HomeMy WebLinkAboutSubsoils Report for Foundation DesignKumar & Associates, Inc. '( Geatechnical and Materials Engineers 5020 County Road 154 and Environmental Scientists Glenwood Springs, CO 81601 phone: (970) 945-7988 fax: (970) 945-8454 email: kaglenwoodpkumarusa.com An Employ®® Owned Company a ww.kumarusa.com Office Locations: Denver (HQ), Parker, Colorado Springs, Fort Collins, Glenwood Springs, and Summit County, Colorado SUBSOIL STUDY FOR FOUNDATION DESIGN PROPOSED RESIDENCE LOT H 25, FILING 7, ASPEN GLEN 345 SADDLEBACK ROAD GARFIELD COUNTY, COLORADO PROJECT NO.24-7-576 OCTOBER 11, 2024 PREPARED FOR: TAMI YORK 1441 WAZEE STREET, APARTMENT 401 DENVER, COLORADO 80202 tonlI.y4)l'kic ;hofmai1xoin TABLE OF CONTENTS PURPOSEAND SCOPE OF STUDY........................................................................................ I PROPOSED CONSTRUCTION .......................... ..... ..........•. I - SITECONDITIONS .............................................. ...................................................................... I - SUBSIDENCEPOTENTIAL................................................................... ............................... I - FIELDEXPLORATION ......................................................................................................... 2- SUBSURFACECONDITIONS.................................................................................................. 2- FOUNDATION BEARING CONDITIONS............................................................................... 3- DESIGN RECOMMENDATIONS ................................................. ...... .......... 3 - FOUNDATIONS.................................................................................................................- 3 - FOUNDATION AND RETAINING WALLS........................................................................ 4- FLOORSLABS....................................................................................................................... 4 - UNDERDRAINSYSTEM.....................................................................................................- 5 - SURFACEDRAINAGE......................................................................................................... - 5- LIMITATIONS...........................................................................................................................- 6- FIGURE I - LOCATION OF EXPLORATORY BORINGS FIGURE 2 - LOGS OF EXPLORATORY BORINGS FIGURE 3 - LEGEND AND NOTES FIGURE 4 - SWELL -CONSOLIDATION TEST RESULTS TABLE I- SUMMARY OF LABORATORY TEST RESULTS Kumar & Associates, Inc. ® Project No. 24-7-576 PURPOSE AND SCOPE OF STUDY This report presents the results of a subsoil study for a proposed residence to be located on Lot H25, Filing 7, Aspen Glen, 345 Saddleback Road, Garfield County, Colorado. The project site is shown on Figure 1. The purpose of the study was to develop recommendations for the foundation design. The study was conducted in accordance with our agreement for geotechnical engineering services to Tami York dated October 2, 2024. A field exploration program consisting of exploratory borings was conducted to obtain information on the subsurface conditions. Samples of the subsoils obtained during the field exploration were tested in the laboratory to determine their classification, compressibility or swell and other engineering characteristics. The results of the field exploration and laboratory testing were analyzed to develop recommendations for foundation types, depths and allowable pressures for the proposed building foundation. This report summarizes the data obtained during this study and presents our conclusions, design recommendations and other geotechnical engineering considerations based on the proposed construction and the subsurface conditions encountered. PROPOSED CONSTRUCTION Plans for the propsoed residence were conceptual at the time of our field exploration. The proposed residence is assumed to be a two story structure with attached garage. Ground floors could be structural over crawlspace or slab -on -grade. Grading for the structure is assumed to be relatively minor with cut depths between about 2 to 6 feet. We assume relatively light foundation loadings, typical of the proposed type of construction. If building loadings, location or grading plans change significantly from those described above, we should be notified to re-evaluate the recommendations contained in this report. SITE CONDITIONS The subject site was vacant at the time of our field exploration. The ground surface was relatively level with a gentle slope down to the north at a grade estimated at 2 percent. A pond borders the lot to the north. Vegetation consists of grass and weeds. SUBSIDENCE POTENTIAL Bedrock of the Pennsylvanian age Eagle Valley Evaporite underlies the Aspen Glen Subdivision. These rocks are a sequence of gypsiferous shale, fine-grained sandstone and siltstone with some massive beds of gypsum and limestone. There is a possibility that massive gypsum deposits associated with the Eagle Valley Evaporite underlie portions of the lot. Dissolution of the gypsum under certain conditions can cause sinkholes to develop and can produce areas of localized subsidence. During previous work in the area, several sinkholes were observed scattered throughout the Aspen Glen Subdivision. These sinkholes appear similar to others associated with the Eagle Valley Evaporite in areas of the Eagle Valley. Kumar & Associates, Inc. 0 Project No. 24-7-576 -2- Sinkholes were not observed in the immediate area of the subject lot. No evidence of cavities was encountered in the subsurface materials; however, the exploratory borings were relatively shallow, for foundation design only. Based on our present knowledge of the subsurface conditions at the site, it cannot be said for certain that sinkholes will not develop. The risk of future ground subsidence on Lot H25 throughout the service life of the proposed residence, in our opinion, is low; however, the owner should be made aware of the potential for sinkhole development. If further investigation of possible cavities in the bedrock below the site is desired, we should be contacted. FIELD EXPLORATION The field exploration for the project was conducted on October 8, 2024. Two exploratory borings were drilled at the locations shown on Figure 1 to evaluate the subsurface conditions. The borings were advanced with 4-inch diameter continuous flight augers powered by a truck - mounted CNM-45B drill rig. The borings were logged by a representative of Kumar & Associates, Inc. Samples of the subsoils were taken with I %-inch and 2-inch I.D. spoon samplers. The samplers were driven into the subsoils at various depths with blows from a 140-pound hammer falling 30 inches. This testis similar to the standard penetration test described by ASTM Method D-1586. The penetration resistance values are an indication of the relative density or consistency of the subsoils. Depths at which the samples were taken and the penetration resistance values are shown on the Logs of Exploratory Borings, Figure 2. The samples were returned to our laboratory for review by the project engineer and testing. SUBSURFACE CONDITIONS Graphic logs of the subsurface conditions encountered at the site are shown on Figure 2. The subsoils encountered below about '/z foot of topsoil consist of stiff to very stiff, sandy silty clay between 3% and 6 feet deep overlying dense, silty sandy gravel and cobbles with possible boulders to the maximum drilled depth of 8 feet. Drilling in the coarse granular soils with auger equipment was difficult due to the cobbles and boulders and drilling refusal was encountered in the deposit. Laboratory testing performed on samples obtained from the borings included natural moisture content and density and gradation analyses. Results of swell -consolidation testing performed on a relatively undisturbed drive sample, presented on Figure 4, indicate low to moderate compressibility under conditions of loading and wetting. Results of percent finer than sand size gradation analyses performed on a small diameter drive sample (minus 1 %-inch fraction) of the sandy silty clay subsoils show that the silt and clay content is 89 percent. The laboratory testing is summarized in Table 1. No free water was encountered in the borings at the time of drilling and the subsoils were slightly moist. Kumar & Associates, Inc. 0 Project No. 24-7-576 -3- FOUNDATION BEARING CONDITIONS The upper silty clay soils encountered in the borings possess low bearing capacity and low to moderate settlement potential especially when wetted. The underlying gravel soils possess moderate bearing capacity and typically low settlement potential. Spread footings placed on the upper silty clay soils will have a risk of long-term foundation settlement especially if the bearing soils become wetted. We recommend the proposed residence be founded with spread footings bearing on the underlying dense gravel soils. If the risk of settlement is understood and accepted by the owner the residence can be founded on the upper silt soils with a reduced bearing capacity. Provided below are recommendations for spread footings bearing on the underlying gravel soils. If recommendations for bearing on the upper silt soils are desired, we should be contacted to provide them. DESIGN RECOMMENDATIONS FOUNDATIONS Considering the subsurface conditions encountered in the exploratory borings and the nature of the proposed construction, we recommend the building be founded with spread footings bearing on the natural granular soils below the upper silt soils. The design and construction criteria presented below should be observed for a spread footing foundation system. 1) Footings placed entirely on the undisturbed natural gravel soils below the upper silty clay soils should be designed for an allowable bearing pressure of 2,500 psf. Based on experience, we expect settlement of footings designed and constructed as discussed in this section will be about 1 inch or less. 2) The footings should have a minimum width of 16 inches for continuous walls and 2 feet for isolated pads. 3) Exterior footings and footings beneath unheated areas should be provided with adequate soil cover above their bearing elevation for frost protection. Placement of foundations at least 36 inches below exterior grade is typically used in this area. 4) Continuous foundation walls should be reinforced top and bottom to span local anomalies such as by assuming an unsupported length of at least 12 feet. Foundation walls acting as retaining structures should also be designed to resist lateral earth pressures as discussed in the "Foundation and Retaining Walls" section of this report. 5) Topsoil, the upper silty clay soils and any loose disturbed soils should be removed and the footing bearing level extended down to the relatively dense natural granular soils. The exposed soils in footing area should then be moistened and compacted. If water seepage is encountered, the footing areas should be dewatered before concrete placement. 6) A representative of the geotechnical engineer should observe all footing excavations prior to concrete placement to evaluate bearing conditions. Kumar & Associates, Inc. 0 Project No. 24-7-576 -4- FOUNDATION AND RETAINING WALLS Foundation walls and retaining structures which are laterally supported and can be expected to undergo only a slight amount of deflection should be designed for a lateral earth pressure computed on the basis of an equivalent fluid unit weight of at least 55 pcf for backfill consisting of the on -site soils. Cantilevered retaining structures which are separate from the residence and can be expected to deflect sufficiently to mobilize the full active earth pressure condition should be designed for a lateral earth pressure computed on the basis of an equivalent fluid unit weight of at least 45 pcf for backfill consisting of the on -site soils. All foundation and retaining structures should be designed for appropriate hydrostatic and surcharge pressures such as adjacent footings, traffic, construction materials and equipment. The pressures recommended above assume drained conditions behind the walls and a horizontal backfill surface. The buildup of water behind a wall or an upward sloping backfill surface will increase the lateral pressure imposed on a foundation wall or retaining structure. An underdrain should be provided to prevent hydrostatic pressure buildup behind walls. Backfill should be placed in uniform lifts and compacted to at least 90% of the maximum standard Proctor density at a moisture content near optimum. Backfill placed in pavement and walkway areas should be compacted to at least 95% of the maximum standard Proctor density. Care should be taken not to overcompact the backfill or use large equipment near the wall, since this could cause excessive lateral pressure on the wall. Some settlement of deep foundation wall backfill should be expected, even if the material is placed correctly, and could result in distress to facilities constructed on the backfill. Backfill should not contain organics, debris or rock larger than about 6 inches. The lateral resistance of foundation or retaining wall footings will be a combination of the sliding resistance of the footing on the foundation materials and passive earth pressure against the side of the footing. Resistance to sliding at the bottoms of the footings can be calculated based on a coefficient of friction of 0.45. Passive pressure of compacted backfill against the sides of the footings can be calculated using an equivalent fluid unit weight of 375 pcf. The coefficient of friction and passive pressure values recommended above assume ultimate soil strength. Suitable factors of safety should be included in the design to limit the strain which will occur at the ultimate strength, particularly in the case of passive resistance. Fill placed against the sides of the footings to resist lateral loads should be compacted to at least 95% of the maximum standard Proctor density at a moisture content near optimum. FLOOR SLABS The natural on -site soils, exclusive of topsoil, are suitable to support lightly loaded slab -on -grade construction. To reduce the effects of some differential movement, floor slabs should be separated from all bearing walls and columns with expansion joints which allow unrestrained vertical movement. Floor slab control joints should be used to reduce damage due to shrinkage cracking. The requirements for joint spacing and slab reinforcement should be established by Kumar & Associates, Inc. 0 Project No. 24-7-576 -5- the designer based on experience and the intended slab use. A minimum 4-inch layer of free - draining gravel should be placed beneath slabs at grade to facilitate drainage. This material should consist of minus 2-inch aggregate with at least 50% retained on the No. 4 sieve and less than 2% passing the No. 200 sieve. All fill materials for support of floor slabs should be compacted to at least 95% of maximum standard Proctor density at a moisture content near optimum. Required fill can consist of the on -site granular soils devoid of vegetation, topsoil and oversized rock. UNDERDRAIN SYSTEM Although free water was not encountered during our exploration, it has been our experience in the area that local perched groundwater can develop during times of heavy precipitation or seasonal runoff. Frozen ground during spring runoff can create a perched condition. We recommend below -grade construction, such as retaining walls, crawlspace and basement areas, if any, be protected from wetting and hydrostatic pressure buildup by an underdrain system. The drains should consist of rigid perforated PVC drainpipe placed in the bottom of the wall backfill surrounded above the invert level with free -draining granular material. The drain should be placed at each level of excavation and at least 1 foot below lowest adjacent finish grade and sloped at a minimum 1/2% to a suitable gravity outlet. Free -draining granular material used in the underdrain system should contain less than 2% passing the No. 200 sieve, less than 50% passing the No. 4 sieve and have a maximum size of 2 inches. The drain gravel backfill should be at least I1/2 feet deep. SURFACE DRAINAGE The following drainage precautions should be observed during construction and maintained at all times after the residence has been completed: 1) Inundation of the foundation excavations and underslab areas should be avoided during construction. 2) Exterior backfill should be adjusted to near optimum moisture and compacted to at least 95% of the maximum standard Proctor density in pavement and slab areas and to at least 90% of the maximum standard Proctor density in landscape areas. 3) The ground surface surrounding the exterior of the building should be sloped to drain away from the foundation in all directions. We recommend a minimum slope of 6 inches in the first 10 feet in unpaved areas and a minimum slope of 3 inches in the first 10 feet in paved areas. Free -draining wall backfill should be covered with filter fabric and capped with about 2 feet of the on -site finer graded soils to reduce surface water infiltration. 4) Roof downspouts and drains should discharge well beyond the limits of all backfill. 5) Landscaping which requires regular heavy irrigation should be located at least 5 feet from foundation walls. Consideration should be given to use of xeriscape to reduce the potential for wetting of soils below the building caused by irrigation. Kumar & Associates, Inc. 0 Project No. 24-7-576 LIMITATIONS This study has been conducted in accordance with generally accepted geotechnical engineering principles and practices in this area at this time. We make no warranty either express or implied. The conclusions and recommendations submitted in this report are based upon the data obtained from the exploratory borings drilled at the locations indicated on Figure 1, the proposed type of construction and our experience in the area. Our services do not include determining the presence, prevention or possibility of mold or other biological contaminants (MOBC) developing in the future. If the client is concerned about MOBC, then a professional in this special field of practice should be consulted. Our findings include interpolation and extrapolation of the subsurface conditions identified at the exploratory borings and variations in the subsurface conditions may not become evident until excavation is performed. If conditions encountered during construction appear different from those described in this report, we should be notified so that re-evaluation of the recommendations may be made. This report has been prepared for the exclusive use by our client for design purposes. We are not responsible for technical interpretations by others of our information. As the project evolves, we should provide continued consultation and field services during construction to review and monitor the implementation of our recommendations, and to verify that the recommendations have been appropriately interpreted. Significant design changes may require additional analysis or modifications to the recommendations presented herein. We recommend on -site observation of excavations and foundation bearing strata and testing of structural fill by a representative of the geotechnical engineer Respectfully Submitted, Kumar & Associates, Daniel E. Hardin, P.E. JHP/kac Kumar & Associates, Inc. 0 Project No. 24-7.576 352 25 0 25 50 APPROXIMATE SCALE -FEET G z' 24-7-576 Kumar & Associates LOCATION OF EXPLORATORY BORINGS Fig. 1 BORING 1 BORING 2 0 0 — 17/12 16/12 w LaWC=7.5 LaDD=91 19/12 — iw j = 5 •' y`; 30/1 WC=9.8 —200=89 5 = 0~ W o J 10 10— F Y 9 C o� MM Yl n W � 1 � Vy� NH 24-7-576 Kumar & Associates LOGS OF EXPLORATORY BORINGS Fig. 2 .1 LEGEND ® TOPSOIL; CLAY, SANDY, FIRM, SLIGHTLY MOIST, BROWN. CLAY (CL); SANDY, STIFF TO VERY STIFF, SLIGHTLY MOIST, BROWN. GRAVEL AND COBBLES (GM); SILTY, SANDY, DENSE, SLIGHTLY MOIST, BROWN AND GRAY. DRIVE SAMPLE, 2—INCH I.D. CALIFORNIA LINER SAMPLE. I DRIVE SAMPLE, 1 3/8—INCH I.D. SPLIT SPOON STANDARD PENETRATION TEST. 1 17/12 DRIVE SAMPLE BLOW COUNT. INDICATES THAT 17 BLOWS OF A 140—POUND HAMMER FALLING 30 INCHES WERE REQUIRED TO DRIVE THE SAMPLER 12 INCHES. PRACTICAL AUGER REFUSAL WHERE SHOWN ABOVE BOTTOM OF BORING, INDICATES THAT I MULTIPLE ATTEMPTS WHERE MADE TO ADVANCE THE HOLE. NOTES 1. THE EXPLORATORY BORINGS WERE DRILLED ON OCTOBER 8, 2024 WITH A 4—INCH—DIAMETER CONTINUOUS —FLIGHT POWER AUGER. 2. THE LOCATIONS OF THE EXPLORATORY BORINGS WERE MEASURED APPROXIMATELY BY PACING FROM FEATURES SHOWN ON THE SITE PLAN PROVIDED. 3. THE ELEVATIONS OF THE EXPLORATORY BORINGS WERE NOT MEASURED AND THE LOGS OF THE EXPLORATORY BORINGS ARE PLOTTED TO DEPTH. 4. THE EXPLORATORY BORING LOCATIONS SHOULD BE CONSIDERED ACCURATE ONLY TO THE DEGREE IMPLIED BY THE METHOD USED. 5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY BORING LOGS REPRESENT THE APPROXIMATE BOUNDARIES BETWEEN MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL. 6. GROUNDWATER WAS NOT ENCOUNTERED IN THE BORINGS AT THE TIME OF DRILLING. 7. LABORATORY TEST RESULTS: WC = WATER CONTENT (%) (ASTM D2216); DD = DRY DENSITY (pcf) (ASTM D2216); —200= PERCENTAGE PASSING NO. 200 SIEVE (ASTM D1140). 24-7-576 1 Kumar & Associates I LEGEND AND NOTES I Fig. 3 2 0 v J —2 w 3 1n 1 —4 z 0 a —6 J O V) z O U -8 am SAMPLE OF: Sandy Clay FROM: Boring 1 @ 2' WC = 7.5 %, DD = 91 pcf ADDITIONAL COMPRESSION 1 r UNDER CONSTANT PRESSURE I DUE TO WETTING - -- - - — i •I I — i— i— --i � - I —I �- I i I 1 1 � I fll I• I i; � 1 I I I Ilfll I � �I I hd 'A WOW. ad� "I M roL t amen eppm d of Kw r mid Aumcwto, 1 o 5.a cw�.�dcuon unnno�.nc,m.d n occa.dleK. .dh u-as�e. 1.0 APPUED PRESSURE — KSF 10 100 24-7-576 1 Kumar & Associates SWELL —CONSOLIDATION TEST RESULTS Fig. 4 IL U) J U) LJJ N LJJ I- O -i J in Q J L L- O a C� G U) w a U U Cd cn 0 w zw�x- Z Z 0aw Z 0 w D U U H � Q O Z � J � CR � rL F J CY J I-Z>W W CAW U Z u� y O d Q N d 0 a Q 0 Q' J 9' 0 J F y 7 U ~ O W Q 0 Z W H : CEO [� ao0 Z C U x U O w J a w -- N 0