retention devices are designed to allow runoff to flow through the control measure, as long as
they are properly maintained and kept free of sediment build up. Remove accumulated sediment before
the depth is one-half the height of the device and repair damage to the device, typically by replacing the
damaged section.
Sediment retention devices are designed to biodegrade. Once the upstream area is stabilized, remove and
properly dispose of the device. Areas disturbed beneath the logs may need to be seeded and mulched.
Sediment retention devices are biodegradable and may occasionally be left in place during final
stabilization. However, removal is typically recommended after final reclamation of the site is achieved.
Western Green WattleFence Product Literature
Sediment Retention Device (SRD)SC-11
March 2023 SC-11 Western Green WattleFence Product Literature
SC-11 Sediment Retention Device (SRD)
SC-11 March 2023 Western Green WattleFence Product Literature
Construction Phasing/Sequencing (CP)SM-1
November 2010 Urban Drainage and Flood Control District CP-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph CP-1. Construction phasing to avoid disturbing the
entire area at one time. Photo courtesy of WWE.
Description
Effective construction site management
to minimize erosion and sediment
transport includes attention to
construction phasing, scheduling, and
sequencing of land disturbing activities.
On most construction projects, erosion
and sediment controls will need to be
adjusted as the project progresses and
should be documented in the SWMP.
Construction phasing refers to
disturbing only part of a site at a time to
limit the potential for erosion from
dormant parts of a site. Grading
activities and construction are completed
and soils are effectively stabilized on one
part of a site before grading and
construction begins on another portion of the site.
Construction sequencing or scheduling refers to a specified work schedule that coordinates the timing of
land disturbing activities and the installation of erosion and sediment control practices.
Appropriate Uses
All construction projects can benefit from upfront planning to phase and sequence construction activities
to minimize the extent and duration of disturbance. Larger projects and linear construction projects may
benefit most from construction sequencing or phasing, but even small projects can benefit from
construction sequencing that minimizes the duration of disturbance.
Typically, erosion and sediment controls needed at a site will change as a site progresses through the
major phases of construction. Erosion and sediment control practices corresponding to each phase of
construction must be documented in the SWMP.
Design and Installation
Control measures appropriate to the major phases of development should be identified on construction
drawings. In some cases, it will be necessary to provide several drawings showing construction-phase
control measures placed according to stages of development (e.g., clearing and grading, utility
installation, active construction, final stabilization). Some municipalities in the Denver area set
maximum sizes for disturbed area associated with phases of a construction project. Additionally,
requirements for phased construction drawings vary among local governments within the UDFCD
boundary. Some local governments require separate erosion
and sediment control drawings for initial control measures,
interim conditions (in active construction), and final
stabilization. Erosion Control Moderate
Sediment Control Moderate
Site/Material Management Yes
SM-1 Construction Phasing/Sequencing (CP)
CP-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Typical construction phasing control measures include:
Limit the amount of disturbed area at any given time on a site to the extent practical. For example, a
100-acre subdivision might be constructed in five phases of 20 acres each.
If there is carryover of stockpiled material from one phase to the next, position carryover material in a
location easily accessible for the pending phase that will not require disturbance of stabilized areas to
access the stockpile. Particularly with regard to efforts to balance cut and fill at a site, careful
planning for location of stockpiles is important.
Typical construction sequencing control measures include:
Sequence construction activities to minimize duration of soil disturbance and exposure. For example,
when multiple utilities will occupy the same trench, schedule installation so that the trench does not
have to be closed and opened multiple times.
Schedule site stabilization activities (e.g., landscaping, seeding and mulching, installation of erosion
control blankets) as soon as feasible following grading.
Install initial erosion and sediment control practices before construction begins. Promptly install
additional control measures for inlet protection, stabilization, etc., as construction activities are
completed.
Table CP-1 provides typical sequencing of construction activities and associated control measures.
Maintenance and Removal
When the construction schedule is altered, erosion and sediment control measures in the SWMP and
construction drawings should be appropriately adjusted to reflect actual "on the ground" conditions at the
construction site. Be aware that changes in construction schedules can have significant implications for
site stabilization, particularly with regard to establishment of vegetative cover.
Construction Phasing/Sequencing (CP)SM-1
November 2010 Urban Drainage and Flood Control District CP-3
Urban Storm Drainage Criteria Manual Volume 3
Table CP-1. Typical Phased Control Measure Installation for Construction Projects
Project
Phase Control Measures
Pre-
disturbance,
Site Access
Install sediment controls downgradient of access point (on paved streets this may consist
of inlet protection).
Establish vehicle tracking control at entrances to paved streets. Fence as needed.
Use construction fencing to define the boundaries of the project and limit access to areas of
the site that are not to be disturbed.
Note: it may be necessary to protect inlets in the general vicinity of the site, even if not
downgradient, if there is a possibility that sediment tracked from the site could contribute
to the inlets.
Site Clearing
and Grubbing
Install perimeter controls as needed on downgradient perimeter of site (silt fence, wattles,
etc).
Limit disturbance to those areas planned for disturbance and protect undisturbed areas
within the site (construction fence, flagging, etc).
Preserve vegetative buffer at site perimeter.
Create stabilized staging area.
Locate portable toilets on flat surfaces away from drainage paths. Stake in areas
susceptible to high winds.
Construct concrete washout area and provide signage.
Establish waste disposal areas.
Install sediment basins.
Create dirt perimeter berms and/or brush barriers during grubbing and clearing.
Separate and stockpile topsoil, leave roughened and/or cover.
Protect stockpiles with perimeter control measures. Stockpiles should be located away
from drainage paths and should be accessed from the upgradient side so that perimeter
controls can remain in place on the downgradient side. Use erosion control blankets,
temporary seeding, and/or mulch for stockpiles that will be inactive for an extended period.
Leave disturbed area of site in a roughened condition to limit erosion. Consider
temporary revegetation for areas of the site that have been disturbed but that will be
inactive for an extended period.
Water to minimize dust but not to the point that watering creates runoff.
SM-1 Construction Phasing/Sequencing (CP)
CP-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Project
Phase Control Measures
Utility And
Infrastructure
Installation
In Addition to the Above Control Measures:
Close trench as soon as possible (generally at the end of the day).
Use rough-cut street control or apply road base for streets that will not be promptly
paved.
Provide inlet protection as streets are paved and inlets are constructed.
Protect and repair control measures, as necessary.
Perform street sweeping as needed.
Building
Construction
In Addition to the Above Control Measures:
Implement materials management and good housekeeping practices for home building
activities.
Use perimeter controls for temporary stockpiles from foundation excavations.
For lots adjacent to streets, lot-line perimeter controls may be necessary at the back of
curb.
Final Grading
In Addition to the Above Control Measures:
Remove excess or waste materials.
Remove stored materials.
Final
Stabilization
In Addition to the Above Control Measures:
Seed and mulch/tackify.
Seed and install blankets on steep slopes.
Remove all temporary control measures when site has reached final
stabilization.
Protection of Existing Vegetation (PV) SM-2
November 2010 Urban Drainage and Flood Control District PV-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph PV-1. Protection of existing vegetation and a sensitive
area. Photo courtesy of CDOT.
Description
Protection of existing vegetation on a
construction site can be accomplished
through installation of a construction
fence around the area requiring protection.
In cases where upgradient areas are
disturbed, it may also be necessary to
install perimeter controls to minimize
sediment loading to sensitive areas such as
wetlands. Existing vegetation may be
designated for protection to maintain a
stable surface cover as part of construction
phasing, or vegetation may be protected in
areas designated to remain in natural
condition under post-development
conditions (e.g., wetlands, mature trees,
riparian areas, open space).
Appropriate Uses
Existing vegetation should be preserved for the maximum practical duration on a construction site
through the use of effective construction phasing. Preserving vegetation helps to minimize erosion and
can reduce revegetation costs following construction.
Protection of wetland areas is required under the Clean Water Act, unless a permit has been obtained from
the U.S. Army Corps of Engineers (USACE) allowing impacts in limited areas.
If trees are to be protected as part of post-development landscaping, care must be taken to avoid several
types of damage, some of which may not be apparent at the time of injury. Potential sources of injury
include soil compaction during grading or due to construction traffic, direct equipment-related injury such
as bark removal, branch breakage, surface grading and trenching, and soil cut and fill. In order to
minimize injuries that may lead to immediate or later death of the tree, tree protection zones should be
developed during site design, implemented at the beginning of a construction project, as well as continued
during active construction.
Design and Installation
General
Once an area has been designated as a preservation area, there should be no construction activity allowed
within a set distance of the area. Clearly mark the area with construction fencing. Do not allow
stockpiles, equipment, trailers or parking within the
protected area. Guidelines to protect various types of
existing vegetation follow. Protection of Existing Vegetation
Functions
Erosion Control Yes
Sediment Control Moderate
Site/Material Management Yes
SM-2 Protection of Existing Vegetation (PV)
PV-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Surface Cover During Phased Construction
Install construction fencing or other perimeter controls around areas to be protected from clearing and
grading as part of construction phasing.
Maintaining surface cover on steep slopes for the maximum practical duration during construction is
recommended.
Open Space Preservation
Where natural open space areas will be preserved as part of a development, it is important to install
construction fencing around these areas to protect them from compaction. This is particularly important
when areas with soils with high infiltration rates are preserved as part of LID designs. Preserved open
space areas should not be used for staging and equipment storage.
Wetlands and Riparian Areas
Install a construction fence around the perimeter of the wetland or riparian (streamside vegetation) area to
prevent access by equipment. In areas downgradient of disturbed areas, install a perimeter control such as
silt fence, sediment control logs, or similar measure to minimize sediment loading to the wetland.
Tree Protection 1
Before beginning construction operations, establish a tree protection zone around trees to be
preserved by installing construction fences. Allow enough space from the trunk to protect the root
zone from soil compaction and mechanical damage, and the branches from mechanical damage (see
Table PV-1). If low branches will be kept, place the fence outside of the drip line. Where this is not
possible, place fencing as far away from the trunk as possible. In order to maintain a healthy tree, be
aware that about 60 percent of the tree's root zone extends beyond the drip line.
Table PV-1
Guidelines for Determining the Tree Protection Zone
(Source: Matheny and Clark, 1998; as cited in GreenCO and WWE 2008)
Distance from Trunk (ft) per inch of DBH
Species Tolerance to Damage Young Mature Over mature
Good 0.5' 0.75' 1.0'
Moderate 0.75' 1.0' 1.25'
Poor 1.0' 1.25' 1.5'
Notes: DBH = diameter at breast height (4.5 ft above grade); Young = <20% of
life expectancy; Mature = 20%-80% of life expectancy; Over mature =>80% of
life expectancy
Most tree roots grow within the top 12 to 18 inches of soil. Grade changes within the tree protection
zone should be avoided where possible because seemingly minor grade changes can either smother
1 Tree Protection guidelines adapted from GreenCO and WWE (2008). Green Industry Best Management Practices (BMPs) for
the Conservation and Protection of Water Resources in Colorado: Moving Toward Sustainability, Third Release. See
www.greenco.org for more detailed guidance on tree preservation.
Protection of Existing Vegetation (PV) SM-2
November 2010 Urban Drainage and Flood Control District PV-3
Urban Storm Drainage Criteria Manual Volume 3
roots (in fill situations) or damage roots (in cut situations). Consider small walls where needed to
avoid grade changes in the tree protection zone.
Place and maintain a layer of mulch 4 to 6-inch thick from the tree trunk to the fencing, keeping a
6-inch space between the mulch and the trunk. Mulch helps to preserve moisture and decrease soil
compaction if construction traffic is unavoidable. When planting operations are completed, the mulch
may be reused throughout planting areas.
Limit access, if needed at all, and appoint one route as the main entrance and exit to the tree
protection zone. Within the tree protection zone, do not allow any equipment to be stored, chemicals
to be dumped, or construction activities to take place except fine grading, irrigation system
installation, and planting operations. These activities should be conducted in consultation with a
landscaping professional, following Green Industry BMPs.
Be aware that soil compaction can cause extreme damage to tree health that may appear gradually
over a period of years. Soil compaction is easier to prevent than repair.
Maintenance and Removal
Repair or replace damaged or displaced fencing or other protective barriers around the vegetated area.
If damage occurs to a tree, consult an arborist for guidance on how to care for the tree. If a tree in a
designated preservation area is damaged beyond repair, remove and replace with a 2-inch diameter tree of
the same or similar species.
Construction equipment must not enter a wetland area, except as permitted by the U.S. Army Corps of
Engineers (USACE). Inadvertent placement of fill in a wetland is a 404 permit violation and will require
notification of the USACE.
If damage to vegetation occurs in a protected area, reseed the area with the same or similar species,
following the recommendations in the USDCM Revegetation chapter.
Construction Fence (CF)SM-3
November 2010 Urban Drainage and Flood Control District CF-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph CF-1. A construction fence helps delineate areas where
existing vegetation is being protected. Photo courtesy of Douglas
County.
Description
A construction fence restricts site access
to designated entrances and exits,
delineates construction site boundaries,
and keeps construction out of sensitive
areas such as natural areas to be
preserved as open space, wetlands and
riparian areas.
Appropriate Uses
A construction fence can be used to
delineate the site perimeter and locations
within the site where access is restricted
to protect natural resources such as
wetlands, waterbodies, trees, and other
natural areas of the site that should not be
disturbed.
If natural resource protection is an objective, then the construction fencing should be used in
combination with other perimeter control measures such as silt fence, sediment control logs or similar
measures.
Design and Installation
Construction fencing may be chain link or plastic mesh and should be installed following manufacturer’s
recommendations. See Detail CF-1 for typical installations.
Do not place construction fencing in areas within work limits of machinery.
Maintenance and Removal
Inspect fences for damage; repair or replace as necessary.
Fencing should be tight and any areas with slumping or fallen posts should be reinstalled.
Fencing should be removed once construction is complete.
Construction Fence
Functions
Erosion Control No
Sediment Control No
Site/Material Management Yes
SM-3 Construction Fence (CF)
CF-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Construction Fence (CF)SM-3
November 2010 Urban Drainage and Flood Control District CF-3
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph VTC-1. A vehicle tracking control pad constructed with
properly sized rock reduces off-site sediment tracking.
Description
Vehicle tracking controls provide
stabilized construction site access where
vehicles exit the site onto paved public
roads. An effective vehicle tracking
control helps remove sediment (mud or
dirt) from vehicles, reducing tracking onto
the paved surface.
Appropriate Uses
Implement a stabilized construction
entrance or vehicle tracking control where
frequent heavy vehicle traffic exits the
construction site onto a paved roadway. An
effective vehicle tracking control is
particularly important during the following conditions:
Wet weather periods when mud is easily tracked off site.
During dry weather periods where dust is a concern.
When poorly drained, clayey soils are present on site.
Although wheel washes are not required in designs of vehicle tracking controls, they may be needed at
particularly muddy sites.
Design and Installation
Construct the vehicle tracking control on a level surface. Where feasible, grade the tracking control
towards the construction site to reduce off-site runoff. Place signage, as needed, to direct construction
vehicles to the designated exit through the vehicle tracking control. There are several different types of
stabilized construction entrances including:
VTC-1. Aggregate Vehicle Tracking Control. This is a coarse-aggregate surfaced pad underlain by a
geotextile. This is the most common vehicle tracking control, and when properly maintained can be
effective at removing sediment from vehicle tires.
VTC-2. Vehicle Tracking Control with Construction Mat or Turf Reinforcement Mat. This type of
control may be appropriate for site access at very small construction sites with low traffic volume over
vegetated areas. Although this application does not typically remove sediment from vehicles, it helps
protect existing vegetation and provides a stabilized entrance.
Vehicle Tracking Control
Functions
Erosion Control Moderate
Sediment Control Yes
Site/Material Management Yes
SM-4 Vehicle Tracking Control (VTC)
VTC-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Photograph VTC-2. A vehicle tracking control pad with wheel wash
facility. Photo courtesy of Tom Gore.
VTC-3. Stabilized Construction Entrance/Exit with Wheel Wash. This is an aggregate pad, similar
to VTC-1, but includes equipment for tire washing. The wheel wash equipment may be as simple as
hand-held power washing equipment to more advance proprietary systems. When a wheel wash is
provided, it is important to direct wash water to a sediment trap prior to discharge from the site.
Vehicle tracking controls are sometimes installed in combination with a sediment trap to treat runoff.
Maintenance and Removal
Inspect the area for degradation and
replace aggregate or material used for a
stabilized entrance/exit as needed. If the
area becomes clogged and ponds water,
remove and dispose of excess sediment
or replace material with a fresh layer of
aggregate as necessary.
With aggregate vehicle tracking controls,
ensure rock and debris from this area do
not enter the public right-of-way.
Remove sediment that is tracked onto the
public right of way daily or more
frequently as needed. Excess sediment
in the roadway indicates that the
stabilized construction entrance needs
maintenance.
Ensure that drainage ditches at the
entrance/exit area remain clear.
A stabilized entrance should be removed only when there is no longer the potential for vehicle tracking to
occur. This is typically after the site has been stabilized.
When wheel wash equipment is used, be sure that the wash water is discharged to a sediment trap prior to
discharge. Also inspect channels conveying the water from the wash area to the sediment trap and
stabilize areas that may be eroding.
When a construction entrance/exit is removed, excess sediment from the aggregate should be removed
and disposed of appropriately. The entrance should be promptly stabilized with a permanent surface
following removal, typically by paving.
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-3
Urban Storm Drainage Criteria Manual Volume 3
SM-4 Vehicle Tracking Control (VTC)
VTC-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Vehicle Tracking Control (VTC) SM-4
November 2010 Urban Drainage and Flood Control District VTC-5
Urban Storm Drainage Criteria Manual Volume 3
SM-4 Vehicle Tracking Control (VTC)
VTC-6 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Stabilized Construction Roadway (SCR)SM-5
November 2010 Urban Drainage and Flood Control District SCR-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph SCR-1. Stabilized construction roadway.
Description
A stabilized construction roadway is a
temporary method to control sediment
runoff, vehicle tracking, and dust from
roads during construction activities.
Appropriate Uses
Use on high traffic construction roads to
minimize dust and erosion.
Stabilized construction roadways are
used instead of rough-cut street controls
on roadways with frequent construction
traffic.
Design and Installation
Stabilized construction roadways typically involve two key components: 1) stabilizing the road surface
with an aggregate base course of 3-inch-diameter granular material and 2) stabilizing roadside ditches, if
applicable. Early application of road base is generally suitable where a layer of coarse aggregate is
specified for final road construction.
Maintenance and Removal
Apply additional gravel as necessary to ensure roadway integrity.
Inspect drainage ditches along the roadway for erosion and stabilize, as needed, through the use of check
dams or rolled erosion control products.
Gravel may be removed once the road is ready to be paved. Prior to paving, the road should be inspected
for grade changes and damage. Regrade and repair as necessary.
Stabilized Construction Roadway
Functions
Erosion Control Yes
Sediment Control Moderate
Site/Material Management Yes
Stabilized Staging Area (SSA) SM-6
November 2010 Urban Drainage and Flood Control District SSA-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph SSA-1. Example of a staging area with a gravel surface to
prevent mud tracking and reduce runoff. Photo courtesy of Douglas
County.
Description
A stabilized staging area is a clearly
designated area where construction
equipment and vehicles, stockpiles, waste
bins, and other construction-related
materials are stored. The contractor
office trailer may also be located in this
area. Depending on the size of the
construction site, more than one staging
area may be necessary.
Appropriate Uses
Most construction sites will require a
staging area, which should be clearly
designated in SWMP drawings. The layout
of the staging area may vary depending on
the type of construction activity. Staging areas located in roadways due to space constraints require
special measures to avoid materials being washed into storm inlets.
Design and Installation
Stabilized staging areas should be completed prior to other construction activities beginning on the site.
Major components of a stabilized staging area include:
Appropriate space to contain storage and provide for loading/unloading operations, as well as parking
if necessary.
A stabilized surface, either paved or covered, with 3-inch diameter aggregate or larger.
Perimeter controls such as silt fence, sediment control logs, or other measures.
Construction fencing to prevent unauthorized access to construction materials.
Provisions for Good Housekeeping practices related to materials storage and disposal, as described in
the Good Housekeeping Control Measure Fact Sheet.
A stabilized construction entrance/exit, as described in the Vehicle Tracking Control Control Measure
Fact Sheet, to accommodate traffic associated with material delivery and waste disposal vehicles.
Over -sizing the stabilized staging area may result in disturbance of existing vegetation in excess of that
required for the project. This increases costs, as well as
requirements for long-term stabilization following the
construction period. When designing the stabilized staging area,
minimize the area of disturbance to the extent practical.
Stabilized Staging Area
Functions
Erosion Control Yes
Sediment Control Moderate
Site/Material Yes
SM-6 Stabilized Staging Area (SSA)
SSA-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
See Detail SSA-1 for a typical stabilized staging area and SSA-2 for a stabilized staging area when
materials staging in roadways is required.
Maintenance and Removal
Maintenance of stabilized staging areas includes maintaining a stable surface cover of gravel, repairing
perimeter controls, and following good housekeeping practices.
When construction is complete, debris, unused stockpiles and materials should be recycled or properly
disposed. In some cases, this will require disposal of contaminated soil from equipment leaks in an
appropriate landfill. Staging areas should then be permanently stabilized with vegetation or other surface
cover planned for the development.
Minimizing Long-Term Stabilization Requirements
Utilize off-site parking and restrict vehicle access to the site.
Use construction mats in lieu of rock when staging is provided in an area that will not be disturbed
otherwise.
Consider use of a bermed contained area for materials and equipment that do not require a stabilized
surface.
Consider phasing of staging areas to avoid disturbance in an area that will not be otherwise
disturbed.
Stabilized Staging Area (SSA) SM-6
November 2010 Urban Drainage and Flood Control District SSA-3
Urban Storm Drainage Criteria Manual Volume 3
SM-6 Stabilized Staging Area (SSA)
SSA-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph TDM-1. This coffer dam, installed to allow grading and
stabilization of the stream bank, consists of concrete blocks covered
by an impermeable linear held in place by sand bags.
Description
Temporary diversion methods are used to
reroute water from a stream or restrict flows to
a designated portion of the stream channel to
allow for construction activities to take place in
the stream, along the banks or beneath the
active channel. Temporary diversion methods
are often required during the construction of
detention ponds, dams, in-stream grade control
structures, utility installation and other
activities, including maintenance, that require
working in waterways. Temporary diversion
methods include temporary diversion channels,
pump-arounds, piped diversions, coffer dams
and other similar practices. The primary
purpose of all temporary diversion methods is
to protect water quality by passing upstream
flows around the active construction zone.
Appropriate Uses
Temporary diversion methods are appropriate in situations when it is necessary to divert the flow around the
area where work is being conducted. Temporary diversion methods vary with the size of the waterway that
is being diverted.
For large streams, a temporary diversion may consist of
berms or coffer dams constructed within the stream to
confine flow to one side of the stream while work progresses
on the “dry” side of the berm. For smaller streams and often
for construction of dams and detention basins, a temporary
diversion method may divert the entire waterway. For short
duration projects (typically less than a month of active construction) with low baseflows, a pump and/or
bypass pipe may serve as a temporary diversion. Whenever a temporary diversion is used, construction
should be scheduled during drier times of the year (November through March) to the extent feasible, and
construction in the waterway should progress as quickly as practical to reduce the risk of exceeding the
temporary diversion capacity. Timing and duration of construction are primary considerations for
determining the design flow most appropriate for a diversion. A sizing method that does not consider these
variables is overly simplistic and can result in inflated project costs and land disturbances that provide little
to no water quality benefit. Additionally, disturbing more area than necessary can result in increased
erosion.
Temporary diversion method section and approach should occur on a project- and site-specific basis. For
short duration projects (typically associated with maintenance of utilities and stream crossings and minor
repairs to outfalls and eroded banks) constructed during dry times of the year, diversion construction can
create greater disturbance and mobilization of sediment than all of the other earth disturbing activities of the
project combined, and the cost of the diversion could be a significant percentage of the overall project cost.
If it can be reasonably determined, based on area and duration of disturbance, that channel work will result
in less disturbance and movement of sediment than would occur through installation of a temporary
diversion, it is reasonable to exempt these activities from the requirement to construct a temporary diversion.
Temporary Diversion Channel
Functions
Erosion Control Yes
Sediment Control No
Site/Material Management No
SM-8 Temporary Diversion Methods (TDM)
TDM-2 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
On the other end of the spectrum, a basis of design for a temporary diversion in excess of the methodology
presented in this Fact Sheet may be appropriate for longer duration projects and/or projects where the
consequences of exceeding diversion capacity are significant in terms of public safety, damage to
infrastructure and property, environmental impacts, damage or delay to the project and other factors. In
short, engineers should recognize that temporary diversions must be thoughtfully analyzed on a case-by-case
basis, considering site-specific circumstances.
Design Considerations
Selection and design of temporary diversion methods should consider many factors, including:
Will construction of a temporary diversion cause greater environmental impacts than if the project is
constructed without a temporary diversion? This frequently applies to short duration, small scale
projects associated with maintenance activities such as bank erosion repair, drop structure and pond
maintenance, outfall improvements/repair and other limited construction activities.
Size of stream, tributary watershed area and anticipated flow rates during construction. Special
consideration should be given to large streams with large tributary areas with higher flow rates since
the sizing methodology presented in this Fact Sheet is based on data from watersheds less than 20
square miles.
Any special water quality or aquatic life conditions the waterway.
Nature of surrounding land use, property ownership, and easements in the project area are important
considerations in determining feasibility and methods for temporary diversions. For example, in a
highly urbanized setting or an area with limited right-of-way, there may not be adequate space to
construct a diversion channel.
Seasonal variations in stream hydrology (baseflow vs. peak flow).
o Irrigation flows: If an irrigation ditch enters the stream, it is recommended that the ditch
company be contacted to confirm when flows from the ditch may be expected.
o Weather (storm runoff): If diversions are constructed in summer months when
thunderstorms and flash flooding can occur, contractors will need to track weather forecasts
closely and provide additional protection when higher flows from runoff are anticipated.
The UDFCD Alert System can be used for daily forecasts and to provide warnings for
severe weather.
Probability of flood flows exceeding diversion capacity and/or diversion failure. Consider the
consequences of exceedance or failure such as:
o Public safety
o Environmental
o Legal
o Regulatory
o Economic
o Project disruption/delay
Realistic estimation of project duration and time of year during which construction will occur.
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-3
Urban Storm Drainage Criteria Manual Volume 3
Comparison of the overall project costs to the temporary diversion costs (design and construction)
and determining the costs and benefits of different diversion strategies relative to the protection that
they provide.
Permitting requirements for overall project and for diversion methods (United States Army Corps of
Engineers, United States Fish and Wildlife Service, Colorado Department of Public Health and
Environment, Federal Emergency Management Agency, Division of Water Resources, local
governments, and others). Permit requirements and existing vegetative cover may limit the
allowable area disturbance.
Public safety aspects. For example, if a pipeline is being used, consideration should be given to
public access and inlet protection.
Legal considerations, which are a function of many different factors such as property ownership,
history of localized flooding, or parties that will have interest in project.
Design and Installation
1.Determine if a diversion is appropriate based on appropriate uses and design considerations stated
earlier. As noted, in some cases, constructing a project under wet conditions is preferable to
constructing a temporary diversion to create dry conditions, especially if construction of the
temporary diversion will require a significant amount of disturbance relative to the overall project.
2.Determine project duration.
“Long duration” projects are projects that last longer than three months and in many cases
are Capital Improvement Projects or traditional land development projects.
“Short duration” projects are projects that are completed within one month or less and
generally are associated with maintenance and repair activities.
“Interim duration” projects are projects that will last longer than one month but up to three
months.
3.Determine the time of year in which construction will occur.
4. Gather necessary temporary diversion sizing parameters that may include tributary area,
imperviousness, project duration safety factor, and seasonal sizing coefficient.
5. Apply applicable sizing methodology and perform necessary calculations (provided following this
section). Use engineering judgment to determine if the temporary diversion design flow is adequate
for the specific project.
6.Determine appropriate method of diversion. Follow the design steps for the selected method
discussed below.
Channel Diversion – For smaller streams, construction of dams and detention basins, or as
the site allows, a channel diversion may divert the entire waterway as illustrated in Figure
TDM-1.
SM-8 Temporary Diversion Methods (TDM)
TDM-4 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
Selecting a Diversion
Method
Selection of the appropriate
diversion type is largely site
specific. The best choice
represents the most efficient
method while keeping
disturbance to a minimum.
Berm or Coffer Dam – A berm or coffer dam is
appropriate for streams of all sizes to confine flow to
one side of the stream.
Piped Diversion – A bypass pipe is generally
appropriate for short duration projects with low
baseflows.
Pumped Diversion – A pumped diversion may be
appropriate for short duration projects with low
baseflows. It may also be the only option where
space for the diversion is limited as shown in
photograph TDM-2.
7.Consider developing an emergency action plan, as a precaution, for rapidly removing equipment and
materials with potential to contribute pollutants to runoff from the waterway in advance of imminent
runoff with the potential to exceed diversion capacity. The emergency action plan should designate
an individual who will be on the site throughout most of the construction project with the authority
to order that work be halted and equipment and materials with potential to contribute to stormwater
pollution be moved to high ground outside of the active channel. The emergency action plan should
identify where equipment and materials removed from the channel will be stored temporarily during
a runoff event that is expected to exceed temporary diversion capacity. The UDFCD Alert System
and warnings of the potential for severe weather issued by UDFCD should be consulted daily during
construction.
Channel Diversion
1. Use sizing methodology to determine temporary diversion design flow rate.
2.Determine channel slope based on existing and proposed site conditions.
Perform initial channel sizing calculations using Manning's Equation. Determine maximum
permissible velocities based on lining material. Pay particular attention to diversion channel
entrance, bends, transitions and downstream return to stream where scour forces may require greater
protection. Unlined channels should not be used. Table TDM-1 gives Manning's "n" values for the
most commonly used lining materials.
Because temporary diversion channels typically are not in service long enough to establish adequate
vegetative lining, they must be designed to be stable for the design flow with the channel shear
stress less than the critical tractive shear stress for the channel lining material.
3.Determine the channel geometry and check the capacity using Manning's Equation and the "n" value
given in Table TDM-1. The steepest side slope allowable is two horizontal to one vertical (2:1),
unless vertical walls are installed using sheet piling, concrete or stacked stone. Consideration for
public access and safety should be accounted for when determining channel geometry.
4. Determine depth of flow. A maximum depth of 1-foot is allowed for flows less than 20 cfs and a
maximum of 3 feet for flows less than 100 cfs. (Flows in excess of 100 cfs should be designed in
accordance with the Major Drainage chapter in Volume 1). Provide a minimum of 0.5 feet of
freeboard above the design water surface elevation.
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-5
Urban Storm Drainage Criteria Manual Volume 3
Table TDM-1. Manning’s n Values for Temporary Diversion Channel Design
Lining Material Manning's n
Depth = 0 to 1.0 ft
Manning's n
Depth = 1.0 to 3.0 ft
Manning's n
Depth = 3.0 to 5.0 ft
Plastic Membrane 0.011 0.010 0.009
Straw/Curled Wood Mats 0.035 0.025 0.020
Riprap, Type VL 0.070 0.045 0.035
Riprap, Type L 0.100 0.070 0.040
Riprap, Type M 0.125 0.075 0.045
Note: Use manufacturer's Manning's n when available. See the Major Drainage chapter of the USDCM for riprap
gradation. Erosion protection should extend a minimum of 0.5 feet above the design water depth.
Berm or Coffer Dam
For coffer dams or berms that are intended to isolate a portion of the stream from the work area steps 1-
4 should be applied to the “wet” side of the coffer dam or berm.
1. Use sizing methodology to determine temporary diversion design flow rate.
2. Determine channel slope based on existing and proposed site conditions.
3. Perform initial channel sizing calculations using Manning's Equation. Determine maximum
permissible velocities based on lining material. Because temporary diversion measures typically are
not in service long enough to establish adequate vegetative lining, they must be designed to be stable
for the design flow with the channel shear stress less than the critical tractive shear stress for the
channel lining material. This stability criterion applies to the stream-side of berms when berms are
used to isolate a work area within a stream.
4.Determine the channel geometry and check the capacity using Manning's Equation and the "n" value
given in Table TDM-1. The steepest side slope allowable is two horizontal to one vertical (2:1),
unless vertical walls are installed using sheet piling, concrete or stacked stone. Provide a minimum
of 0.5 feet of freeboard above the design water surface elevation.
Piped Diversion
1. Use sizing methodology to determine temporary diversion design flow rate.
2. Size the pipe to accommodate the design flow using no more than 80 percent of the pipe full flow
capacity. Select a Manning’s n value based on the type of pipe material that will be used (concrete
n = 0.013 [typ.], corrugated metal pipe n = 0.024 [typ.]).
SM-8 Temporary Diversion Methods (TDM)
TDM-6 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
“Long duration” projects last
longer than three months.
“Short duration” projects are
completed within one month or
less.
“Interim duration” projects last
longer than one month and up
to three months.
Photograph TDM-2. Despite a relatively significant baseflow, a
pumped diversion was selected for this Lakewood Gulch project due
to a lack of space crossing Federal Boulevard. Photo courtesy of City
and County of Denver.
Pumped Diversion
1. Use sizing methodology to
determine temporary diversion
design flow rate.
2. A backup pump (or pumps) with
capacity equal to or greater than the
diversion design flow rate should
be on site and in good working
order at all times.
Sizing Methodology
The methodology for sizing of temporary
diversion methods was developed using
baseflow observations and Crest Stage
Indicator (CSI) peak flow data collected
from 21 watersheds within the UDFCD
boundary. These data were collected over extended periods of time (up to 31 years) and, as a result, provide
a sound statistical basis for the sizing methodology.
Determine sizing procedure to use based on the project
duration.
•“Long duration” projects last longer than three
months and in many cases are Capital
Improvement Projects or traditional land
development projects.
•“Short duration” projects are completed within one
month or less and generally are associated with
maintenance and repair activities. For these
projects, it is recommended that the temporary
diversion be sized based on the statistics identified
for baseflows (i.e., vs. peak flows) and be of
sufficient size to convey a flow that has a less than
50% chance of being exceeded between November
–March, including a project duration safety factor.
•“Interim duration” projects will last longer than one month but up to three months. In these projects,
engineering judgment must be applied, drawing on sizing methods for “short duration” and “long
duration” project criteria and the time of year of construction to develop a basis of design for the
temporary diversion method that is appropriate for the project.
It is highly recommended that projects involving temporary diversions be constructed between November
and March. If a short duration project requiring a temporary diversion must be conducted between April and
October, the extended weather forecast should be evaluated to avoid periods of anticipated precipitation and
a conservative safety factor should be applied. Additional protection may need to be provided for the site if
higher flows from runoff are anticipated.
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-7
Urban Storm Drainage Criteria Manual Volume 3
Sizing Procedure for Long Duration Projects (duration greater than three months)
1.Determine the tributary drainage area, A, in square miles.
2.Determine the watershed imperviousness (adjusted as appropriate for disconnected impervious area, see
Chapter 3).
3. Determine the design peak flow rate according to Figure TDM-2. Note: For long duration projects, or
where the consequences of diversion failure warrant, a larger design flow may be necessary, and/or a
more detailed, site-specific hydrologic analysis.
Figure TDM-2 may be used to estimate the design discharge for the sizing of temporary diversion methods
for projects exceeding three months in duration. The curves in this figure were originally developed using
annual peak flow data collected from 17 watersheds within the UDFCD boundary and then updated in 2012
using annual peak flow data from 21 watersheds with CSI gages. These data were collected over extended
periods of time (up to 31 years) and, as a result, provide a sound statistical basis for the figure. The data
supporting Figure TDM-2 were taken during the high flood potential period of April through September.
Figure TDM-2 provides estimated 2-year peak flow rates with the upper 5% and lower 95% confidence
limits shown and is based on watershed imperviousness for small waterways (25 square miles or less).1
Because Figure TDM-2 was developed using data from small watersheds, it is not appropriate to extrapolate
from this figure for larger, more complex watersheds. For larger waterways (e.g., South Platte River, Sand
Creek, Bear Creek, etc.), including ones controlled by flood control reservoirs (e.g., Chatfield Dam, Cherry
Creek Dam, etc.), site-specific hydrologic analysis and risk assessment will be necessary to evaluate the
appropriate level of protection to be provided by the temporary diversion. For any size watershed, it is
important that the designer understand watershed characteristics to determine applicability of the simplified
method and how these characteristics influence the choice of diversion method. It is also important to
recognize that larger floods can and do occur. It is the responsibility of the designer and the contractor to
assess their risk of having the temporary diversion being exceeded and to evaluate the damages such an
event may cause to the project, adjacent properties and others.
1 There are a multitude of factors affecting rainfall-runoff response of a watershed in addition to impervious area.
Other factors include soil types, total area, fraction of connected/disconnected impervious area, watershed shape,
topography and many other factors). Figure TDM-2 provides a simplified design tool based on watershed
imperviousness but should not be blindly relied upon without due consideration of other factors including those listed
above and others.
SM-8 Temporary Diversion Methods (TDM)
TDM-8 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
When a diversion is determined
to be appropriate, safety factors
and K values in Table TDM-2
are minimum recommended
values. Depending on the many
factors to consider in selecting
and sizing a temporary
diversion listed above, higher
values for K and S may be
appropriate.
Sizing Procedure for Short Duration Projects (one month or less of active construction)
1.Determine the tributary drainage area, A, in
square miles.
2.Select a safety factor, S, based on project
duration from Table TDM-2. Short duration
projects have been broken down further into
projects less than two weeks and projects from
two weeks up to one month.
3.Select the sizing coefficient, K, corresponding
to the month in which the project will occur (see
Table TDM-2). For projects that span two
months with different K values, use the greater
of the two K values. For short duration projects
that will occur during the traditionally dry
period of the year (November through March) a
K value of 0.2 is recommended. For short
duration projects that will occur April through
October, and wet weather is not predicted, a K value of 0.5 is recommended.
Table TDM-2.Temporary Diversion Sizing Coefficients and Safety Factors for
Short Duration Projects
Time of Year Project Duration Safety Factor, S Temporary Diversion
Sizing Coefficient, K
November - March Less than 2 weeks 1.0 0.2
November - March 2 weeks to 1 month 1.5 0.2
April - October
Less than 2 weeks
(during dry weather
conditions)
1.0 0.5
April - October 2 weeks to 1 month 1.5 0.5
Note: K coefficients were developed from regression analysis of baseflow data from USGS Crest Stage Indicator (CSI)
data to approximate flows that have a less than 50% chance of being exceeded between November - March.
4. Calculate the recommended temporary diversion design flow rate using equation TDM-1:
Q = S K A (Equation TDM-1)
In which,
Q = temporary diversion design flow rate for short-duration projects (cfs).
S = safety factor coefficient from Table TDM-2 based on duration.
K = diversion sizing coefficient from Table TDM-2 based on seasonality.
A = tributary area (square miles).
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-9
Urban Storm Drainage Criteria Manual Volume 3
Example of Short-Duration Temporary Diversion Sizing Methodology
Project Location: Goldsmith Gulch Downstream (north) of E. Cornell Avenue
Planned project will involve approximately 0.12 acres of disturbance for bank stabilization, which will be
completed within two weeks during the November to March time period. Using StreamStats, the gross
contributing watershed area was determined to be approximately 6.2 mi2. Based on project duration and
seasonal timing, Table TDM-2 yields S = 1.0, K = 0.2. Equation TDM-1 can be used to calculate the
recommended diversion flow:
Q = S K A
Q = 1.0 0.2 6.2 mi2 = 1.2 cfs
Had this been a larger restorative maintenance project that will last 4 weeks, but will be started and
completed within the November through March period, application of Equation TDM-1 and the
recommended safety factor suggest the following diversion design flow:
Q = S K A
Q = 1.5 0.2 6.2 mi2 = 1.9 cfs
Of course, if the observed condition at the construction site suggests a higher flow, this should be
estimated and used instead.
Sizing Procedure for Interim Duration Projects (longer than one month and up to three months)
When projects last longer than one month but up to three months, a combination of sizing methods should be
applied. The recommended temporary diversion flow rate should be evaluated using both the sizing
procedure for short duration projects as well as the sizing procedure for long duration projects. These
calculated flow rates should be weighed in combination with site-specific factors to determine an appropriate
design flow rate. Each site should be evaluated individually to determine factors that may affect the design
flow choice. For example, the designer may select to use the more conservative design flow for an interim
duration project occurring in July and August where a chance for wet weather is forecast and flooding or
damage to the area surrounding the project is unacceptable.
Maintenance and Removal
Because temporary diversions are one of the most critical control measures for work in waterways, they
must be inspected and maintained frequently to remain in effective operating condition. Flow barriers
should be inspected at the start and end of each workday and at any time that excess water is noted in dry
work areas. For diversion channels, the diversion channel itself should be inspected for signs of erosion,
and the lining should be repaired or replaced if there are signs of failure. Check armoring at the diversion
return point to the waterway, and add additional armoring if erosion is noted.
Water should not be allowed to flow back through the natural stream until all construction is completed.
After redirecting the flow through the natural channel, temporary diversion measures should be removed.
For temporary diversion channels, lining materials should be removed, and the diversion channel should
then be backfilled and stabilized. Points of tie-in to the natural channel should be protected with riprap sized
SM-8 Temporary Diversion Methods (TDM)
TDM-10 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
material in accordance with the Major Drainage chapter in Volume 1.
Figure TDM-1. Typical Temporary Diversion Channel
Former Location of
Stream Bank
Former Location of
Stream Bank
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-11
Urban Storm Drainage Criteria Manual Volume 3
Figure TDM-2. Temporary Diversion Facility Sizing Nomograph for Long Duration Projects
(Duration in excess of three months) Based on 2-year Peak Flows -
Denver Metropolitan and Adjacent Areas, Updated April 2012
SM-8 Temporary Diversion Methods (TDM)
TDM-12 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
Temporary Diversion Methods (TDM)SM-8
June 2012 Urban Drainage and Flood Control District TDM-13
Urban Storm Drainage Criteria Manual Volume 3
Dewatering Operations (DW)SM-9
November 2010 Urban Drainage and Flood Control District DW-1
Urban Storm Drainage Criteria Manual Volume 3
Photograph DW-1. A relatively small dewatering operation using straw
bales and a dewatering bag.
Photograph DW-2. Dewatering bags used for a relatively large
dewatering operation.
Description
The control measuress selected for
construction dewatering vary depending
on site-specific features such as soils,
topography, anticipated discharge
quantities, and discharge location.
Dewatering typically involves pumping
water from an inundated area to a control
measure, and then downstream to a
receiving waterway, sediment basin, or
well-vegetated area. Dewatering
typically involves use of several control
measures in sequence.
Appropriate Uses
Dewatering operations are used when an
area of the construction site needs to be
dewatered as the result of a large storm
event, groundwater, or existing ponding
conditions. This can occur during deep
excavation, utility trenching, and wetland
or pond excavation.
Design and Installation
Dewatering techniques will vary
depending on site conditions. However,
all dewatering discharges must be treated
to remove sediment before discharging
from the construction site. Discharging
water into a sediment trap or basin is an
acceptable treatment option. Water may
also be treated using a dewatering filter bag,
and a series of straw bales or sediment logs. If these previous options are not feasible due to space or the
ability to passively treat the discharge to remove sediment, then a settling tank or an active treatment
system may need to be utilized. Settling tanks are manufactured tanks with a series of baffles to promote
settling. Flocculants can also be added to the tank to induce more rapid settling. This is an approach
sometimes used on highly urbanized construction sites. Contact the state agency for special requirements
prior to using flocculents and land application techniques.
Some commonly used methods to handle the pumped
water without surface discharge include land application
to vegetated areas through a perforated discharge hose
(i.e., the "sprinkler method") or dispersal from a water
truck for dust control.
Dewatering Operations
Functions
Erosion Control Moderate
Sediment Control Yes
Site/Material Management Yes
SM-9 Dewatering Operations (DW)
DW-2 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Dewatering discharges to non-paved areas must minimize the potential for scour at the discharge point
either using a velocity dissipation device or dewatering filter bag.
Design Details are provided for these types of dewatering situations:
DW-1. Dewatering for Pond Already Filled with Water
DW-2 Dewatering Sump for Submersed Pump
DW-3 Sump Discharge Settling Basin
DW-4 Dewatering Filter Bag
Maintenance and Removal
When a sediment basin or trap is used to enable settling of sediment from construction dewatering
discharges, inspect the basin for sediment accumulation. Remove sediment prior to the basin or trap
reaching half full. Inspect treatment facilities prior to any dewatering activity. If using a sediment
control practice such as a sediment trap or basin, complete all maintenance requirements as described in
the fact sheets prior to dewatering.
Properly dispose of used dewatering bags, as well as sediment removed from the dewatering control
measures. Depending on the size of the dewatering operation, it may also be necessary to revegetate or
otherwise stabilize the area where the dewatering operation was occurring.
Dewatering Operations (DW)SM-9
November 2010 Urban Drainage and Flood Control District DW-3
Urban Storm Drainage Criteria Manual Volume 3
SM-9 Dewatering Operations (DW)
DW-4 Urban Drainage and Flood Control District November 2010
Urban Storm Drainage Criteria Manual Volume 3
Dewatering Operations (DW)SM-9
November 2010 Urban Drainage and Flood Control District DW-5
Urban Storm Drainage Criteria Manual Volume 3
Temporary Stream Crossing (TSC)SM-10
June 2012 Urban Drainage and Flood Control District TSC-1
Urban Storm Drainage Criteria Manual Volume 3
Description
Where an actively flowing watercourse
must be crossed regularly by
construction vehicles, a temporary
crossing should be provided. Three
primary methods are available:
Culvert crossing
Stream ford
Temporary bridge
Culvert crossings and fords are the most
commonly used methods. Due to the
expense associated with a temporary
bridge, these are used primarily on long-
term projects.
Appropriate Uses
Construction vehicles shall be kept out of waterways to the maximum extent practicable. Use a
temporary stream crossing when it is absolutely necessary to cross a stream on a construction site.
Construct a temporary crossing even if the stream or drainageway is typically dry. Multiple stream
crossings should be avoided to minimize environmental impacts.
A permit is required for placement of fill in a waterway under Section 404 of the Clean Water Act. The
local office of the U.S. Army Corps of Engineers (USACE) should be contacted concerning the
requirements for obtaining a 404 permit. In addition, a permit from the U.S. Fish and Wildlife Service
(USFWS) may be needed if endangered species are of concern in the work area. Typically, the USFWS
issues are addressed by a 404 permit, if one is required. The municipality of jurisdiction should also be
consulted, and can provide assistance. Other permits to be obtained may include a floodplain
development permit from the local jurisdiction.
Design and Installation
Design details are provided for these types of stream crossings:
TSC-1. Culvert Crossing
TSC-2. Ford Crossing
TSC-3. Flume Crossing
Temporary Stream Crossing
Functions
Erosion Control Yes
Sediment Control Yes
Site/Material Management No
Photograph TSC-1. A temporary stream crossing using culverts.
Photo courtesy of Tom Gore.
SM-10 Temporary Stream Crossing (TSC)
TSC-2 Urban Drainage and Flood Control District June 2012
Urban Storm Drainage Criteria Manual Volume 3
A culvert crossing should be sized appropriately with consideration for the duration of construction and
seasonal variation of flows. The sizing methodology provided in the Temporary Diversion Methods Fact
Sheet is also appropriate for determining the design flow for temporary stream crossings. Culvert sizing
must account for the headwater and tailwater controls to properly size the culvert. For additional
discussion on design of box culverts and pipes, see the Major Drainage chapter in Volume 1. The
designer also needs to confirm that the riprap selected is appropriate for the conditions in the channel
being crossed.
When a ford must be used, namely when a culvert is not practical or the best solution, the ford should be
lined with at least a 12-inch thick layer of Type VL (D50 = 6 inches) or Type L (D50 = 9 inches) riprap
with void spaces filed with 1-1/2 inch diameter rock. Ford crossings are recommended primarily for
crossings of ephemeral (i.e. intermittently, briefly flowing) streams.
For a temporary bridge crossing, consult with a structural and/or geotechnical engineer for temporary
bridge design or consider pre-fabricated alternatives.
Maintenance and Removal
Inspect stream for bank erosion and in-stream degradation. If bank erosion is occurring, stabilize banks
using erosion control practices such as erosion control blankets. If in-stream degradation is occurring,
armor the culvert outlet(s) with riprap to dissipate energy. If sediment is accumulating upstream of the
crossing, remove excess sediment as needed to maintain the functionality of the crossing.
Remove the temporary crossing when it is no longer needed for construction. Take care to minimize the
amount of sediment lost into the stream upon removal. Once the crossing has been removed, stabilize the
stream banks with seed and erosion control blankets.