HomeMy WebLinkAboutEngineer's Final letter 10.09.24SGM Inc.
118 West Sixth St, Suite 200
Glenwood Springs, CO 81601
970.945.1004
CONSTRUCTION OBSERVATION REPORT
Page 1 of 2
DATE: 10/9/2024
PROJECT: Brettelberg SGM JOB NO. 2020-396.001
BY: John Partch, PE
CONSTRUCTION ACTIVITIES:
I performed limited visual observations of repairs to the landings and walkways of Building A, B, and F as
work progressed. Based on my observations, the repairs were completed in substantial conformance with
the repair plans provided:
1. Brettelberg Condominiums, A-B Walkway Repairs, dated 08/12/2024
2. Brettelberg Condominiums, F-G Walkway Repairs, dated 08/13/2024
This report is based on our site observations, research of available records, and experience with structures of
this type in this area. Our observations were limited by the presence of backfill, finish materials, and physical
constraints. Unseen defects or conditions may exist that could affect the structural integrity of the structures
observed. The observations, interpretations and conclusions herein have been conducted to the standard of
care ordinarily practiced by other engineers in this area at this time. No warranty is made, express or implied.
10/09/2024
SGM Inc.
118 West Sixth St, Suite 200
Glenwood Springs, CO 81601
970.945.1004
CONSTRUCTION OBSERVATION REPORT
Page 2 of 2
PHOTOS - PAGE 1:
Photo #1: Photo #2: Photo #3:
Photo #4: Photo #5: Photo #6:
Distribution:
SGM File
I:\2020\2020-396-Brettelberg\001-11101CR107\L-ConstMgmt\ConstDocs\InspectReports\ConstObs-DeckRepairs-241009.docx