HomeMy WebLinkAboutRescheck ReportCNJ/ REScheck*Web TM
Compliance Certificate
Project Information
Project Title:
Energy Code:
Location:
Construction Type:
Project Type:
Project Sub Type:
Climate Zone:
Project No:
All Electric:
Is Renewable:
Has Battery:
Has Charger:
Has Heat Pump
Construction Site,
318 Midland Ave
Carbondale , CO 81623
Project Notes:
Czechowicz Mechanical
2018 IECC
Carbondale, Colorado
Single Family
Alteration
None
5b (7313 HDD)
1789817
true
true
true
true
true
Owner/Agent:
Joe Czechowicz
318 Midland Ave
Carbondale , CO 81623
970.948.0458
Interior Alteration to existing building only. This Rescheck is for Mechanical only.
Designer/Contractor:
Robert Thorpe
1980 Lazy O Rd
Thorpe Architects
Carbondale , CO 81623
970.394.4406
bob@thorpeforce.com
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 1 of 9
Envelope Assemblies
Prop. Req.
Assembly Gross Area or Cavity Cont. U- U- Prop. Req.
Perimeter R-Value R-Value Factor/ Factor/ UA UA
F-Factor F-Factor
Compliance::.
Slab -on -grade tradeoffs are no longer considered in the UA or performance compliance path in REScheck. Each slab -on -grade
assembly in the specified climate zone must meet the minimum energy code insulation R-value and depth requirements.
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 2 of 9
r�(, Inspection Checklist
Energy Code: 2018 IECC
Requirements: 44% were addressed directly in the RESCheCk software
Text in the "Comments/Assumptions" column is provided by the user in the REScheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception is being
claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Pre-Inspection/Plan Review
Section Plans
i # Verified
& Req.ID Pre-Inspection/Plan Review Value
103.1,
Construction drawings and
103.2,
documentation demonstrate
403.7
energy code compliance for
[PR3]1
lighting and mechanical
Systems. Systems serving
multiple dwelling units must
demonstrate compliance with
the IECC Commercial Provisions.
1 302.1, Heating and [aaling equipment
is ACCA Manual 5
Heating:
Btu/hr
403.7 sized per
i [PR2]2 based on loads calculated per
ACCA Manual 1 or other methods
` approved by the code official.
Cooll ng:
I
Btu.._ 1hr
Additional Comments/Assumptions:
Field
Verified
Value
Heating:
Btu/hr
.i
Cooling:
Btu hr
Complies? Comments/Assumptions
Complies
PDoes Not
omply
Not
servable
Not
pplicable
Complies
Does Not
omply
Not
servable
Not
pplicable
1 I High Impact (Tier 1) 2 Medium Impact (Tier 2) 3 Low Impact (Tier 3)
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 3 of 9
Foundation Inspection
Section
& Req.ID Foundation Inspection Complies?
403.9 Snow- and ice -melting system controls
Complies
[FO12]2 installed.
o Does Not
Umply
Not
servable
PNot
licable
Additional Comments/Assumptions:
Comments/Assumptions
1 1 High Impact (Tier 1) 1 2 1 Medium Impact (Tier 2) 3 1 Low Impact (Tier 3)
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 4 of 9
Framing / Rough -in Inspection
Section Plans Field
# Framing /Rough -In Verified Verified
I & Req.ID Inspection Value Value
Complies? Comments/Assumptions
403.3.1 Supply and return ducts in attics
I insulated >= R-8 where duct is
Complies
[FR12]1
>= 3 inches in diameter and
Does Not
>= R-6 where < 3 inches.
omply
Supply .and return ducts in other
building
Not
portions of the
insulated R-5 for diameter
servable
>=
>= 3 inches and R-4.2 for < 3
Not
inches in diameter.
pplicable
403.3.2 Ducts, air handlers and filter
Q Complies
+
[FR13]1
boxes are sealed with
joints/seams compliant with
Does Not
Jll
International Mechanical Code
omply
or International Residential
Not
Code, as applicable.
servable
Not
Applicable
403.3.5
Building cavities are not used as
Complies
[FR15]3
ducts or plenums.
Does Not
`
omply
a Not
Observable
Not
pplicable
403.3.6(1,
Ducts partially or completely
Complies
2) [FR26]3
buried in ceiling insulation have
Does Not
an insulation R•value not. less
omply
than R-8, the sum cf the ceiling
insulation R-value against and
❑ Not
above the top of the duct, and
Observable
against and below the bottom of
Not
the duct, is >— than R-19,
excluding the R-value of the
pplicable
duct insulation.
403.4
HVAC piping conveying fluids
RR
L
❑ Complies
[FR17]�
above 105 -F or chilled fluids
below 55 °F are insulated to >_R-
!
Does Not
1 3
omply
Not
I
Observable
l
Not
pplicable
403.4.1
Protection of insulation on HVAC
{
❑ Complies
[FR24]1
iplping•
❑ Does Not
Comply
Not
servable
Not
pplicable
403.5.3
Hot water pipes are insulated to
R f1 R f�
Complies
[FR18]2
>_R-3.
Q Does Not
Comply
o Not
Observable
PANot
pplicable
Additional Comments/Assumptions:
1 1 High Impact (Tier 1) 1 2 1 Medium Impact (Tier 2) 1 3 1 Low Impact (Tier 3)
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 5 of 9
Insulation inspection
Section #
& Req.ID Insulation Inspection
Additional Comments/Assumptions:
Complies? Comments/Assumptions
1 Hiah Impact (Tier 1) 2 I Medium Impact
13 I Low Impact (Tier 3)
Report Title: Czechowi¢ Mechanical Report Date: 11/13/25, 1:19 PM 6 of 9
Final Inspection Provisions
Section
& Rea.ID
[FI10]z
403.5.1
[FI11]z
Plans
Verified
Final Inspection Provisions Value
Heat pump thermostat installed
on heat pumps.
Circulating service hot water
systems have automatic or
accessible manual controls.
403.6.1 All mechanical ventilation
[FI25]2 system fans not part of tested
and listed HVAC equipment
meet efficacand air flow limits
per Table R463.6.1.
403.2
Hot water boilers supplying heat
[FI26]2
through one- I twa-pipe
heating systems have outdoor
setback control to lower boiler
water temperature based on
outdoor temperature.
I
403.5.1.1
Heated water circulation
[FI28]2
systems have a circulation
pump. The system return pipe is
a dedicated return pipe or a
cold water supply pipe. Gravfty
and thermos -syphon circulation
systems are not present.
Controls for circulating hot
water system pumps start the
within the occupancy
demand
Controls automatically turn off
the pump when water Is in
circulation loop is at set -point
temperature and no demand for
hot water exists.
1 403.5.1.2
Electric heat trace syYstems
1 11L
[FI29]2
comply with IEEE 515 or
515. Controls automatically
adjust the energy input to the
heat tracing to maintain the
desired water temperature in
the piping.
I
i
403.5.2
Demand recirculation water
[FI30]2
controls
manage operation of the pump
and limit the temperature of the
water entering the cold water
piping to <= 104°F.
403.5.4 Drain water heat recovery units
[FI31]2 tested in accordance with CSA
B55.1. Potable water -side
pressure loss of drain water
heat recovery units < 3 psi for
individual units connected to
one or two showers. Potable
water -side pressure loss of drain
water heat recovery units < 2
psi for individual units
connected to three or more
showers.
Field
Verified
Value
Complies?
Q Complies
PoDoesNot
omply
Not
servable
PNot
plicable
Complies
Does Not
omply
Not
servable
Not
pplicable
Complies
Does Not
Does
Not
servable
Not
pplicable
Complies
Does Not
omply
Not
servable
Not
pplicable
0 Complies
RDoes Not
omply
9 Not
servable
PNot
plicable
Complies
RDoes Not
omply
Not
servable
Not
pplicable
Complies
Does Not
omply
Not
servable
Not
Applicable
0 Complies
Q Does Not
Comply
Not
servable
Not
pplicable
Comments/Assumptions
Exception: Requirement
is not applicable.
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 7 of 9
Section
4t
& Req.ln
Plans
Verified
Final Inspection Provisions Value
Field
Verified
value Complies? CornmentslAssumptions
404.1
90% or more of permanent
Complies
[FI611
fixtures have high efficacy
Does Not
lamps.
ompfy
'
Q Not
servable
I�
1� Not
pplicable
404.1.1 Fuel gas lighting systems have Complies
[FI2313 no continuous pilot light. [�J Does Not
Comply
PINot
servable
[� Not
l pplicable
303.3 Manufacturer manuals for Complies
[FI1813 mechanical and water heating Does Not
systems have been provided.
ompfy
Not
servable
0ppNot
{ licable
403.3.3 Ducts are pressure tested to Complies
[FI2711 determine air leakage with
either: Rough -in test: Total cfm/100 ft2 cfm/100 ft2 Does Not
leakage measured with a omply
pressure differential of 0.1 inch Not
[�
w.g. across the system including servable
the manufacturer's air handler Not
enclosure if installed at time of
test. Postconstruction test: Total pplicable
leakage measured with a
pressure differential of 0.1 Inch
w.g. across the entire system
Including the manufacturer's air
handler enclosure.
403.3.4 Duct tightness test result of n Complies
[FI411 r=4 cfmi100 ft2 across the
system or <=3 cfm/100 ft2 cfm/100 ft2 Does Not
cfm/100 ft2
without air handler @ 25 Pa. For omply
rough -in tests. verification may Not
need to occur during Framing servable
Inspection. Not
pplicable
403.3.2.1 Air handler leakage designated i Q Complies
[FI2411 by manufacturer at <=2 h of
design air flow. Does Not
omply
Not
servable
PpNot
plicable
403.1,1 Programmable thermostats 0 Complies
[Flglr installed for control of primary
heating and cooling systems Does Not
and initially set b manufacturer ompfy
to code specditatYons. Not
servable
Not
pplicable
Additional Comments/Assumptions:
1 1 High Impact (Tier 1) 1 2 1 Medium Impact (Tier 2) 3 I Low Impact (Tier 3)
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 8 of 9
2018 IECC Energy
Efficiency
Certificate
Above -Grade Wall
Below -Grade Wall
Floor
Ceiling / Roof
Ductwork (unconditioned spaces):
Window
Door
Skylight
Heating System:
Cooling System:
Water Heater:
Name:
Comments:
0.00
0.00
0.00
Date:
0.00
0.00
0.00
0.00
Report Title: Czechowicz Mechanical Report Date: 11/13/25, 1:19 PM 9 of 9