HomeMy WebLinkAboutCompaction Report #1Activity Date:06/25/2024 Technician:Downing, Thomas
Placement Location:
Structural fill placement, site retaining wall, building A, south and
east footings
Plans/Details:
CTL Thompson Geotechnical report GS06693.000125, dated
August 22, 2022
Discrepancy:
The items observed were found to be in general conformance with the approved drawings and standard construction
practice:
Yes No
Discrepancy:
Yes No
General Remarks:
As requested, a site visit was made to observe completed placement of structural fill in site retaining wall excavation. The
earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been
processed to a 4 inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose
lifts. Compactive effort was applied with a a large steeldrum vibratory compactor. We judge the compacted structural fill as
acceptable for a bearing pressure of 3000 psi.
✔
✔
Field Observation Report FOR000005Report #:
06/25/2024
Glenwood Springs
234 Center Drive
Glenwood Springs, CO 81601
Phone: 9709452809
Client:
Andover Management Group
333 East main Street
Suite 300
Louisville, KY 40202
Project:
GS06693.001F345
214 Center Drive
214 Center Drive
Garfield County, CO
Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2
Activity Date:06/25/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A, south andeast footings Plans/Details:CTL Thompson Geotechnical report GS06693.000125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No
Discrepancy:
Yes No
General Remarks:
As requested, a site visit was made to observe completed placement of structural fill in site retaining wall excavation. The
earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been
processed to a 4 inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose
lifts. Compactive effort was applied with a a large steeldrum vibratory compactor. We judge the compacted structural fill as
acceptable for a bearing pressure of 3000 psi.
Images:
Comments:east half of retaining wall excavation, looking north Comments:east half of retaining wall excavation, looking north
✔
✔
Field Observation Report FOR000005Report #:
06/25/2024
Glenwood Springs
234 Center Drive
Glenwood Springs, CO 81601
Phone: 9709452809
Client:
Andover Management Group
333 East main Street
Suite 300
Louisville, KY 40202
Project:
GS06693.001F345
214 Center Drive
214 Center Drive
Garfield County, CO
Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2