HomeMy WebLinkAboutCold Formed Steel Framing ReportsActivity Date:08/30/2024 Technician:Downing, Thomas Placement Location: Building A, cold formed steel framing observation, level 1 to level 2. Between gridlines A to U, from 1 to 36 line Plans/Details: AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. Sheet S210, S410, S420 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for building "A". Items inspected included layout and spacing of structural members, and screw size and layout. All framing inspected today was erected per approved drawings and standard construction practices. ✔ ✔ Field Observation Report FOR­000001Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:08/30/2024 Technician:Downing, ThomasPlacement Location:Building A, cold formed steel framing observation, level 1 to level2. Between gridlines A to U, from 1 to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS210, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for building "A". Items inspected included layout and spacing of structural members, and screw size and layout. All framing inspected today was erected per approved drawings and standard construction practices. Images: Comments:Typical header framing at corridor Comments:Typical framing at corridor ✔ ✔ Field Observation Report FOR­000001Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:08/30/2024 Technician:Downing, ThomasPlacement Location:Building A, cold formed steel framing observation, level 1 to level2. Between gridlines A to U, from 1 to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS210, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for building "A".Items inspected included layout and spacing of structural members, and screw size and layout. All framing inspected todaywas erected per approved drawings and standard construction practices.Images: Comments:Typical header framing at corridor Comments:Typical framing at corridor Comments:Typical corridor framing ✔✔ Field Observation Report FOR­000001Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3 Activity Date:08/30/2024 Technician:Downing, Thomas Placement Location: Building A, level 2 steel pan deck. Between gridlines A to U, from 3 to 36 line Plans/Details: AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. Sheet S211, S410, S420 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the level 2 steel pan deck for the north half of building "A". Items inspected included screw size and layout of screw patterns. All pan decking inspected today was erected per approved drawings and standard construction practices. ✔ ✔ Field Observation Report FOR­000002Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:08/30/2024 Technician:Downing, ThomasPlacement Location:Building A, level 2 steel pan deck. Between gridlines A to U, from 3to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS211, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the level 2 steel pan deck for the north half of building "A". Items inspected included screw size and layout of screw patterns. All pan decking inspected today was erected per approved drawings and standard construction practices. Images: Comments:Typical screw spacing at panel overlap Comments:Typical screw spacing at perimeter ✔ ✔ Field Observation Report FOR­000002Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:08/30/2024 Technician:Downing, ThomasPlacement Location:Building A, level 2 steel pan deck. Between gridlines A to U, from 3to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS211, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe the level 2 steel pan deck for the north half of building "A". Items inspectedincluded screw size and layout of screw patterns. All pan decking inspected today was erected per approved drawings andstandard construction practices.Images: Comments:Typical screw spacing at panel overlap Comments:Typical screw spacing at perimeter Comments:Typical screw spacing at panel overlap ✔✔ Field Observation Report FOR­000002Report #: 08/30/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3 Activity Date:09/12/2024 Technician:Downing, Thomas Placement Location: Building A, cold formed steel framing observation, level 1 to level 2. Between gridlines U to PP, from 1 to 36 line Plans/Details: AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. Sheet S210, S410, S420 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for the south half of building "A". Items inspected included layout and spacing of structural members, and screw size and layout. All framing inspected today was erected per approved drawings and standard construction practices. ✔ ✔ Field Observation Report FOR­000003Report #: 09/12/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:09/12/2024 Technician:Downing, ThomasPlacement Location:Building A, cold formed steel framing observation, level 1 to level2. Between gridlines U to PP, from 1 to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS210, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for the south half of building "A". Items inspected included layout and spacing of structural members, and screw size and layout. All framing inspected today was erected per approved drawings and standard construction practices. Images: Comments:Typical header framing at corridor Comments:Typical framing at corridor ✔ ✔ Field Observation Report FOR­000003Report #: 09/12/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:09/12/2024 Technician:Downing, ThomasPlacement Location:Building A, cold formed steel framing observation, level 1 to level2. Between gridlines U to PP, from 1 to 36 line Plans/Details:AO Drafting, Inc, Job # GLENWOOD, dated March 1, 2024. SheetS210, S410, S420Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe the cold formed steel framing for the level 1 to level 2 framing for the south halfof building "A". Items inspected included layout and spacing of structural members, and screw size and layout. All framinginspected today was erected per approved drawings and standard construction practices.Images: Comments:Typical header framing at corridor Comments:Typical framing at corridor Comments:doorway framing detail ✔✔ Field Observation Report FOR­000003Report #: 09/12/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3 Activity Date:11/18/2024 Technician:Downing, Thomas Placement Location: Building C, interior partition wall cold formed steel framing observation Plans/Details: AO Drafting, Inc, Job # S KING­C, dated June 24, 2024. Sheet S210, S410, S420, S430, S440 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel partition wall framing for Building "C". Items inspected included layout and spacing of cold formed steel partition wall framing, and screw size and layout. Any missing screws in partition framing were installed in our presence during todays inspection. All framing inspected today was installed per approved drawings and standard construction practices at the conclusion of our inspection. The general contractor was notified of our observations. Additional site visits will be scheduled with our office when required. ✔ ✔ Field Observation Report FOR­000004Report #: 11/18/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:11/18/2024 Technician:Downing, ThomasPlacement Location:Building C, interior partition wall cold formed steel framingobservation Plans/Details:AO Drafting, Inc, Job # S KING­C, dated June 24, 2024. SheetS210, S410, S420, S430, S440Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe the cold formed steel partition wall framing for Building "C". Items inspected included layout and spacing of cold formed steel partition wall framing, and screw size and layout. Any missing screws in partition framing were installed in our presence during todays inspection. All framing inspected today was installed per approved drawings and standard construction practices at the conclusion of our inspection. The general contractor was notified of our observations. Additional site visits will be scheduled with our office when required. Images: Comments:Typical partition framing at bottom channel Comments:Typical partition framing at top channel ✔ ✔ Field Observation Report FOR­000004Report #: 11/18/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:11/18/2024 Technician:Downing, ThomasPlacement Location:Building C, interior partition wall cold formed steel framingobservation Plans/Details:AO Drafting, Inc, Job # S KING­C, dated June 24, 2024. SheetS210, S410, S420, S430, S440Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe the cold formed steel partition wall framing for Building "C". Items inspectedincluded layout and spacing of cold formed steel partition wall framing, and screw size and layout. Any missing screws inpartition framing were installed in our presence during todays inspection. All framing inspected today was installed perapproved drawings and standard construction practices at the conclusion of our inspection. The general contractor wasnotified of our observations. Additional site visits will be scheduled with our office when required.Images: Comments:Typical partition framing at bottom channel Comments:Typical partition framing at top channel Comments:Typical partition framing at top channel Comments:Typical partition framing at doorway header ✔✔ Field Observation Report FOR­000004Report #: 11/18/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­391 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3