HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-06-25-9328
VANTAGE AVIATION FUEL FARM
GARFIELD COUNTY AIRPORT
375 COUNTY ROAD 352
1) AS A FUEL FARM IS NOT ATYPICAL PERMIT SUBMITTAL AND HAS LIFE SAFETY
CONCERNS NOT ALWAYS ADDRESSED IN THE LOCAL ADOPTED CODES, THE
ENGINEER OF RECORD IS TO APPROVE ALL THE LIFE SAFETY ASPECTS OF THE
FUEL FARM. PLEASE PROVIDE A LETTER OF ACCEPTANCE PRIOR TO THE FINAL
INSPECTION.
2) COMPLIANCE WITH IFC CHAPTER 20 AND NFPA 407 IS REQUIRED.
3) THE COUNTY BUILDING DEPARTMENT WILL BE CONDUCTING REBAR
INSPECTIONS AND FINAL INSPECTIONS WHEN THE PROJECT IS COMPLETED. A
SIGN -OFF FROM THE LOCAL FIRE DISTRICT IS REQUIRED PRIOR TO THE COUNTY'S
FINAL INSPECTION. THIS MAY REQUIRE SPECIAL INSPECTIONS BASED ON THE FIRE
PROTECTION ENGINEER'S REPORT, AS THERE ARE PARAMETERS FOR PIPE TESTING
IN NFPA 407.
4) THE APPROVED PLANS ARE TO BE ON -SITE FOR INSPECTIONS.
5) SANITARY FACILITIES ARE REQUIRED TO BE PROVIDED FOR WORKERS.
6) A LIST OF REQUIRED INSPECTIONS WILL BE ATTACHED TO THE PLANS. THE STATE
IS TO PERMIT AND APPROVE THE ELECTRICAL WORK.
HTTPS://WWW.COLORADO.GOWPACIFIC/DORA/DPO ELECTRICAL PLUMBING PE
RMITS
7) UNDERGROUND UTILITY LOCATES IS THE RESPONSIBILITY OF THE OWNER OR
CONTRACTOR. 811 IS THE COLORADO UTILITY LOCATE HOT LINE.
8) ELECTRICAL CODE COMPLIANCE WILL BE DETERMINED BASED ON FIELD
INSPECTIONS PERFORMED BY THE STATE ELECTRICAL INSPECTOR, (303) 869-3458.
PLEASE HAVE THE INSPECTOR SIGN THE BUILDING CARD OR PROVIDE WRITTEN
DOCUMENTATION OF THE INSPECTIONS.
9) THE ENGINEER OF RECORD IS TO VIEW THE INFRASTRUCTURE WORK AND
PROVIDE A LETTER OF ACCEPTANCE TO THE COUNTY BUILDING DEPARTMENT.
10) GEOTECHNICAL OBSERVATION REPORT IS REQUIRED AT FOOTING INSPECTION
INCLUDING STRUCTURAL FILL PLACEMENT AND COMPACTION, 2000 PSF.
11)ANY WATER SUPPLYTHAT FEEDS A FIRE SUPPRESSION SYSTEM OR FIRE
HYDRANTS IS TO BE INSPECTED BY THE FIRE MARSHAL FOR THAT FIRE DISTRICT
PRIOR TO BACKFILLING ALONG WITH THE WATER PROVIDER.