S C O P E O F W O R K
Project: Aster Units
Date: March 6, 2025
Budget Price: (58 Units) $1,160,000.00
INCLUSIONS:
Fan coil system with heat pump, refrigeration piping, and controls (super high efficiency)
Complete ductwork system insulated
Exhaust Fans
ERV
Dryer Boxes and dryer venting with fire wrap
Electric Heaters
Diffusers, Registers, and grilles
Radiation dampers
Exclusions:
Condenser Pads
Line voltage electrical
Boiler or Water heater flues
Framing penetrations
Any item not specifically listed above
Roof patching
Test and Balance
Gas Pipe and condensate pipe
RESPECTFULLY SUBMITTED,
Max Winward
Estimator
Quote is valid for 15 days, if we don’t have a contract, we reserve the right to adjust the quote to the current vendor pricing.
The below items will be added to each contract we sign. We will provide a number for the storage of the material and equipment if that option
is desired.
With the current volatile pricing of materials and equipment, and the extended lead times of most materials and equipment, to maintain the
pricing of this quote we would need to order the equipment within 30 days of the bid. This means we would need approved submittals back so
that we can release the order. If this is the case, we would need to add additional storage fees (warehouse rental cost, labor to unload and
reload the materials, and freight/ shipping) for storing the equipment and then getting it to the jobsite for the storage site. Which means we
would need to be paid for the equipment or charge additional interest and other fees if the owner doesn’t want to pay for it. The second
option would be for the owner to release the equipment when it would be needed onsite, but the owner would be responsible for all price
increase on all material and equipment. We would provide the original quote and the revised quote in the change order.
With the current volatility in availability of materials and equipment, items that were specified may not be available at the time of purchase or
may have extended lead times. We reserve the right to make modifications to the brands or models of equipment that is available. We will
again send the original quote for that material or equipment with the pricing of what available material or equipment is with a cut sheet for
owner approval.
S C O P E O F W O R K
Project: Aster Clubhouse
Date: March 6, 2025
Price: $ 59,251.00
INCLUSIONS:
1-fan coil system with heat pump, refrigeration piping, and controls
Complete ductwork system insulated
1-Exhaust Fans
1-ERV
Diffusers, Registers, and grilles
Test and Balance
Exclusions:
Condenser Pads
Line voltage electrical
Boiler or Water heater flues
Framing penetrations
Any item not specifically listed above
Roof patching
Gas Pipe and condensate pipe
RESPECTFULLY SUBMITTED,
Max Winward
Estimator
Quote is valid for 15 days, if we don’t have a contract, we reserve the right to adjust the quote to the current vendor pricing.
The below items will be added to each contract we sign. We will provide a number for the storage of the material and equipment if that option
is desired.
With the current volatile pricing of materials and equipment, and the extended lead times of most materials and equipment, to maintain the
pricing of this quote we would need to order the equipment within 30 days of the bid. This means we would need approved submittals back so
that we can release the order. If this is the case, we would need to add additional storage fees (warehouse rental cost, labor to unload and
reload the materials, and freight/ shipping) for storing the equipment and then getting it to the jobsite for the storage site. Which means we
would need to be paid for the equipment or charge additional interest and other fees if the owner doesn’t want to pay for it. The second
option would be for the owner to release the equipment when it would be needed onsite, but the owner would be responsible for all price
increase on all material and equipment. We would provide the original quote and the revised quote in the change order.
With the current volatility in availability of materials and equipment, items that were specified may not be available at the time of purchase or
may have extended lead times. We reserve the right to make modifications to the brands or models of equipment that is available. We will
again send the original quote for that material or equipment with the pricing of what available material or equipment is with a cut sheet for
owner approval.
S C O P E O F W O R K
Project: Aster Units
Date: March 6, 2025
Budget Price: (58 Units) $1,160,000.00
INCLUSIONS:
Fan coil system with heat pump, refrigeration piping, and controls (super high efficiency)
Complete ductwork system insulated
Exhaust Fans
ERV
Dryer Boxes and dryer venting with fire wrap
Electric Heaters
Diffusers, Registers, and grilles
Radiation dampers
Exclusions:
Condenser Pads
Line voltage electrical
Boiler or Water heater flues
Framing penetrations
Any item not specifically listed above
Roof patching
Test and Balance
Gas Pipe and condensate pipe
RESPECTFULLY SUBMITTED,
Max Winward
Estimator
Quote is valid for 15 days, if we don’t have a contract, we reserve the right to adjust the quote to the current vendor pricing.
The below items will be added to each contract we sign. We will provide a number for the storage of the material and equipment if that option
is desired.
With the current volatile pricing of materials and equipment, and the extended lead times of most materials and equipment, to maintain the
pricing of this quote we would need to order the equipment within 30 days of the bid. This means we would need approved submittals back so
that we can release the order. If this is the case, we would need to add additional storage fees (warehouse rental cost, labor to unload and
reload the materials, and freight/ shipping) for storing the equipment and then getting it to the jobsite for the storage site. Which means we
would need to be paid for the equipment or charge additional interest and other fees if the owner doesn’t want to pay for it. The second
option would be for the owner to release the equipment when it would be needed onsite, but the owner would be responsible for all price
increase on all material and equipment. We would provide the original quote and the revised quote in the change order.
With the current volatility in availability of materials and equipment, items that were specified may not be available at the time of purchase or
may have extended lead times. We reserve the right to make modifications to the brands or models of equipment that is available. We will
again send the original quote for that material or equipment with the pricing of what available material or equipment is with a cut sheet for
owner approval.