HomeMy WebLinkAboutRes CheckCOMcheck Software Version 4.1,5.5
Envelope Gompliance Certificate
Project lnformation
Energy Code:
Project Title:
Location:
Climate Zone:
Project Type:
Construction Site:
Additional Efficiency Package(s)
Credits: 1.0 Required 1.0 Proposed
On-site Renewable Energy, 1.0 credit
Building Area
2018 |ECC
Silt, Colorado
5b
New Construction
Owner/Agent:Designer/Contractor:
Floor Area
1-Workshop : Nonresidential 4800
Envelope Assemblies
Assembly Gross Area
or
Perimeter
Cavity
R-Value
Cont.
R-Value
Proposed
U-Factor
Budget U-
Factorr"t
Roof 1: Metal Building, Standing Seam, Liner System with Thermal
Blocks (b), [Bldg. Use 1 - Workshop]
Exterior Wall 1: Metal Building Wall, Single Layer Mineral Fiber (in
cavity, thermal block at girt), [Bldg. Use 1 - Workshop]
5059
4860
38.0
30.0
0.030
0.052
0.035
0.052
0.0
0.0
(a) Budget U-factors are used for software baseline calculations ONLY, and are not code requirements.
(b) Thermal spacer block with minimum R-3.5 must be installed above the purlin/batt, and the roof deck secured to the purlins.
Envelope Gompliance Statement
Compliance Statement; The proposed envelope design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application. The proposed envelope systems have been
designed to meet the 2018 IECC requirements in COMcheck Version 4.1.5.5 and to comply with any applicable mandatory
requirements listed in the lnspection Checklist.
Name - Title Date
Envelope PASSES: Design 6% better than code
Project Title:
Data filename: Untitled.cck
Report dale: 08127 124
Page 1 of 11