Loading...
HomeMy WebLinkAboutOWTS Installation Observation 09.30.25CBO Inc. 129 Cains Lane Carbondale, CO 81623 970.309.5259 carla.ostberg@gmail.com September 30, 2025 Project No. C1959 Dan Richardson dan@boldepp.com Onsite Wastewater Treatment System (OWTS) Installation Observations 116 Crystal River Road Garfield County, Colorado Permit SEPT-9281 Dan, CBO Inc. observed the installation of the onsite wastewater treatment system (OWTS) on September 25, 2025 and September 29, 2025 for the subject property. Alpine Excavation and Land Clearing installed the system. The OWTS design is based on 4-bedrooms. An average daily wastewater flow of 525 GPD was used. The existing septic tank was abandoned by crushing it and filling the void. The existing soil treatment area (STA) was abandoned in place and any distribution piping was removed where the new STA was installed. The new 4-inch SDR-35 sewer line exiting the residence had a double-sweep clean out and a minimum 2% grade to the septic tank. The sewer line connects to the existing cast iron sewer line with a Fernco as close to the foundation as feasible. The system installation included a 1500-gallon, two-compartment Infiltrator® poly septic tank with an Orenco® Biotube Effluent filter followed by a 500-gallon, single-compartment Infiltrator® poly pump chamber with an Orenco® Biotube Pump Vault and an Orenco® PF3005 pump. These filters must be cleaned annually, or as needed. The septic tanks are anchored with Deadmen. Anchoring was implemented as a preventative measure and not required based on the height of the groundwater in the area of the septic tanks being less than 36-inches from the bottom of the septic tank and depth of cover over the septic tanks at approximately 2-feet. The floats are set to dose 65 gallons each pump cycle. The control panel for the pump is located within line of sight of the septic tank. Start up was performed by Valley Precast out of Buena Vista. Effluent is pressure dosed through a 1.5-inch diameter pump line to a 13’ x 50.5’ mounded, unlined sand filter. The excavation for the sand filter begins 1.0-foot below native grade. Two-feet of sand filter material was installed in the over-excavated footprint, resulting in 1-foot of sand filter material extending above native grade. Effluent is pumped through a 1.5-inch diameter pump line from the pump chamber to an Orenco® automatic distributing valve (ADV), model 6402. The ADV was placed at a high point in an insulated riser with access from grade. Laterals are 1.5-inches in diameter with 5/32-inch diameter orifices facing down, spaced 3.0-feet on center, installed on the GeoMat™ with the filter fabric over the laterals. Four 39” wide GeoMat™ sheets are placed on the 13-foot wide bed. Each 1.5-inch diameter lateral ends in a sweeping ell facing up with a ball valve for flushing. Inspection ports were installed at each corner of the bed. The OWTS was generally installed according to specifications. This observation is not a guarantee of workmanship and/or parts and materials. CBO Inc. should be notified if changes are made to the OWTS in the future. Any additional OWTS construction must be according to the county regulations. LIMITS: Observations are limited to components that are visible at the time of the inspection. The installer must have documented and demonstrated knowledge of the requirements and regulations of the county in which they are working. The quality of the installation is dependent on the expertise of the installer, soil type, and weather conditions. Please call with questions. Sincerely, CBO Inc. Carla Ostberg, MPH, REHS - Garfield County Public Health 2014 Blake Ave. Glenwood Springs, CO 81601 Phone: (970) 945-6614 ext. 8150 For inspections, call: 970-945-6614 ext. 8150 and call the Design Engineer, if applicable Project Address: 116 Crystal River Road, Carbondale Parcel No.: _239333409001 Owner Name: Owl Moon LLC Owner Phone: (239) 379-3414 Designed By: CBO Inc. Designer Phone: (970) 309-5259 Number of Bedrooms: _4_Minimum Tank Capacity: 1,250-gallon Minimum Absorption: 656.25 ft2 OWTS PERMIT KEEP AVAILABLE AT PROJECT SITE Permit Number _SEPT-9281______________________________ Permit Type X New X Repair X Remodel/addition X Tank only Issue Date _06/13/2025____________________ Expiration Date_06/13/2026_________________ Permit Conditions: This OWTS Permit is approved on the condition of compliance with the report and design as submitted by CBO Inc. dated May 15, 2025. Changes to the design and permit must be approved by Garfield County Public Health and the designer prior to construction. Prior to installation of OWTS components, the soils in the proposed STA must be confirmed by the designer and a report of the soil conditions shall be provided to GCPH. The new OWTS will serve an existing four-bedroom residence. The new OWTS components will consist of a new 1,500-gallon two compartment septic tank on the CDPHE approved list, set level with access to grade and equipped with an effluent filter in the outlet tee. Effluent will flow from the septic tank to a 500-gallon single compartment pump chamber which will house a new screened high-head pump. The septic tank and pump chamber will be anchored according to manufacturer recommendations due to the presence of high ground water. Effluent will be dosed from the pump chamber to an automatic distributing valve set at the high point of the system that will distribute effluent to 656.5 ft2 of STA. The new STA will consist of a 13 ft by 50.5 ft unlined sand filter bed, consisting of at least 2 feet of secondary sand media overlain by perforated distribution laterals placed in GeoMat distribution media. Distribution laterals are to be 1 ½ inch Schedule 40 PVC, with 5/32-inch orifices every 3-feet on center facing downwards with orifice shields. Each lateral is to end in a flushing valve at the distal end. The residual head (squirt height) at the end of the system is to be 5-feet. The lower infiltrative surface shall be at 1-foot below grade and final cover will be mounded to reach approximately 1.5ft of soil over the distribution laterals and sloped at a 3:1 ratio to the native grade. Inspection ports are to be installed at each corner of the bed. Maintain all setbacks and elevations as designed. The existing tank and pump chamber must be abandoned per Garfield County OWTS Regulations by crushing or removal. To assist in scheduling, please contact Garfield County Public Health (970-945-6614 ext. 8150) to notify the start of OWTS construction. Contact the designer and Garfield County Public Health at least 48 hours prior to requesting final inspection of the installed system prior to backfill. NO OWTS COMPONENT SHALL BE BACKFILLED WITHOUT PRIOR APPROVAL FROM GARFIELD COUNTY PUBLIC HEALTH AND THE DESIGNER. Agreement All installations must comply with all requirements of the Garfield County OWTS regulations including but not limited to the conditions specified above. In consideration of the issuance of the permit, the applicant hereby agrees to comply with all laws and regulations related to the zoning, location, construction, and erection of the proposed OWTS and associated structures for which this permit is granted. The applicant further agrees that if the above said regulations are not fully complied with in the zoning, location, erection, and construction of the above described OWTS and structure, the permit may then be revoked by notice from the Health Department and immediately become null and void. The issuance of a permit and specifications of terms and conditions therein will not constitute assumption of liability, nor create presumption that the local public health agency or its employees may be liable for the failure or malfunctioning of any system. Permit issuance will not constitute a certification that the system, the equipment used in the system, or any component used for system operation will ensure continuous compliance with the provision of the OWTS Act, the regulations adopted thereunder, or any terms and conditions of a permit. Permit Approval Plans and specifications for the proposed OWTS have been reviewed and are considered satisfactory. Permission is hereby given to the property owner(s) to perform the work indicated in accordance with the Garfield County OWTS Regulation. This Permit will expire 1 year from the date of issuance unless construction on the system has commenced. An "as-built" drawing must be submitted and inspection of the system must be completed by GCPH before final approval of the system will be issued. 06/13/2025 Issued By: Garfield County Environmental Health Department Date infiltratorwater.com • (800) 221-4436 Buoyancy Control Guidance July 2023Infiltrator Tanks Before you Begin This guidance document presents a method for assessing buoyancy control needs for Infiltrator Water Technologies Infiltrator tanks. Tank buoyancy control measures must be implemented according to state and/or local regulations and approvals, which may supersede these guidelines. If unsure of the requirements for a particular site, contact the state or local health department or permitting authority. If tank buoyancy control measures are implemented, refer to Infiltrator Tank General Installation Instructions and Riser Connection Guidance documents, as applicable, for completing the installation. This guidance document is not a tank installation instruction document. How to Use this Document 1. Using Step 1, Table 1, and Figures 1 and 2, verify that the level of subsurface water is below the height of the outlet pipe saddle and determine if buoyancy control is required. See page 2 notes on terminology. 2. Use the appropriate row in Step 2, Table 2 to determine the minimum buoyancy control methods for the site conditions. 3. Once the preferred buoyancy control method is selected, follow the implementation procedures provided in Step 3. Step 1 – Determine Need for Buoyancy Control Required information: (1) maximum height of subsurface water above the tank bottom; and (2) the depth of soil cover above the tank top. Tank buoyancy control may be required if: • the level of subsurface water outside the tank has the potential to rise 30 inches (750 mm) or more above the bottom of the tank; and • less than 12 inches (300 mm) of soil cover is to be placed as backfill over the tank top. [ FOR ALL TANK MODELS, NO BUOYANCY CONTROL IS REQUIRED IF THERE ARE AT LEAST 12 INCHES (300 MM) OF SOIL COVER ABOVE THE TANK TOP. FOR THE IM-300, NO BUOYANCY CONTROL IS REQUIRED IF THERE ARE AT LEAST 6 INCHES (150 MM) OF SOIL COVER ABOVE THE TANK TOP. Table 1 Instructions 1. In the left-hand column of Table 1, locate the row corresponding to the height of the subsurface water elevation outside the tank and above the tank bottom (Parameter I) for the site conditions. See Figure 2. 2. Follow that row to the right until reaching the column corresponding to the depth of soil cover above the tank top (Parameter II). See Figure 2. 3. If the tank model is listed in that cell, then buoyancy control is required, proceed to Step 2. If the tank model is not listed in that cell, then no buoyancy control is required. 4. Infiltrator tanks shall not be installed where the subsurface water level outside the tank exceeds the height of the outlet pipe saddle. See Figure 1 and Table 1, Note 4 for outlet pipe saddle information. Notes: 1. Infiltrator tank models include: IM-300, IM-540, IM-1060, CM-1060, IM-1250, and IM-1530. 2. Minimum 6 inches (150 mm) soil cover backfill is required. 3. Infiltrator tanks shall not be installed where the subsurface water level outside the tank exceeds the height of the outlet pipe saddle. See Figure 1. 4. The height of the outlet pipe saddle for the IM-540, IM-1060, CM-1060, IM-1250, and IM-1530 is 43 in (1,075 mm). The height of the outlet pipe saddle for the IM-300 is 40.75 in (1,035 mm). 5. For Indiana installations, if the depth of uninterrupted saturated soil conditions cannot be determined from the site soil evaluation report or other site-related data and other information indicates the possible presence of a perched ground water table, no buoyancy controls are required. See page 2 note on terminology. Table 1: Infiltrator Tank Models1 and Conditions Requiring Buoyancy Control Parameter I: Subsurface water height above tank bottom Parameter II: Soil cover depth above tank top2 A B 6 in (150 mm) up to 12 in (300 mm) 12 in (300 mm) or greater 1 Above outlet pipe saddle4 (greater than 43” [1,075 mm]Do not install tank Do not install tank 2 36” (900 mm) to 43” (1,075 mm)4 (to outlet pipe saddle) All models except IM-300 Not Required 3 30” (750 mm) to 36” (900 mm) IM-1530 Not Required 4 Less than 30” (750 mm)Not Required Not Required Figure 1: Limitations When Subsurface Water is Present Above Tank Bottom Figure 2: Buoyancy Control Parameters for Table 1Depth of Soil Cover Above Tank Top Tank Top Tank Bottom 6" (150 mm) min. 48" (1,200 mm) max. Outlet Pipe Saddle: Maximum Allowable Subsurface Water Elevation Maximum Subsurface Water Condition Above Tank Bottom 1 Do Not Install Allowable Tank Bottom Tank Top Parameter II Depth of Soil Cover Above Tank Top Parameter IPosition ofMaximumSubsurfaceWater ConditionAbove Tank Bottom Depth of Soil Cover Above Tank Top Tank Top Tank Bottom 6" (150 mm) min. 48" (1,200 mm) max. Outlet Pipe Saddle: Maximum Allowable Subsurface Water Elevation Maximum Subsurface Water Condition Above Tank Bottom 1 Do Not Install Allowable Tank Bottom Tank Top Parameter II Depth of Soil Cover Above Tank Top Parameter IPosition ofMaximumSubsurfaceWater ConditionAbove Tank Bottom Table 2: Buoyancy Control Method Selection Tank Model Parameter 1:Position of subsurface water above tank bottom Parameter 2:Soil cover depth above tank top Buoyancy Control Methods1 Minimum supplemental downward force required3 (total, both tank sides) Wood Beam Anchor Ballast Options (min. length/side)Concrete Beam Anchor Ballast Options (min. length/side)Precast concrete plates (min. no./side) Helical anchors2 (min. no./side) Anchor-lock system2 (min. no./side) Concrete collar (min. width x min. height)1 6”x6” beam 2 6”x6” beam with cross-members 3 6”x6” beamside-by-side 1 6” wide 2 8” wide 3 12” wide IM-540 36 in (900 mm) to outlet pipe saddle4 6 in (150 mm) to 12 in (300 mm) 3.8 ft (1.2 m) 3.8 ft (1.2 m) 3.8 ft (1.2 m) 3.8 ft (1.2 m) 3.8 ft (1.2 m) 3.8 ft (1.2 m)2 2 2 6 in (150 mm) x 9 in (225 mm) 1,000 lbs (450 kg) IM-1060 36 in (900 mm) to outlet pipe saddle4 6 in (150 mm) to 12 in (300 mm) 7.5 ft (2.3 m) 6.0 ft (1.8 m) 5.5 ft (1.7 m) 7.5 ft (2.3 m) 6.5 ft (2.0 m) 5.0 ft (1.5 m)2 2 2 6 in (150 mm) x 9 in (225 mm) 3,550 lbs (1,620 kg) CM-1060 36 in (900 mm) to outlet pipe saddle4 6 in (150 mm) to 12 in (300 mm) 4.8 ft (1.5 m) 4.8 ft (1.5 m) 4.8 ft (1.5 m) 6.3 ft (1.9 m) 5.5 ft (1.7 m) 4.8 ft (1.5 m)2 2 2 6 in (150 mm) x 9 in (225 mm) 2,200 lbs (1,000 kg) IM-1250 30 in (750 m) to outlet pipe saddle4 6 in (150 mm) to 12 in (300 mm)6.3 ft (1.9 m)6.3 ft (1.9 m)6.3 ft (1.9 m)6.3 ft (1.9 m)6.3 ft (1.9 m)6.3 ft (1.9 m)2 2 2 6 in (150 mm) X 9 in (225 mm)3,300 lbs IM-1530 30 in (750 mm) to outlet pipe saddle3 6 in (150 mm) to 12 in (300 mm) Use alternate method (1,500 kg)9.5 ft (2.9 m) Use alternate method Use alternate method Use alternate method 2 2 2 9 in (225 mm) x 9 in (225 mm) 6,200 lbs (2,820 kg) Notes: 1. See method-specific technical specifications and installation instructions below. 2. See manufacturer-specific information below. 3. Supplemental downward force is provided for custom-designed anchor ballast systems. See discussion below. 4. The height of the outlet pipe saddle for the IM-540, IM-1060, CM-1060, IM-1250, and IM-1530 is 43 in (1,075 mm). 5. For the IM-300, no buoyancy control is required if there are at least 6 inches (150 mm) of soil cover above the tank top. Installation Terminology Notes: 1. “Subsurface water” refers to a water-saturated zone of soil. Do not install if subsurface water is continuous from the tank bottom elevation to any point above the outlet pipe saddle elevation. 2. “Uninterrupted saturated soil” refers to water-saturated soil with no gaps in the saturated condition. An example of a gap in the saturated condition is a perched water table, when two water-saturated soil zones are interrupted by an unsaturated soil zone. Do not install if uninterrupted saturated soil is present from the tank bottom elevation to any point above the outlet pipe saddle elevation. 3. A perched water table is allowable above the outlet pipe saddle elevation only if unsaturated soil is present between the perched water table zone and tank bottom elevation. Step 2 – Determine Buoyancy Control Method Step 2 is used if the Step 1 analysis shows that buoyancy control is required for the tank model and installation conditions. The site-specific maximum height of subsurface water outside of the tank and above the tank bottom and the depth of soil cover above the tank top must be known to complete Step 2. Table 2 Instructions For the appropriate tank model, select the desired buoyancy control method under each method description column. Refer to Step 3 – Implementation and Supplemental Step 3 – Implementation Effective buoyancy control requires careful preparation, proper excavation, precise placement, secure strapping and proper backfilling, as described and illustrated in Step 3 below and the Infiltrator Tank Installation Instructions. Step 3 includes specifications and system installation guidance for five buoyancy control system categories. • 3-1: Beam Anchor Ballast • 3-2: Precast Concrete Plate Anchor Ballast • 3-3: Helical Anchors and Anchor-Lock Assemblies • 3-4: Concrete Collar Anchor Ballast • 3-5: Custom-Designed Buoyancy Controls Following Step 3, supplemental technical guidance is provided for use with these buoyancy control methods. See the Supplemental Technical Guidance section for strap information as well. Straps meeting the appropriate are available from IWT (TANK-BCS-KIT). This guidance document is not a tank installation instruction document. Refer to the Infiltrator Tank Installation Instructions for complete information on tank installation requirements. Step 3-1: Beam Anchor Ballast The beam anchor ballast options shown in Table 2 include the installation of wood or concrete beams adjacent to the tank, connected with two straps positioned across the top of the tank. The beam anchor ballast option allows the installer to select either beam construction material. The beam options resist tank buoyant forces using the weight of the soil column over the beam anchor ballast to counteract uplift. Therefore, it is critical that the widest dimension of the beam be placed horizontally on the base of the tank excavation, running parallel with the length of the tank. Beam construction materials shall meet the following specifications: • Pressure-treated lumber shall be American Wood Protection Association (AWPA) Use Category UC4B, UC4C, UC5B, or UC5C. • Concrete parking bumpers (also referred to as wheel stops) shall be steel- reinforced concrete with dimensions of 6-, 8-, or 12-inches wide by 6 inches high (150 mm, 200 mm, or 300 mm wide x 150 mm high). • Fasteners shall be hot-dipped galvanized steel or stainless steel. WARNING: Infiltrator does not recommend the use of beams fabricated using thermoplastics, including, but not limited to, chambers, pipe, decking, and parking bumpers. 2 Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. Wood Beams The wood beam anchor ballast can be configured three ways, depending on material and space availability: • Wood Beam Option 1: Pressure-treated 6” x 6” – This option includes a single 6” x 6” beam connected to straps on each side of the tank (Figure 3). Figure 3: Wood Beam Option 1 • Wood Beam Option 2: Pressure-treated 6” x 6” with cross-members – This option includes a single 6” x 6” beam on each side of the tank equipped with a series of pressure-treated wood cross-members to increase the surface area of the beam, connected to straps (Figure 4). Cross-members shall be 2” x 8” x 18” connected to the beam with four screws per member and distributed uniformly along the long axis of the beam. Cross member placement must not interfere with the strap locations. Figure 4: Wood Beam Option 2 • Wood Beam Option 3: Pressure-treated 6” x 6” members placed side-by-side – This option includes two 6”x6” beams placed side by side and connected to looped straps on each side of the tank (Figure 5). The beams shall be connected using two 2” x 6” members screwed to the top and bottom of the side-by-side beams in two locations near the ends of the beams. Fasteners shall be 3.5-in screws with washers. Figure 5: Wood Beam Option 3 Concrete Beams The concrete beam can be configured three ways, depending on material and space availability, using parking bumpers (also referred to as wheel stops). This option includes a single concrete beam connected to straps on each side of the tank (Figures 6 and 7). Three concrete beam anchor ballast options are available, depending upon the parking bumper width as follows: • Option 1: 6-in-wide precast concrete parking bumper • Option 2: 8-in-wide precast concrete parking bumper • Option 3: 12-in-wide precast concrete parking bumper Note that the Concrete Beam Option is not recommended for use with the IM-1530 tank due to limitations in availability of parking bumpers that would be long enough to provide adequate resisting force. Use an alternative buoyancy control method for the IM-1530. Figure 6: Concrete Beam Parking Bumpers Figure 7: Concrete Beam Table 2 provides the minimum length of beam required for the tank model and installation conditions. A minimum 1.5 factor of safety has been applied to determine the minimum required beam length. Wood and concrete beam installation should be as described below. See Ratchet Strap Material Specifications section below for additional information. 1. Determine the minimum beam length from Table 2. 2. Place beams on the excavation bottom, such that the beam and tank bottoms are at the same elevation. The beam must be oriented with the widest dimension placed horizontally. 3. Position beams parallel to the long axis of the tank. 4. Position beams to be centered between strap locations and extend at least 6 in beyond the strap locations. 5. Position the beam a minimum of 6 in (150 mm) from the outermost footprint of the tank to allow connection of the strap system and placement and compaction of soil backfill below the tank haunches. WARNING: Never place any portion of the anchor ballasts beneath the outermost footprint of the tank, including beneath the haunches. 2, 3, 52, 3, 5 Position beam and tank. 44 Position strap on beam. Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. 3 WARNING: Do Not Use Cable Tie-Downs: The use of cables to connect anchor ballasts in lieu of strapping is prohibited. Cables concentrate the load exerted by the buoyancy control system within a small area on the tank surface, resulting in the potential to damage the tank. 6. Position the 14-ft-long (4.3 m) strap across the top of the tank at the locations embossed for strap placement (Figure 10). 7. At each beam connection point, wrap the 5-ft-long (1.5 m) looped-end strap to the beam at points aligning with the straps placed across the top of the tank. If the beam includes cross-members, position to prevent interference between looped-end straps and cross-members. 8. Connect the hooked end of the 14-ft-long (4.3 m) strap to the two looped ends of the 5-ft-long (1.5 m) looped-end strap. 9. Connect the non-hooked end of the 14-ft-long (4.3 m) strap to the ratchet. 10. Connect the hooked end of the ratchet strap to the 5-ft-long (1.5 m) looped-end straps, such that the ratchet is positioned below the mid- seam elevation of the tank. Do not allow the ratchet to be in contact with the tank. 11. Remove slack in the straps through a combination of beam positioning and the ratchet, such that the ratchet is positioned below the mid-seam elevation of the tank and not contacting the tank. Maintain the minimum 6-in (150 mm) spacing between the edge of tank and beam. 12. Place and compact backfill beneath the tank haunches and around and above the beams to an elevation 6 inches (150 mm) above the top of the beams. Place and compact backfill as described in the Infiltrator Tank Installation Instructions. 13. With the anchor ballasts stabilized by 6 inches (150 mm) of compacted backfill, tension the strap to eliminate all slack using the ratchet. The tension should make the strap tight, without displacing the beams or damaging the tank. 14. Do not over tighten the straps. 15. Complete backfilling the tank as described in the Infiltrator Tank Installation Instructions. Step 3-2: Precast Concrete Plate Anchor Ballast The precast concrete plate anchor ballast option shown in Table 2 includes the installation of four individual concrete anchor ballasts, connected with straps positioned across the top of the tank. Historically, precast concrete plate anchors have been spare concrete septic tank lids repurposed as anchor ballasts, but they can be fabricated specifically as anchor ballasts as well. The precast concrete plate anchor ballast option allows the installer to select plate size and shape, provided that each plate provides a minimum 4 ft2 (0.37 m2) of horizontal area and minimum 3-in thickness (75 mm). The precast concrete plate anchor ballast options resist tank buoyancy forces using the weight of the soil column over the plate anchor ballast to counteract uplift. Therefore, it is critical that the widest dimension of the plate anchor ballast be placed horizontally on the base of the tank excavation. Plate construction material shall be precast concrete having a minimum 3,500 psi (24.1 MPa) compressive strength at 28 days and minimum 6% air entrainment. Connectors protruding from the anchor plate and used for strap connection shall be steel reinforcing bar, galvanized steel, or stainless steel capable of supporting a 2,500-lb (1,134 kg) tensile force. Do not use plastic connectors. WARNING: Infiltrator does not recommend the use of plate anchor ballasts fabricated using materials other than concrete. The precast concrete plate anchor ballast can be configured using a square, rectangular, or circular shape. For rectangular-shaped anchor ballasts, the long axis of the plate shall be placed parallel with the long axis of the tank. Precast concrete plate anchor ballast sizing and configuration options are shown in Table 3 and Figure 8. Table 3: Precast Concrete Plate Anchor Ballast Precast concrete plate anchor ballast shape Minimum horizontal dimensions (minimum 3-in (75 mm) thickness) Square 2 ft x 2 ft (0.61 m x 0.61 m) Rectangular Maintain a 1 ft (0.31 m) minimum width, with length to provide a minimum 4 ft2 (0.37 m2 ) horizontal plate area per anchor ballast Circular 2.3 ft diameter (0.70 m diameter) As shown in Table 2 and Figure 8, four precast concrete plate anchor ballasts are required for all tank models. The minimum horizontal plate area specifications are the same for all tank models. A minimum 1.5 factor of safety has been applied to determine the minimum horizontal plate area. Figure 8: Precast Concrete Plate Anchor Ballast Options Precast concrete plate anchor ballast installation should be as described below. See Ratchet Strap Material Specifications section below for additional information. 1. Use 4 precast concrete plate anchor ballasts per installed tank. 2. Place anchor ballasts on the excavation bottom, such that the anchor ballast and tank bottoms are at the same elevation. The precast concrete plate anchor ballast must be oriented with the widest dimension placed horizontally. 3. Position anchor ballasts to align with the locations on the tank embossed for strap placement (Figure 10). 4. Position the anchor ballasts a minimum of 6 in (150 mm) from the outermost footprint of the tank to allow connection of the strap system and placement and compaction of soil backfill below the tank haunches. WARNING: Never place any portion of the anchor ballasts beneath the outermost footprint of the tank, including beneath the haunches. STRAPWIDTH MINIMUM 3-IN. (75 mm) THICK PLATE MAY BE SQUARE, RECTANGLE, OR CIRCLE WITH MINIMUM 4 FT2 (0.37 m2) HORIZONTAL AREA STRAP WITH RATCHET (TYP.) 66 Position straps on tank. 8, 108, 10 Connect straps to beam. Remove strap slack. 10, 1110, 11 Position plate and tank. 2, 42, 4 4 Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. WARNING: Do Not Use Cable Tie-Downs: The use of cables to connect anchor ballasts in lieu of strapping is prohibited. Cables concentrate the load exerted by the buoyancy control system within a small area on the tank surface, resulting in the potential to damage the tank. Cable may damage the tank. 5. Position the 14-ft-long (4.3 m) straps across the top of the tank at the locations embossed for strap placement (Figure 10). 6. Connect the hooked end of the 14-ft-long (4.3 m) strap to the concrete anchor ballast hardware. Looped-end straps are not required to connect to the anchor ballast hardware. 7. Connect the non-hooked end of the 14-ft-long (4.3 m) strap to the ratchet. 8. Connect the hooked end of the ratchet strap to the concrete anchor ballast hardware. Looped-end straps are not required to connect to the anchor ballast hardware. 9. Position the ratchet below the mid-seam elevation of the tank. Do not allow the ratchet to be in contact with the tank. 10. Remove slack in the straps through a combination of anchor ballast positioning and the ratchet. 11. Place and compact backfill beneath the tank haunches and around and above the anchor ballasts to a height of 6 in (150 mm) above to top of the anchor ballast. Place and compact backfill as described in the Infiltrator Tank Installation Instructions. 12. With the anchor ballasts stabilized by 6 inches (150 mm) of compacted backfill, tension the strap to eliminate all slack using the ratchet. The tension should make the strap tight, without displacing the precast concrete plate anchor ballasts or damaging the tank. 13. Do not over tighten the straps. 14. Complete backfilling the tank as described in the Infiltrator Tank Installation Instructions. Step 3-3: Helical Anchors and Anchor-Lock Assemblies Helical anchors and anchor-lock assemblies may be installed as buoyancy control systems. For both types of system described below, refer to the equipment manufacturer’s installation instructions for details on how to use and install the specified products. For helical and anchor-lock systems other than those described below, use Step 3-5: Custom- Designed Buoyancy Controls and Table 2 to determine the required pullout force per anchor and the manufacturer’s literature to determine the required product model and installation requirements. • Chance™ No-Wrench Screw Anchors – The Chance helical anchor shall have a 6-inch (150 mm) diameter helix, Class 7, or equal. These anchors rely on the shear strength of the soil combined with the weight of the soil above the anchor helix to provide holding strength. Proper installation is to 4 ft (1.2 m) below the bottom of the tank excavation and to within 5° of alignment with the strap alignment. Helical anchors should be installed so that the eye loop is level with the bottom of the tank excavation. Determine the proper locations for anchor installation to ensure that tie-down straps will be aligned properly for each tank model (Figure 10). Never place helical anchors beneath the outermost footprint of the tank, including beneath the tank haunches. Follow the anchor manufacturer installation and testing instructions. • DuckBill® Anchor-Lock Assembly – DuckBill models are shown for each tank model in Table 4 below. These anchors rely on the shear strength of the soil combined with the weight of the soil above the anchor to provide holding strength. Determine the proper locations for anchor installation to ensure that tie-down straps will be aligned properly for each tank model (Figure 10). The system installer shall determine the DuckBill assembly materials of manufacture for the specified model. Polyester straps shall be connected to the DuckBill anchor wire assembly such that the wire assembly is not in contact with the tank body. Never place anchor-lock assemblies beneath the outermost footprint of the tank, including beneath the tank haunches. Follow the anchor manufacturer installation and testing instructions. Table 4: Anchor-lock Assembly Specifications Tank Model DuckBill Assembly IM-540 Model 40 IM-1060 Model 68 CM-1060 Model 68 IM-1250 Model 68 IM-1530 Model 88 WARNING: Do Not Use Cable Tie-Downs: The use of cables to connect anchor ballasts in lieu of strapping is prohibited. Cables concentrate the load exerted by the buoyancy control system within a small area on the tank surface, resulting in the potential to damage the tank. Cable may damage the tank. Step 3-4: Concrete Collar Anchor Ballast The concrete-collar anchor ballast option includes a cast-in-place concrete ring along the perimeter of the mid-height seam (Figure 9). Cast-in-place concrete shall be a minimum 3,000 psi (20.7 MPa) compressive strength at 28 days and minimum 6% air entrainment. Concrete shall be cast in contact with the exterior surface of the tank to allow interlock with sidewall ribs and the mid-height seam. Reinforcing steel is not required, but may be added if desired. The concrete collar shall be continuous around the entire tank perimeter. Figure 9: Concrete Collar Anchor Ballast Concrete collar anchor ballast installation should be as follows: 1. Backfill the tank to the mid-seam area in accordance with the Infiltrator Tank Installation Instructions. 2. If reinforcing steel is being used, place reinforcing bars in the desired location. 3. Pour concrete in contact with the exterior surface of the tank to create an interlocking connection with tank sidewall ribs and the mid-height flange. 4. Pour concrete such that the bottom of the collar is located at the top of the mid- seam flange of the tank. 5. Pour concrete such that the collar width and height conform with Table 2 minimum dimensional specifications. 6. Allow sufficient curing of the concrete to prevent damage to the concrete collar before completing the tank backfilling process. 7. Backfill in accordance with the Infiltrator Tank Installation Instructions. 5, 85, 8 88 8, 9, 108, 9, 10 Position straps on tank. Connect strap to plate. Remove strap slack. Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. 5 Step 3-5: Custom-Designed Buoyancy Controls Table 2 includes a column listing minimum supplemental downward forces to allow custom-designed buoyancy controls not described in this guidance document. Possible custom-designed anchor ballasts include, but are not limited to, precast and cast-in-place concrete blocks, traffic barriers, concrete-filled half pipe, and a concrete slab. Note that the Table 2 values include a suggested 1.5 factor of safety applied to the calculated minimum downward force required to restrain the tank and assumes the subsurface water level is positioned at the outlet elevation for the tank model. Custom-designed buoyancy control methods must consider the effect of saturated soil conditions on the tank and custom-designed buoyancy control mechanism. As long as buoyancy control is provided that supplies the minimum downward force listed in Table 2, the tank is calculated to be stable for the subsurface water level outside the tank and above the tank bottom and corresponding soil cover conditions. All Infiltrator strapping, fastening, and anchor ballast positioning recommendations and the Infiltrator Tank Installation Instructions apply for custom-designed buoyancy control methods. Since custom-designed buoyancy controls may rely on the weight of the anchor ballast, the weight of soil column over the anchor ballast, a combination of anchor ballast and soil weight, or anchor pullout resistance, anchor placement and installation must account for its functional design. Never place any portion of the anchor ballasts beneath the outermost footprint of the tank, including beneath the tank haunches. Design and installation methods shall be determined by the installer. Contact Infiltrator’s Technical Services Department with any questions regarding supplemental downward force requirements. WARNING: Do Not Use Geogrid-Based Buoyancy Controls Some tank manufacturers endorse the use of buoyancy control systems incorporating geogrid draped across the tank connected to an anchor ballast system or anchored within soil around the tank. Infiltrator has determined that the use of geogrid buoyancy control systems is unacceptable with Infiltrator tanks. Infiltrator advises against the use of geogrid-based tank restraint systems for Infiltrator tanks. The presence of the geogrid across the tank top and sides prevents the proper placement and compaction of soil between the tank-body corrugations and beneath the tank haunches, as required per the Infiltrator Tank Installation Instructions. Supplemental Technical Guidance Supplemental technical guidance is provided below for use with the five buoyancy control methods described in Step 3. Excavation Requirements The excavation width should provide a minimum of 36 inches (900 mm) clearance beyond the tank on all sides when utilizing buoyancy control. This will allow sufficient space within the excavation to place anchoring equipment and fasten strapping. The excavation should provide a minimum 48-inch (1,200 mm) clearance beyond the tank when using helical- and anchor-lock-type anchors to allow for sufficient space to properly install the anchoring system. The actual excavation size shall be determined by the installer. Refer to Infiltrator Tank Installation Instructions for additional excavation procedures. WARNING: Never place any portion of the anchor ballasts beneath the outermost footprint of the tank, including beneath the haunches. Short And Long-Term Groundwater Control It may be necessary to implement groundwater control measures during tank installation. Maintain dry conditions by expanding the excavation to create a short-term groundwater collection sump for temporary placement of a dewatering pump if needed. Long-term groundwater control measures such as underdrains and interceptor trenches may be sensible if the site is amenable to construction of a control system and such systems are not prohibited by regulation or law, and the tank location is not subject to flooding. Underdrains and groundwater interceptor trenches may prevent the need for tank buoyancy control measures. Ratchet Strap Material Specifications The configuration and capacity of the four-strap Infiltrator Tank Buoyancy Control Strap Assembly (TANK-BCS-KIT) is designed to be compatible with both the beam and precast concrete plate buoyancy control options shown in Table 2. If using a beam anchor ballast, all four straps are required to complete the installation. If using a precast concrete plate anchor ballast, only the 14-ft-long (4.3 m) strap with hooked end and ratchet strap with hooked end are required, with connection directly to the precast concrete plate hardware, thereby eliminating the need for the 5-ft-long (1.5 m) looped-end straps. Off-the-shelf, commercially available strap systems can also be used for beam and precast concrete plate buoyancy control options shown in Table 2. For the beam anchor ballasts, a commercially available four-strap system (two hooked-end straps, two looped-end straps) is recommended for connecting the anchor ballasts to the tank. For the precast concrete plate anchor ballast, a commercially available two-strap system (two hooked-end straps) is recommended for connecting the anchor ballasts to the tank. The suggested strap configuration is as follows: • Two 5-ft-long (1.5 m) straps with sewn, looped ends (applies to beam only) • One 14-ft-long (4.3 m) strap with a hooked end • One ratchet strap with hooked end For commercially available strap systems, the recommended method of strap tightening is a ratchet, which is used to remove all slack and slightly pre-load the system. All connections, fittings, and hardware must be corrosion resistant (stainless steel or galvanized) or coated with epoxy or other corrosion-resistant materials to inhibit deterioration in the subsurface environment. If not using stainless steel or galvanized components, apply a corrosion-resistant coating prior to burial. The recommended strap and ratchet specifications for commercially available strap system components are as follows: • Strap width: 2 in (5 cm) • Strap material: Polyester • Strap minimum working load limit: 3,300 lbs (1,500 kg) • Strap assembly break strength: 10,000 lbs (4,538 kg) • Strap hooks: Stainless steel • Strap tightening mechanism: Stainless steel ratchet • Ratchet working capacity: 10,000 lbs (4,538 kg) Strap materials and capacity are the same for helical anchors and anchor-lock assemblies. The strap length and connection configuration and hardware may differ depending upon the type of anchor ballast system being used. 6 Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. WARNING: Do Not Use Cable Tie-Downs: The use of cables to connect anchor ballasts in lieu of strapping is prohibited. Cables concentrate the load exerted by the buoyancy control system within a small area on the tank surface, resulting in the potential to damage to the tank. Ratchet Strap Placement Proper installation of straps over the tank is critical for tank stability under changing conditions both inside and outside the tank. Straps must be placed at the specified strapping locations for each tank model, as illustrated in Figure 10. Strapping locations are embossed on the exterior surface of the tank. Strapping locations correspond to structurally reinforced areas of the tank body. Straps must never be placed over access openings, lids, or inlet/outlet piping. The ratchet must be positioned below the tank midseam so it is not in contact with the tank body. Straps must be tightened with a ratchet to remove slack and slightly pre-load the system, without displacing the connected anchor ballasts or damaging the tank. Strapping Notes: 1. Beam anchor ballasts shall be centered across the straps. Concrete plate and helical anchor and anchor-lock ballasts shall be aligned with the strap installation location embossed on the tank exterior. 2. Beam anchor ballasts shall extend a minimum of 6 inches (150 mm) beyond the maximum strap width. 3. When applicable in Table 2, the minimum beam anchor ballast length corresponds to the tank model-specific strap width plus 12 inches (300 mm), allowing for a minimum of 6 inches to beam length beyond the strap. Figure 10: Strap Positioning WARNING: Do Not Use Cable Tie-Downs: The use of cables to connect anchor ballasts in lieu of strapping is prohibited. Cables concentrate the load exerted by the buoyancy control system within a small area on the tank surface, resulting in the potential to damage to the tank. Backfilling A critical aspect of tank installation is proper backfilling. At a minimum, compacted soil must be present: 1) between the tank-body corrugations; 2) beneath the tank haunches; and 3) around and above the anchor ballasts (Figure 11). Backfill shall consist of compacted, suitable soil placed in lifts no greater than 12 inches (300 mm), as described in the Infiltrator Tank Installation Instructions. Figure 11: Backfill Placement WARNING: Use of Tank Installation Instructions: This guidance document provides general statements on backfilling and tank installation only. Refer to the Infiltrator Tank Installation Instructions for complete tank installation requirements. Note: Infiltrator tanks do not require filling with water prior to backfill placement. Water filling and backfilling to the tank mid-height is required if the tank is left in either an open or backfilled excavation that may fill with water from precipitation or other sources. Parts and Supplies The parts and supplies necessary are to be purchased separately from the tank. All parts and supplies are either commercially available or available through Infiltrator’s network of tank distributors. Some parts may require fabrication on site using common construction practices. General Information • Refer to the Infiltrator Tank Installation Instructions for complete information on tank installation requirements. Failure to comply with installation instructions will void the warranty. • Prior to ground disturbance, check for subsurface obstructions and utilities in conformance with applicable regulatory requirements. • Excavation safety provisions shall conform to applicable government regulations. • Follow manufacturer instructions for all products and devices used for Infiltrator tank buoyancy control. • Buoyancy control methods described herein do not account for unanticipated conditions such as surface flooding, temporary inundation or other natural occurrences, unintended removal of cover fill over tank, etc. • Buoyancy control methods described herein are recommendations only; consult a professional engineer for customized designs, if desired. Tank Model Strap Spacing (Dimension “X”) IM-300 32 in (813 mm) IM-540 33 in (838 mm) IM-1060 33 in (838 mm) CM-1060 45 in (1,143 mm) IM-1250 63 in (1,600 mm) IM-1530 63 in (1,600 mm) IM-1530 63 in (1,600 mm) X X Contact Infiltrator Water Technologies at (800) 221-4436 or info@infiltratorwater.com for additional information. 7 TANK03 0723 Infiltrator Water Technologies, LLC (“Infiltrator”) INFILTRATOR® SEPTIC TANK LIMITED WARRANTY FIVE (5) YEAR MATERIALS AND WORKMANSHIP LIMITED WARRANTY (a) This limited warranty is extended to the end user of an Infiltrator Tank. A Tank manufactured by Infiltrator, when installed and operated in accordance with Infiltrator’s installation instructions and local regulation by a person or company that is properly qualified to install the Infiltrator tank in accordance with applicable state and/or local requirements, is warranted to you: (i) against defective materials and workmanship for five (5) years after installation. Infiltrator will, at its option, (i) repair the defective product or (ii) replace the defective materials. Infiltrator’s liability specifically excludes the cost of removal and/or installation of the Tank. (b) In order to exercise its warranty rights, you must notify Infiltrator in writing at its corporate headquarters in Old Saybrook, Connecticut within fifteen (15) days of the alleged defect. (c) YOUR EXCLUSIVE REMEDY WITH RESPECT TO ANY AND ALL LOSSES OR DAMAGES RESULTING FROM ANY CAUSE WHATSOEVER SHALL BE SPECIFIED IN SUBPARAGRAPH (a) ABOVE. INFILTRATOR SHALL IN NO EVENT BE LIABLE FOR ANY CONSEQUENTIAL OR INCIDENTAL DAMAGES OF ANY KIND, HOWEVER OCCASIONED, WHETHER BY NEGLIGENCE OR OTHERWISE. SOME STATES DO NOT ALLOW THE EXCLUSION OR LIMITATION OF INCIDENTAL OR CONSEQUENTIAL DAMAGES, SO THIS LIMITA TION OR EXCLUSION MAY NOT APPLY TO YOU. THIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS AND YOU MAY ALSO HAVE OTHER RIGHTS WHICH VARY FROM STATE TO STATE. (d) THIS LIMITED WARRANTY IS THE EXCLUSIVE WARRANTY GIVEN BY INFILTRATOR AND SUPERSEDES ANY PRIOR, CONTRARY, ADDITIONAL, OR SUBSEQUENT REPRESENTATIONS, WHETHER ORAL OR WRITTEN. INFILTRATOR DISCLAIMS AND EXCLUDES TO THE GREATEST EXTENT ALLOWED BY LAW ALL OTHER WARRANTIES, WHETHER EXPRESS OR IMPLIED, OR STATUTORY, INCLUDING ANY WARRANTY OF MERCHANTABILITY, FINESSE FOR A PARTICULAR PURPOSE AND ANY IMPLIED WARRANTIES OTHERWISE ARISING FROM COURSE OF DEALING, COURSE OF PERFORMANCE, OR USAGE OF TRADE. NO PERSON (INCLUDING ANY EMPLOYEE, AGENT, DEALER, OR REPRESENTATIVE) IS AUTHORIZED TO MAKE ANY REPRESENTATION OR WARRANTY CONCERNING THIS PRODUCT, EXCEPT TO REFER YOU TO THIS LIMITED WARRANTY. EXCEPT AS EXPRESSLY SET FORTH HEREIN, THIS WARRANTY IS NOT A WARRANTY OF FUTURE PERFORMANCE, BUT ONLY A WARRANTY TO REPAIR OR REPLACE. (e) YOU MAY ASSIGN THIS LIMITED WARRANTY TO A SUBSEQUENT PURCHASER OF YOUR HOME. (f) NO REPRESENTATIVE OF INFILTRATOR HAS THE AUTHORITY TO CHANGE THIS LIMITED WARRANTY IN ANY MANNER WHATSOEVER, OR TO EXTEND THIS LIMITED WARRANTY. (g) NO WARRANTY OF ANY KIND IS MADE WITH REGARD TO ANY PRODUCT, COMPONENTS, DEVICES, MEDIA OR TREATMENT UNITS WHICH ARE MANUFACTURED BY OTHERS AND ARE INSTALLED IN AN INFILTRATOR TANK. USE OF THESE PRODUCTS ARE AT YOUR OWN RISK. (h) THE INFILTRATOR TANK IS DESIGNED TO BE BURIED UNDERGROUND. NO WARRANTY OF ANY KIND IS MADE IF YOUR TANK IS NOT BURIED UNDERGROUND AS SPECIFIED IN THE PRODUCT’S INSTALLATION INSTRUCTIONS. CONDITIONS AND EXCLUSIONS There are certain conditions or applications over which Infiltrator has no control. Defects or problems as a result of such conditions or applications are not the responsibility of Infiltrator and are NOT covered under this warranty. They include failure to install the Tank in accordance with instructions or applicable regulatory requirements or guidance, altering the Tank contrary to the installation instructions and disposing of chemicals or other materials contrary to normal tank usage. The above represents the Standard Limited Warranty offered by Infiltrator. A limited number of regulatory jurisdictions have different warranty requirements. Any purchaser of a Tank should contact Infiltrator’s corporate headquarters in Old Saybrook, Connecticut, prior to such purchase to obtain a copy of the applicable warranty, and should carefully read that warranty prior to the purchase of a Tank. Contact Infiltrator’s Technical Services Department for assistance at 1-800-221-4436 or info@infiltratorwater.com 10/7/2025 To Whom It May Concern: We have been to the following site: 116 Crystal River Rd, Carbondale, Garfield County We have verified that the system was started properly. The System went through several cycles with no issues. - Amperage and voltage of control panel, floats, and pump are all within manufacturers specifications and tolerance at start up. - Floats verified for functionality. - The high-level alarm functions upon activation at control panel. If you have any questions, please do not hesitate to call me at 719-395-6764, ext. 13. Sincerely, Scott McIntosh Service Manager 832‐R‐13‐002