403 N. 1st Street, Montrose Colorado 81401
bbriggs@bkbassoc.com +1 970.596.1982
B.K. Briggs & Associates, LLC.
403 N. 1st Street
Montrose, CO 81401
P: 970.596.1982
E: bbriggs@bkbassoc.com
November 10, 2025 Sent Via Email: dave.porterhomes@outlook.com
Mr. David Hancock
Porter Homes LLC
419 Brach Dr.
Grand Junction, CO 81507
RE: Footer and Residential Ufer 4410 CR 209 Debeque, CO 81630
Dear Dave,
Inspection of the footers at 4410 CR 209 in Debeque was completed on October 27th,
2025. Exterior footers were constructed/installed as designed at 24” footers with 3#5
rebar with supporting rebar at 12” centers. Interior footers were 18” with 2#5 rebar at 12”
centers (B) and 30” with 4 #5 rebar (C). Vertical bars were approved to wet set for walls
at 32”. Interior pads (C) constructed as designed at 30”x30” with 3 #5 rebar each way.
Exterior column pads were 18”x18” and 30”x30” with 2 and 3 #4 rebar each way.
Residential ufer was installed.
Please see attached pictures.
2 | P a g e
RE: Stem wall 4410 CR 209 Debeque, CO 81630
Inspections of the stem walls on 4410 CR 209 in Debeque were completed on November
3rd, 2025. Walls were constructed as designed with 2 #5 rebar top and bottom with
horizontal supports at 18” centers and 32” vertical supports. Walls were constructed at
36” height and 8” width per design recommendations. Concrete Piers on columns were
constructed with 4 #4 vertical rebar and # 4 ties at 12” centers. Please see attached
pictures.
With this action I have no further recommendation. Should you have any questions or
comments please feel free to contact me at (970) 596-1982
Sincerely,
B.K. Briggs & Associates
Brian K. Briggs, P.E.
Principal