06/04/2025
Owner:
Glenwood Partners LLLP
214 Center Drive
Glenwood Springs, CO 81601
Contractor:
Andover Construction, Dan Kunau
333 E. Main Street Suite 300
Louisville, KY 40202
Re: Conditional Use of the Storage Building
Job Address: 267 Center Drive
Permit BLCO-03-24-8553
Parcel # 218506100042
Dear Dan Kunau,
The County has performed the final inspection of the building, there are item to be completed
prior to full occupancy of the building. The life-safety items in the building appear to be
addressed, ie; The State Electrical Inspector has approved the final electrical inspection, the
Fire Department has approved the fire suppression and fire alarm, and all special inspection
have been submitted.
The understanding is that empoyees need to occupy the building to get the facility ready for
tenants, which is acceptible and allowed. There are items regarding the site access that need to
be completed prior to allowing the general public access. Below is a list of those items and other
items that were observed during the inspection to address.
• Supply a letter of acceptance from the Civil Engineer of Record that the infrastructure is
installed per plan.
• Complete the public improvements, public sidewalks, pedestrian crosswalks, per
Resolution No. 2023-42, see attached.
• Complete asphalt paving and striping for parking, the accessible parking spaces, and
road delineation.
Community Development Department
108 Eighth Street, Suite 401
Glenwood Springs, Colorado 81601
(970) 945-8212
• Please provide County Road and Bridge approvals for access per the attached
driveway permit.
• Exposed gas piping at the meter is required to be protected from corrosion, paint is
sufficient.
• Complete the gutter downspout transitions to the underground storm water system.
• There are areas where the siding/soffit material is missing on the dormers located on
the north side of the building that need completion.
• The downspout on the west side of the building is not draining away from the building
that needs attention.
• The exterior lighting is to maintain compliance with the County Land Use Code and the
2018 IECC. The light fixtures under the canopies are not the ones listed in the Lighting
Schedule. The County has received complaints regarding these fixtures. Shields have
been installed to divert the lighting downwards. This may need additional attention if the
county receives complaints in the future.
Once all the items are complete a permanent Certificate of Occupancy can be considered for
issuance.
Sincerely,
John Plano
John Plano
Building Official
CC via e-mail:
Noah Valencia, Project Manager
Robin Pitt, Glenwood Fire Department