HomeMy WebLinkAboutGS06693.001F-360 Reinforcing Steel Report 11Activity Date:08/12/2024 Technician:Peskuski, Ryan
Placement Location:Building C SOG east side Plans/Details:AO drafting sheet S110, sheet S100 details 1 and 2.
Items Observed:
Placement Type Observed:
Grade Beam
Pier Cap
Column
Structural Slab
Slab on Grade
Slab on Deck
Footing
Wall
Other
Items Checked:
Bar Size
Bar Quantity and Spacing
Lap Length
Cover
Form Void
Dowel Bars
Other
UFER Ground:
Yes No N/A
Conformance:
The items observed were found to be in general conformance with the approved drawings and standard construction
practice:
Yes No
Discrepancy:
Yes No
General Remarks:
As requested, a site visit was made to reinspect the rebar placement for the SOG on the east side of the Building C. We
obsereved that the deficient spacing of the mat slab rebar had been corrected.
✔
✔
✔
✔
✔
✔
✔
✔
Reinforcing Steel Report RSPO000011Report #:
08/12/2024
Glenwood Springs
234 Center Drive
Glenwood Springs, CO 81601
Phone: 9709452809
Client:
Andover Management Group
333 East main Street
Suite 300
Louisville, KY 40202
Project:
GS06693.001F360
214 Center Drive
214 Center Drive
Garfield County, CO
Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3
Activity Date:08/12/2024 Technician:Peskuski, RyanPlacement Location:Building C SOG east side Plans/Details:AO drafting sheet S110, sheet S100 details 1 and 2.Items Observed:Placement Type Observed:Grade BeamPier CapColumnStructural SlabSlab on GradeSlab on DeckFootingWallOther Items Checked:Bar SizeBar Quantity and SpacingLap LengthCoverForm VoidDowel BarsOther UFER Ground:Yes No N/AConformance:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:
Yes No
Discrepancy:
Yes No
General Remarks:
As requested, a site visit was made to reinspect the rebar placement for the SOG on the east side of the Building C. We
obsereved that the deficient spacing of the mat slab rebar had been corrected.
Images:
Comments:
Mat slab reinforcing in general conformance with project plans.
Comments:
Mat slab reinforcing in general conformance with project plans.
✔✔✔✔✔✔
✔
✔
Reinforcing Steel Report RSPO000011Report #:
08/12/2024
Glenwood Springs
234 Center Drive
Glenwood Springs, CO 81601
Phone: 9709452809
Client:
Andover Management Group
333 East main Street
Suite 300
Louisville, KY 40202
Project:
GS06693.001F360
214 Center Drive
214 Center Drive
Garfield County, CO
Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3
Activity Date:08/12/2024 Technician:Peskuski, RyanPlacement Location:Building C SOG east side Plans/Details:AO drafting sheet S110, sheet S100 details 1 and 2.Items Observed:Placement Type Observed:Grade BeamPier CapColumnStructural SlabSlab on GradeSlab on DeckFootingWallOther Items Checked:Bar SizeBar Quantity and SpacingLap LengthCoverForm VoidDowel BarsOther UFER Ground:Yes No N/AConformance:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to reinspect the rebar placement for the SOG on the east side of the Building C. Weobsereved that the deficient spacing of the mat slab rebar had been corrected.Images:
Comments:
Mat slab reinforcing in general conformance with project plans.
Comments:
Mat slab reinforcing in general conformance with project plans.
Comments:Area of observation.
✔✔✔✔✔✔✔✔
Reinforcing Steel Report RSPO000011Report #:
08/12/2024
Glenwood Springs
234 Center Drive
Glenwood Springs, CO 81601
Phone: 9709452809
Client:
Andover Management Group
333 East main Street
Suite 300
Louisville, KY 40202
Project:
GS06693.001F360
214 Center Drive
214 Center Drive
Garfield County, CO
Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3