HomeMy WebLinkAboutField Observation 1Activity Date:06/03/2024 Technician:Downing, Thomas Placement Location:Building 3 envelope Plans/Details: CTL|T Report GS06693.000­125, dated August 22, 2022. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, Cain with CW Construction requested CTL|T observe the soils exposed after stripping of vegetation in the Building 3 envelope. We noted substantial roots visible in the current subgrade elevation and recommended an additional 4"­6 inches be removed for the building envelope prior to subgrade preparation and fill placement. Images: ✔ ✔ Field Observation Report FOR­000001Report #: 06/03/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:06/14/2024 Technician:Downing, Thomas Placement Location: Structural fill placement, site retaining wall, building A Plans/Details: CTL Thompson Geotechnical report GS06693.000­125, dated August 22, 2022 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi ✔ ✔ Field Observation Report FOR­000002Report #: 06/14/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:06/14/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi Images: Comments:West portion of retaining wall excavation Comments: West portion of retaining wall excavation, looking north ✔ ✔ Field Observation Report FOR­000002Report #: 06/14/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:06/14/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe placement of structural fill in site retaining wall excavation. The earthworkcontractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactiveeffort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for abearing pressure of 3000 psiImages: Comments:West portion of retaining wall excavation Comments: West portion of retaining wall excavation, looking north Comments: West portion of retaining wall excavation, looking south ✔✔ Field Observation Report FOR­000002Report #: 06/14/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3 Activity Date:06/17/2024 Technician:Downing, Thomas Placement Location: Structural fill placement, site retaining wall, building A Plans/Details: CTL Thompson Geotechnical report GS06693.000­125, dated August 22, 2022 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe ongoing placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. ✔ ✔ Field Observation Report FOR­000003Report #: 06/17/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:06/17/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe ongoing placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. Images: Comments: North portion of retaining wall excavation, looking east Comments: North portion of retaining wall excavation, looking west ✔ ✔ Field Observation Report FOR­000003Report #: 06/17/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:06/24/2024 Technician:Downing, Thomas Placement Location: Structural fill placement, site retaining wall, building A, south and east footings Plans/Details: CTL Thompson Geotechnical report GS06693.000­125, dated August 22, 2022 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe ongoing placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. ✔ ✔ Field Observation Report FOR­000004Report #: 06/24/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 4Page 1 of 3 Activity Date:06/24/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A, south andeast footings Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe ongoing placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. Images: Comments:south half of retaining wall excavation, looking west Comments:south half of retaining wall excavation, looking east ✔ ✔ Field Observation Report FOR­000004Report #: 06/24/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 4Page 2 of 3 Activity Date:06/24/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A, south andeast footings Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, a site visit was made to observe ongoing placement of structural fill in site retaining wall excavation. Theearthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has beenprocessed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" looselifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill asacceptable for a bearing pressure of 3000 psi.Images: Comments:south half of retaining wall excavation, looking west Comments:south half of retaining wall excavation, looking east Comments:east half of retaining wall excavation, looking north ✔✔ Field Observation Report FOR­000004Report #: 06/24/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 3 of 4Page 3 of 3 Activity Date:06/25/2024 Technician:Downing, Thomas Placement Location: Structural fill placement, site retaining wall, building A, south and east footings Plans/Details: CTL Thompson Geotechnical report GS06693.000­125, dated August 22, 2022 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe completed placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. ✔ ✔ Field Observation Report FOR­000005Report #: 06/25/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:06/25/2024 Technician:Downing, ThomasPlacement Location:Structural fill placement, site retaining wall, building A, south andeast footings Plans/Details:CTL Thompson Geotechnical report GS06693.000­125, datedAugust 22, 2022Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe completed placement of structural fill in site retaining wall excavation. The earthwork contractor is placing an imported fill material consisting of silty sand with gravel and cobbles that has been processed to a 4­ inch minus. The material is being placed and moisture conditioned with a loader and skidsteer in 8" loose lifts. Compactive effort was applied with a a large steel­drum vibratory compactor. We judge the compacted structural fill as acceptable for a bearing pressure of 3000 psi. Images: Comments:east half of retaining wall excavation, looking north Comments:east half of retaining wall excavation, looking north ✔ ✔ Field Observation Report FOR­000005Report #: 06/25/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:08/05/2024 Technician:Peskuski, Ryan Placement Location:Building A rough slab subgrade Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, we made a site visit to observe a proof roll of the imported subgrade materials under the slab of Building A. We observed a fully loaded water truck drive over the area of observation. We did not observe any significant deflection or pumping of the materials under load. Portions of the southeast corner were not ready for proof rolling. Our office should be notified during fill placement of the unobserved area to approve means and methods or another proof roll should take place prior once fill is in place and compacted. Images: Comments:Equipment used.Comments: Area of observation looking from the southeast towards the northwest. ✔ ✔ Field Observation Report FOR­000006Report #: 08/05/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:08/05/2024 Technician:Peskuski, RyanPlacement Location:Building A rough slab subgradeDiscrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:As requested, we made a site visit to observe a proof roll of the imported subgrade materials under the slab of Building A. Weobserved a fully loaded water truck drive over the area of observation. We did not observe any significant deflection or pumpingof the materials under load. Portions of the southeast corner were not ready for proof rolling. Our office should be notifiedduring fill placement of the unobserved area to approve means and methods or another proof roll should take place prior oncefill is in place and compacted.Images: Comments:Equipment used.Comments: Area of observation looking from the southeast towards the northwest. Comments: Area of observation looking from the southwest towards the northeast. Comments:Area not accessible for proof roll. ✔✔ Field Observation Report FOR­000006Report #: 08/05/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:10/23/2024 Technician:Barbone, Ryan Placement Location: Proof­roll Observation STA 1+00 to 4+50 on Chaparral Dr. and 5+00 to 8+48 on Center Dr. Plans/Details: Sopris Engineering, LLC (dated March 1, 2024) Sheet C­2.0 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: Soft and deflecting areas of subgrade were encountered around manhole and inlet structures as well as beyond STA 4+50 on Chaparral Dr. General Remarks: As requested, a site visit was made to observe a proof­roll of the prepared subgrade soils along Chaparral Dr. and Center Dr. We observed the contractor perform a proof­roll of the subgrade soils with a fully­loaded water truck. The subgrade soils in the main roadway areas appeared to be placed and compacted in accordance with the project specifications. Soft and deflecting soils were encountered around manholes and inlets. We recommended that the soft and deflecting soils be moisture conditioned, reprocessed, and compacted. Our office should be contacted to provide recommendations to stabilize the subgrade soils, if needed. The contractor was notified of our observations and recommendations. Our office will be contacted when a return visit is required. Images: Comments:Looking south along Chaparral Drive.Comments: Soft and deflecting soils encountered near an inlet on Chaparral Drive. ✔ ✔ Field Observation Report FOR­000007Report #: 10/23/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:10/24/2024 Technician:Barbone, Ryan Placement Location: Proof­roll Observation STA 5+00 to 8+48 on Center Drive and the access drive along the west, south, and east sides of Building C. Plans/Details: Sopris Engineering, LLC (Dated March 1, 2024) Sheet C­2.0 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: Soft and deflecting soils encountered around manholes and inlets as well as at the southeast corner of the access dive around Building C. General Remarks: As requested, a site visit was made to observe a proof­roll of the prepared subgrade soils around Building C. We observed the contractor perform a proof­roll with a fully­loaded water truck on the access drive around Building C. We observed areas of soft and deflecting soils around manholes and inlets as well as at the southeast corner of the drive around Building C. We recommended that the subgrade soils be removed, moisture conditioned, processed, and recompacted. Our office should be contacted if additional recommendations to stabilize the subgrade soils are needed. The contractor was notified of our observations and recommendations. Our office will be contacted to schedule a return visit. Images: Comments: Soft and deflecting soils encountered near inlets at the northeast corner of Building C. Comments: Looking west along Chaparral Dr. north of Building C. ✔ ✔ Field Observation Report FOR­000008Report #: 10/24/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:10/25/2024 Technician:Downing, Thomas Placement Location: Proof­roll observation STA 5+00 to 8+48 on Center Drive and the access drive along the west, south, and east sides of Building C. Plans/Details: Sopris Engineering, LLC (Dated March 1, 2024) Sheet C­2.0 Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe a proof­roll of the prepared subgrade soils around Building C. We observed the contractor perform a proof­roll with a fully­loaded water truck on the access drive around Building C, in the areas that deflection was previously observed around storm inlets and the manhole structure adjacent to the southeast side of Building C. These areas had been reworked yesterday. No significant deflection of the subgrade was noted in these areas. The contractor was notified of our observations and recommendations. Additional site visits will be scheduled with our office when necessary. ✔ ✔ Field Observation Report FOR­000009Report #: 10/25/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:10/25/2024 Technician:Downing, ThomasPlacement Location:Proof­roll observation STA 5+00 to 8+48 on Center Drive and theaccess drive along the west, south, and east sides of Building C.Plans/Details:Sopris Engineering, LLC (Dated March 1, 2024) Sheet C­2.0Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe a proof­roll of the prepared subgrade soils around Building C. We observed the contractor perform a proof­roll with a fully­loaded water truck on the access drive around Building C, in the areas that deflection was previously observed around storm inlets and the manhole structure adjacent to the southeast side of Building C. These areas had been reworked yesterday. No significant deflection of the subgrade was noted in these areas. The contractor was notified of our observations and recommendations. Additional site visits will be scheduled with our office when necessary. Images: Comments: Looking south toward area of proof roll observation near manhole structure on southeast side of Building C ✔ ✔ Field Observation Report FOR­000009Report #: 10/25/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:02/25/2025 Technician:Peskuski, Ryan Placement Location:Sidewalk to the north of Building A Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to perform density testing of the sidewalk subgrade to the north of Building A. Upon arrival onsite, we observed areas that were saturated and unstable. We recommended to scarify the material and allow to dry before recompacting. Observations and recommendations were relayed to the contractor while onsite. Our office will be notified when additional testing is required. Images: ✔ ✔ Field Observation Report FOR­000010Report #: 02/25/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:02/26/2025 Technician:Peskuski, Ryan Placement Location:Sidewalk to the north of Building A Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to observe a proof roll of the sidewalk subgrade material. We observed a wheeled skid steer drive over the sidewalk sub grade. Significant deflection/pumping of the materials was observed. Our recommendations is to remove Class 6 and expose the underlying previously placed material. The underlying materials should be observed by our office before replacement of Class 6 material. Contractor was notified of our observations. Our office will be contacted when our services are needed again. Images: ✔ ✔ Field Observation Report FOR­000011Report #: 02/26/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:02/27/2025 Technician:Peskuski, Ryan Placement Location:Sidewalk to the north of Building A Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to observe the condition of the previously placed fill material under the sidewalk to the north of Building A. We observed the Class 6 material had been removed exposing the underlying fill. This fill was observed to be saturated and was pumping/deflecting under foot pressure. Our recommendation is to let the area dry out before proceeding with work. If this is not feasible, our office should be consulted for other recommendations. Images: ✔ ✔ Field Observation Report FOR­000012Report #: 02/27/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:03/11/2025 Technician:Downing, Thomas Placement Location: Proof Roll, drive/sidewalk subgrade, south side of Building "A" Plans/Details: Sopris Engineering, Job No. 30017, dated March 1, 2024. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: Soft, deflecting areas over utility trenches at southeast side of building A and soft, deflecting area a southwest corner, heading east to be scarified and recompacted. Saturated material in these areas should be removed and replaced with properly moisture conditioned material and recompacted. General Remarks: As requested, a proof roll was observed along the south side of Building "A", from the southeast corner of the building to the southwest corner. Areas of soft, deflecting soils were encountered at the water line and storm sewer line on the east side of the building. An additional soft, deflecting area was encountered on the southwest side of the building, from the southwest corner, heading east to approximately 13 line, approximately 10’ wide. We recommended that this area be scarified down one foot and allowed to air dry before being recompacted. The general contractor was notified of our observations and requested a proof roll be scheduled for tomorrow morning, Wednesday March 12, 2025. We will return as requested for a proof roll at the scheduled time. ✔ ✔ Field Observation Report FOR­000013Report #: 03/11/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:03/11/2025 Technician:Downing, ThomasPlacement Location:Proof Roll, drive/sidewalk subgrade, south side of Building "A"Plans/Details:Sopris Engineering, Job No. 30017, dated March 1, 2024.Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoDiscrepancy Remarks:Soft, deflecting areas over utility trenches at southeast side of building A and soft, deflecting area a southwest corner, heading east to be scarified and recompacted. Saturated material in these areas should be removed and replaced with properly moisture conditioned material and recompacted. General Remarks: As requested, a proof roll was observed along the south side of Building "A", from the southeast corner of the building to the southwest corner. Areas of soft, deflecting soils were encountered at the water line and storm sewer line on the east side of the building. An additional soft, deflecting area was encountered on the southwest side of the building, from the southwest corner, heading east to approximately 13 line, approximately 10’ wide. We recommended that this area be scarified down one foot and allowed to air dry before being recompacted. The general contractor was notified of our observations and requested a proof roll be scheduled for tomorrow morning, Wednesday March 12, 2025. We will return as requested for a proof roll at the scheduled time. Images: Comments: Subject area, looking west toward southwest corner of Building A ✔✔ Field Observation Report FOR­000013Report #: 03/11/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:03/12/2025 Technician:Downing, Thomas Placement Location: Proof Roll, drive/sidewalk subgrade, south side of Building "A", between 3 and 13 lines Plans/Details: Sopris Engineering, Job No. 30017, dated March 1, 2024. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a proof roll was observed along the south side of Building "A", from the 3 lines to 13 line, approximately 10 feet from the building to the south. The area of soft, deflecting soils encountered in this area yesterday had been scarified and allowed to air dry overnight. The area had been recompacted prior to our arrival on­site. Little to no deflection of the subgrade was noted during this morning’s proof roll. We judge the area on the south side of Building “A”, from 3 line to 29 line as acceptable for placement and compaction of required thickness of aggregate base course to achieve proposed sidewalk subgrade in this area. The general contractor was notified of our observations while on­site. Additional site visits will be scheduled with our office when required. ✔ ✔ Field Observation Report FOR­000014Report #: 03/12/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:03/12/2025 Technician:Downing, ThomasPlacement Location:Proof Roll, drive/sidewalk subgrade, south side of Building "A",between 3 and 13 lines Plans/Details:Sopris Engineering, Job No. 30017, dated March 1, 2024.Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy: Yes No General Remarks: As requested, a proof roll was observed along the south side of Building "A", from the 3 lines to 13 line, approximately 10 feet from the building to the south. The area of soft, deflecting soils encountered in this area yesterday had been scarified and allowed to air dry overnight. The area had been recompacted prior to our arrival on­site. Little to no deflection of the subgrade was noted during this morning’s proof roll. We judge the area on the south side of Building “A”, from 3 line to 29 line as acceptable for placement and compaction of required thickness of aggregate base course to achieve proposed sidewalk subgrade in this area. The general contractor was notified of our observations while on­site. Additional site visits will be scheduled with our office when required. Images: Comments: Subject area, looking west toward southwest corner of Building A ✔ ✔Field Observation Report FOR­000014Report #: 03/12/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:03/12/2025 Technician:Downing, Thomas Placement Location: Proof Roll, drive/curb subgrade, west side of Building "A" Plans/Details: Sopris Engineering, Job No. 30017, dated March 1, 2024. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: Soft, deflecting subgrade was observed along the curb line on west side of building. Contractor to scarify this area and allow soils to air dry before recompacting. General Remarks: As requested, a proof roll was observed along the west side of Building "A", in the curb and gutter and drive area. An area of soft, deflecting soils was encountered along the west curb line during today’s proof roll. The main drive in this area was acceptable. We recommended the curb subgrade be scarified and allowed to air dry. Earthwork contractor indicated they would scarify this area as recommended. The general contractor was notified of our observations while on­site. A return visit was scheduled for additional proof roll observations in this area for tomorrow, Thursday March 13, 2025. ✔ ✔ Field Observation Report FOR­000015Report #: 03/12/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:03/12/2025 Technician:Downing, ThomasPlacement Location:Proof Roll, drive/curb subgrade, west side of Building "A"Plans/Details:Sopris Engineering, Job No. 30017, dated March 1, 2024.Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes No Discrepancy Remarks: Soft, deflecting subgrade was observed along the curb line on west side of building. Contractor to scarify this area and allow soils to air dry before recompacting. General Remarks: As requested, a proof roll was observed along the west side of Building "A", in the curb and gutter and drive area. An area of soft, deflecting soils was encountered along the west curb line during today’s proof roll. The main drive in this area was acceptable. We recommended the curb subgrade be scarified and allowed to air dry. Earthwork contractor indicated they would scarify this area as recommended. The general contractor was notified of our observations while on­site. A return visit was scheduled for additional proof roll observations in this area for tomorrow, Thursday March 13, 2025. Images: Comments: Subject area, looking north toward northwest corner of property Comments:soft, deflecting soils along west curb line ✔✔ Field Observation Report FOR­000015Report #: 03/12/2024 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:03/24/2025 Technician:Thibault, Sandon Placement Location:Subgrade west of Building A, curb and gutter Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, we observed a proofroll of the curb and gutter subgrade west of Building A. The subgrade west of Building A was proofrolled with a loaded water truck. Proofroll was considered acceptable. Our office will be contacted when additional inspections are needed. Images: Comments:Subgrade west side of Building A. ✔ ✔ Field Observation Report FOR­000016Report #: 03/24/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:03/26/2025 Technician:Thibault, Sandon Placement Location:South Side of Building A, parking lot area. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: This area was proofrolled yesterday 3­25­2025, with unsatisfactory results. The contractor decided to subexcavate 12­inches and replace with suitable materials to ensure stability. At this site visit, it was suggested to the contractor to proofroll the resulting subexcavation to determine stability prior to importing suitable material. Images: Comments: Looking east along south side of Building A parking area. Comments:Looking east of Building A parking area. ✔ ✔ Field Observation Report FOR­000017Report #: 03/26/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:03/26/2025 Technician:Thibault, SandonPlacement Location:South Side of Building A, parking lot area.Discrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes NoDiscrepancy:Yes NoGeneral Remarks:This area was proofrolled yesterday 3­25­2025, with unsatisfactory results. The contractor decided to subexcavate 12­inchesand replace with suitable materials to ensure stability. At this site visit, it was suggested to the contractor to proofroll theresulting subexcavation to determine stability prior to importing suitable material.Images: Comments: Looking east along south side of Building A parking area. Comments:Looking east of Building A parking area. Comments:Looking east of Building A parking area. ✔✔ Field Observation Report FOR­000017Report #: 03/26/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:03/26/2025 Technician:Thibault, Sandon Placement Location: Building A. Parking area. South side of roadway. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a second site visit was made to observe the proofroll of the red silty rock fill place in the subexcavation in the parking area south of Building A. Four small areas were removed and replaced with a dryer fill material, recompacted and reproofrolled with satisfactory results. A site visit was scheduled for tomorrow morning for density testing on the base course placed below the curb and gutter only. Images: Comments:Proofrolling the parking area south of Building A ✔ ✔ Field Observation Report FOR­000018Report #: 03/26/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:03/27/2025 Technician:Cozza, Seth Placement Location:East side of Building A Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to the east side of Building A to observe a proofroll. We observed a water truck drive over the area of observation, we identified multiple areas with significant pumping of the material under load recommended fixing areas prior to base placement. Contractor was notified onsite, our office will be notified when more observations are needed. Images: Comments:Basic overview of site ✔ ✔ Field Observation Report FOR­000019Report #: 03/27/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:03/28/2025 Technician:Cozza, Seth Placement Location:East of Building A proof roll Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to observe a proof roll on the east side of Building A. A full water truck was driven back and fourth across the material and we observed movement in the bottom section of material starting at the southeast corner of the building heading north 50ft on either side of the road. We recommended reworking the bottom portion, due to temporary power lane incomplete grading this area was not ready for proof rolling. The upper portion of the road was deemed satisfactory. Another site visit will take place when our office is notified. Weather pending. ✔ ✔ Field Observation Report FOR­000020Report #: 03/28/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:03/28/2025 Technician:Cozza, SethPlacement Location:East of Building A proof rollDiscrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No Discrepancy Remarks: As requested, a site visit was made to observe a proof roll on the east side of Building A. A full water truck was driven back and fourth across the material and we observed movement in the bottom section of material starting at the southeast corner of the building heading north 50ft on either side of the road. We recommended reworking the bottom portion, due to temporary power lane incomplete grading this area was not ready for proof rolling. The upper portion of the road was deemed satisfactory. Another site visit will take place when our office is notified. Weather pending. Images: ✔ ✔ Field Observation Report FOR­000020Report #: 03/28/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2 Activity Date:03/31/2025 Technician:Peskuski, Ryan Placement Location:East side of Building A. Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe a proof roll of the subgrade below the road on the east side of Building A. We observed a fully loaded water truck roll over the area that had previously failed. We did not observe any significant pumping or deflection of the material under load. Our observations indicated that the subgrade was sufficiently compacted and ready for ABC to be applied overtop. Images: Comments:Equipment used.Comments:Area of observation. ✔ ✔ Field Observation Report FOR­000021Report #: 03/31/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 2Page 1 of 1 Activity Date:04/08/2025 Technician:Downing, Thomas Placement Location: Proof roll observation, north half of entrance to Building A, at intersection of Center Drive and Building A access drive Discrepancy: The items observed were found to be in general conformance with the approved drawings and standard construction practice: Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe a proof roll at red top elevation for the north half of the driveway for Building A adjacent to Center Drive. A loaded tandem axle water truck was utilized for the proof roll. The north half of the intersection, from approximately 5’ north of the 01­EX storm inlet is acceptable. Significant deflection of the subgrade around storm inlet 01­EX was observed, as well as deflection of the irrigation trench running across the intersection. We recommended these areas be reworked to a depth of 18”­24”. The general contractor was notified of our observations. Additional site visits will be scheduled when required. ✔ ✔ Field Observation Report FOR­000022Report #: 04/08/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 1 of 3Page 1 of 2 Activity Date:04/08/2025 Technician:Downing, ThomasPlacement Location:Proof roll observation, north half of entrance to Building A, atintersection of Center Drive and Building A access driveDiscrepancy:The items observed were found to be in general conformance with the approved drawings and standard constructionpractice:Yes No Discrepancy: Yes No General Remarks: As requested, a site visit was made to observe a proof roll at red top elevation for the north half of the driveway for Building A adjacent to Center Drive. A loaded tandem axle water truck was utilized for the proof roll. The north half of the intersection, from approximately 5’ north of the 01­EX storm inlet is acceptable. Significant deflection of the subgrade around storm inlet 01­EX was observed, as well as deflection of the irrigation trench running across the intersection. We recommended these areas be reworked to a depth of 18”­24”. The general contractor was notified of our observations. Additional site visits will be scheduled when required. Images: Comments:area of observation Comments:proof roll in progress ✔ ✔Field Observation Report FOR­000022Report #: 04/08/2025 Glenwood Springs 234 Center Drive Glenwood Springs, CO 81601 Phone: 970­945­2809 Client: Andover Management Group 333 East main Street Suite 300 Louisville, KY 40202 Project: GS06693.001F­345 214 Center Drive 214 Center Drive Garfield County, CO Legal: Contractor to ensure integrity of completed work is maintained during subsequent construction activities.Page 2 of 3Page 2 of 2